"for providing all labour and small tools necessary to offload, check, distribute and fix steel reinforcement on the above contract from your commencement on this project on9th June 2003 ."
"The above rates are fixed for the duration of our works. Valuations will be weekly and subject to 5% retention for a period of six weeks from your Commencement Date and will then be twice monthly, subject to 5% retention."
"2. The Contract provided for the deduction and retention at 5%. There was no express provision for the release of such retention. 3. PCH have failed to repay any or all orof the retention. As a consequence, a dispute exists as to the method and timing in which the retention should have been repaid… 6. The Adjudicator is asked to decide that the retention should have been repaid by reason of an implied term and what that term shall be. 7. The Adjudicator is asked to decide the final dates or date that the retention should have been repaid. 8. The Adjudicator is asked to decide that the total retention of£66,628.50 or such other sum as the Adjudicator shall decide is to be repaid forthwith… 10. The Adjudicator is asked to decide that the responding party weare liable for the Adjudicator’s fees and expenses."
“5.3. It is to be inferred from paragraph 16 that PCH issued 111 certificates without once checking that the total being certified was correct. These 111 presumably were prepared by Mr McGann and authorised by Mr Wood …if this is correct then it would appear that PCH are author of their own misfortune by reason of their mismanagement and incompetence …5.10 Two possible conclusions may be drawn from Mr McGann's statement:- 1. That he has been either grossly negligent or grossly incompetent having overvalued the work on the Wembley contract by over £¼ million at 2005 values. Or 2. That his revaluation is a complete fabrication. Whichever of the above is correct and Mr McGann having been employed by PCH for 8 years suggests that he is not regarded as being incompetent, the Adjudicator must find Mr McGann's evidence unreliable and reject it." In Paragraph 5.6 in a chapter headed "The Decisions Requested by P.C. Harrington”, Harrington stated as follows: “The Adjudicator is asked to decide the amount of the final accounts under the Contract and from which to the side the amount of retention, if any, becoming due to Tyroddy.”
“THE DISPUTE 8. The Notice of Adjudication states that:- " PCH have failed to repay any or all of the retention withheld. As a consequence a dispute exists as to the method and timing in which the retention should have been repaid. " 9. The Referral specifically requests my decision(s) on the implied term governing when a. retention should be paid; b. The final date(s) of payment; c. the sum that is payable forthwith; d. the interest due; and e. that the Responding Party is liable for my fees and expenses… MY DECISION 14. I decide that the retention should have been repaid in accordance with an implied term of half of the retention monies should have been paid at completion of the subcontract works and the remainder 12 months later. 15. I decide that the final dates of payment were:14 June 2006 for the first moiety; and14 June 2007 for the remainder. 16. I decide that the total retention of£66,628.50 is to be paid forthwith by PCH to TCL… REASONS 22…My reasons follow. 23. The matters to be considered in my Decision include:- • Does a Dispute exist? • Was the matter resolved by a Settlement Agreement? • What is the Dispute?... • What is the correct quantification of Retention? • To whom does the Retention along? • What is the purpose of Retention? • When is retention due for release?... • Is set-off allowed under this contract claims on another contract?... 27. The dispute, as described in the 'Notice of intention to refer a dispute to adjudication' concerns the release mechanism for the retention monies held on this contract in the sum of "…£66,628.50 ”
“60. In general terms, absent any jurisdictional objections, I consider that if an adjudicator is appointed and neither party makes a contract with the adjudicator, the parties by participating in the adjudication and thereby requesting the adjudicator to act, enter into a contract with the adjudicator who acts in that capacity as a result of that request. Such a contract would be formed by conduct. There would, I consider be implied terms that the party would be liable to pay the reasonable fees and expenses of the adjudicator and would be jointly and severally liable with the other party to do so. There would also, I consider be an implied term that the adjudicator would act in accordance with the terms of the Adjudication Agreement between those parties. 61. In principle, I can see no reason why the position should not be similar where only one party makes a contract with the adjudicator but the other one does not. In those circumstances, the party who does not make a contract but participates in the adjudication thereby requests the adjudicator to act and there is a contract made by conduct with the adjudicator who acts in that capacity as a result of that request. There would, similarly be implied terms that the party would be liable to pay the reasonable fees and expenses of the adjudicator, that the party would be jointly and severally liable with the other party to make payment and that the adjudicator would act in accordance with the terms of the Adjudication Agreement between those parties… 63. Whilst the position as set out above would apply where there is no jurisdictional issue, as I have stated above, such issues are frequently taken and some succeed. What then is the position? It seems to me that where a party wishes to raise a jurisdictional argument, as has now become common in adjudications, it has one of two options. 64. First, it can make an assertion of lack of jurisdiction and withdraw, taking no further part in the adjudication proceedings and leaving the adjudicator and the other party to proceed at their risk. It might then seek an urgent declaration as to jurisdiction from the court or seek to challenge any decision on the grounds that the adjudicator had no jurisdiction. In such circumstances in the absence of any agreement with the adjudicator, there would be no request for the adjudicator to do anything and it would, in my judgment, be difficult to make that party liable for the fees and expenses of the adjudicator… 71. If, however, a party has participated in the adjudication process, albeit without prejudice to its contention that the adjudicator did not have jurisdiction, then in principle by participating and thereby requesting the adjudicator to adjudicate on the dispute I consider that the party will generally be liable for the reasonable fees and expenses of the adjudicator on the same basis as set out above. 76. In this case it is evident that Halliwells took the second route which I have identified above. They asked the adjudicator to withdraw but, in the alternative asked him to adjudicate the merits, albeit reserving the position on jurisdiction. In doing so, I consider that they asked the adjudicator to proceed and carry out work and, in my judgment, whatever the correct position on jurisdiction, there was an acceptance by Halliwells that, if the Adjudicator rejected the jurisdictional argument, he would carry out work in dealing with the merits which would involve considering the arguments of both sides. The Adjudicator then rejected the jurisdictional argument and proceeded to consider the merits, including Halliwells' arguments. 77. In such circumstances, the Adjudicator proceeded both in compliance with the request of Halliwells and pursuant to the agreement with ISG. In relation to Halliwells the adjudicator proceeded at their request and did so without any express agreement as to fees. I consider that, as submitted by Ms Monastiriotis, the request from Halliwells and the fact that the Adjudicator proceeded with the adjudication gave rise to a contract formed by conduct with an obligation by Halliwells to pay the Adjudicator's reasonable fees and expenses. 78. If that be wrong or if, in a particular case, the matter could not be characterised in terms of a contract, I consider that Ms Monastiriotis would be correct in her submissions that the principles identified by Lord Steyn in Banque Financiere de la Cite v Parc (Battersea) Ltd[1999] 1 AC 221 at 227 apply. First, a responding party such as Halliwells has benefited or been enriched by having a decision on the merits which it can seek to rely on if it wishes. Secondly, that enrichment was at the expense of the adjudicator who spent time and incurred cost in dealing with Halliwells' submissions and the arguments raised. Thirdly, that enrichment was unjust where a party accepts the benefit of the adjudicator's services without payment. Fourthly, there are no specific defences to the payment of the fees in this case.”
“3. The scheme apparently implicitly confers on the adjudicator power to apportion his fees and to decide who should pay the apportionment. The adjudicator has done so on the basis of all the work that he carried out. However in the light of my decision [on jurisdiction and severability] it is clear some of that work was unauthorised as it was beyond his jurisdiction and accordingly the defendant cannot be liable for it. Only the party that sought adjudication is liable for the fees, expenses and costs incurred by asking for a decision which the adjudicator had no authority to make and to which it was not entitled under the contract and which in breach of contract it sought…”
“The term ‘judgement in rem’ has been judicially described as ‘a specialised and somewhat misleading term of art limited to judgements concerned with status’. A judgement in rem may be defined as the judgement of the court of competent jurisdiction determining the status of the person or thing, for the disposition of the thing, as distinct from a particular interest in it of a party to the litigation. Apart from the application of the term to persons, it must affect the subject matter of the proceedings in the way of condemnation, forfeiture, declaration of status or title, or order for sale or transfer.”
“An English decision which affects a disposition of the thing order determines its status is conclusive in rem, four, or against any member of the English public. An order setting aside an alienation of property to defeat creditors or a spouse is in rem. A decision can only operate in rem if the thing was within the territorial jurisdiction of the court…”
“(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section… (2) The contract shall— (a) enable a party to give notice at any time of his intention to refer a dispute to adjudication; (b) provide a timetable with the object of securing the appointment of the adjudicator and referral of the dispute to him within 7 days of such notice; (c) require the adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred; (d) allow the adjudicator to extend the period of 28 days by up to 14 days, with the consent of the party by whom the dispute was referred; (e) impose a duty on the adjudicator to act impartially; and (f) enable the adjudicator to take the initiative in ascertaining the facts and the law. (3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined… (4) The contract shall also provide that the adjudicator is not liable for anything done or omitted in the discharge or purported discharge of his functions as adjudicator unless the act or omission is in bad faith, and that any employee or agent of the adjudicator is similarly protected from liability. (5) If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply.”
“13. The adjudicator may take the initiative in ascertaining the facts and the law necessary to determine the dispute, and shall decide on the procedure to be followed in the adjudication. In particular he may— (a) request any party to the contract to supply him with such documents as he may reasonably require including, if he so directs, any written statement from any party to the contract supporting or supplementing the referral notice and any other documents given under paragraph 7(2), (b) decide the language or languages to be used in the adjudication and whether a translation of any document is to be provided and if so by whom, (c) meet and question any of the parties to the contract and their representatives, (d) subject to obtaining any necessary consent from a third party or parties, make such site visits and inspections as he considers appropriate, whether accompanied by the parties or not, (e) subject to obtaining any necessary consent from a third party or parties, carry out any tests or experiments, (f) obtain and consider such representations and submissions as he requires, and, provided he has notified the parties of his intention, appoint experts, assessors or legal advisers, (g) give directions as to the timetable for the adjudication, any deadlines, or limits as to the length of written documents or oral representations to be complied with, and (h) issue other directions relating to the conduct of the adjudication. 17. The adjudicator shall consider any relevant information submitted to him by any of the parties to the dispute and shall make available to them any information to be taken into account in reaching his decision.”