“Groundwater indicated from the site investigation activities, and subsequent instrument monitoring is summarised in Table 7.2. The groundwater observations indicate no consistent trend in water level across the site. However, generalisations may be made for incorporation in the geotechnical design, as follows: • Where encountered, groundwater bodies tend to be associated with relatively high permeability claystone bands. These tend to be of local occurrence, and it may be anticipated that the water represents perched bodies of a minor lateral extent. • The highest standing water level recorded was at c. 36.0m OD [Ordinance Datum] in RW4. This lies below the maximum extent of anticipated excavation within the works, but may affect pile design. On the basis of groundwater observations to date, it is concluded that groundwater will not significantly affect near surface excavations or the design of shallow foundations. Local bodies of perched near surface water should be anticipated during construction, although these are likely to be of minor extent and drain rapidly as works progress. Piles should be designed for a water table at 38 m OD (i.e. 2 metres above the highest recorded level). The assessment of the stability of slopes should be undertaken incorporating a suitable ru value to allow for local perched water conditions, and infiltration into the slope…”
“The Contractor shall be deemed to have satisfied himself as to, and to adopt and accept responsibility for, any design contained in and/or reasonably to be inferred from the Employer’s Requirements as though such design had been carried out by or on behalf of the Contractor. In particular, but without prejudice to the generality of the foregoing, the Contractor hereby warrants:- (i) that the design contained in and/or reflected by the Employer’s Requirements and/or design prepared by or on behalf of the Contractor does, or as the case may be, will meet in all respects the requirements of the Contract. (ii) that he will exercise all reasonable skill care and diligence in the design, construction, testing and commissioning of the Works and all parts thereof.” (i) that the design contained in and/or reflected by the Employer’s Requirements and/or design prepared by or on behalf of the Contractor does, or as the case may be, will meet in all respects the requirements of the Contract. (ii) that he will exercise all reasonable skill care and diligence in the design, construction, testing and commissioning of the Works and all parts thereof.”
“The depot site is adjacent to a residential area and the contractor shall ensure that any disturbance from construction activity be kept to a minimum. Particular attention should be made regarding noise during the construction of the works as well as minimising light pollution to the adjacent properties (e.g. Low level lighting in lieu of tower/mast lighting)." It went on in relation to "Depot Operation" at Paragraph 2.3: “The general direction of Depot operation will be from South (London end) to North (Country end). The layout, signalling and design must allow for bidirectional running should the depot be used in the North to South direction. The carriage wash is to be used for cleaning operations in the South to North direction only but must allow unrestricted travel in the reverse direction….”
“We are proposing to use timber permacrib walls for a project at Wembley Depot (LUL). I believe that you may have helped us with this when the project was tendered approximately one year ago. When the project resurfaced the client mentioned a little unease with timber crib walls, although this probably was mainly due to unfamiliarity with the system. I believe that you have helped Andy Kenyon of Mowlem by issuing examples of crib walling in a rail environment. We need to make sure that the client is completely happy with this proposal in order to progress. We believe that the client may have spotted the 6m height limit in the BBA Certificate. To this end it would be extremely useful to get a preliminary design to back up the proposal, or at least a statement confirming that the proposal is a workable solution. We would be extremely grateful if you could assist us in this, with time as always being critical. I have attached a section through the proposed wall and a copy of the soils data for the site …”
“Organisation proposed to be responsible for the detail of design: Robert West Consulting Ltd. Design of specialist retained walls by specialist contractor, with a review by Robert West Consulting Ltd. Robert West Consulting Ltd will ensure that the specialist designers have addressed slip circle issues adequately.” (c) Section 4 identified as one of the "Design Standards" BS 8002 which deals with Earth Retaining Structures. (d) Section 5 identified various Geotechnical Considerations including soil properties which were to be used for analysis which were "based on URS Report 49810-007”. (e) Section 6 set out a "Design Statement" which included at Section 6.2 "proposed earth pressure coefficients" to be used for earth retaining elements" Section 6.5 provided as follows: “Compliance with the AIP: the AIP (Form A) will be used as the basis of design.” (f) Section 7 of the document dealt with the subject of accompanying documents and drawings: Section 7.1 specifically referred to the “Site Investigation Report No. 49810/007 by URS, dated September 2003.”
“Further to our meeting of 11 March, and your subsequent provision of sections and site investigation, we have undertaken a basic design at each section, and consider that a soil nailed solution and geotextile facing, given the site constraints, is historically acceptable for a 120 year design life. We do not consider that a crib wall solution will provide for this life expectancy, since it cannot provide long term resistance to the movement effect of deep-seated slope failure …”
“Further to the recent site meeting…we have carried out a preliminary design appraisal of your retaining wall requirements at the above development based on the following:-… Wall 2 (Between chainages 8210.0.0-8480.0m) Based on the use of soil nailing techniques to provide both the short and long-term stability for the strength and embankment. The existing levels are reduced in a series of stages, at each stage, the excavated face is stabilised prior to reducing levels to the next stage. We note from the Engineers that the excavated face is proposed to be clad in a geotextile facing, however, in order to prevent localised ‘sloughing’ and face instability between the nail plates we would discourage the use of a geotextile alone and for this reason have therefore also included with our quotation for the supply and installation of structural facing mesh… Wall 4 (Between chainages 8630.0-8700.0m) As Soil Nailing Wall 2 above… We have based our preliminary design proposals and Quotations on the information provided. Details of our design proposal are as stated in our Preliminary Technical Appraisal attached hereto. The Site investigation shows that the in-situ soils consist of stiff LONDON CLAY. These soils have potentially poor effective shear strengths. In order to provide a ‘safe’ temporary earthworks profile during wall construction and to minimise the earth pressures applied to the wall and thereby achieve the most cost-effective solution we have assumed that the in-situ soils will be removed back to a minimum 60° profile. The resulting void, to the rear of the wall, should be filled in accordance with the Permacrib backfill specification.”
“The proposal seems fine. Comments as below: Soil Nailing-Option B seems sensible given small cost difference… Programme-allow at least one week for RWC to check Phi design and coordinate interfaces with Phi.”
“… at present we have based our design on the soil parameters specified in the site investigation. Although these seem reasonable it would be prudent to carry out the additional testing in line with the site investigation recommendations to determine the long term design parameters for the in-situ material. We will carry out proof load testing of the soil nails to confirm the nail design assumptions are correct, but we will need confirmation of the soils …”
“…soil parameters differ slightly for our design, see our calculations at section 3.0. Phi reasonable parameters (φ = 27°,c’ = 4kPa, ru = 0.15) Phi worst credible parameters (φ = 23°, C = 3kPa, ru = 0.2) …”
“…our calculations are based on similar parameters to the SI but not those exact ones. We took a slightly more optimistic approach on stress parameters, but a much more pessimistic approach on the water regime. However, if we rerun the design again with the SI’s worst credible values of Ø = 21 and C =2kN/m2 our design still exceeds an FOS of 1.2. However, with these low parameters, and having re-analysed the SI with respect to water, we have used a ru of 0.05. Thus we confirm the current design can meet the AIP’s requirements…”
“We have used the soil parameters as specified in the site investigation, and have not considered the possibility of existing slip surfaces ...” (ii) At Paragraph 2.1.2, within Section 2 – design reference, Phi identified the site investigations upon which the calculations were based. Phi also identified, at Paragraph 2.1.3, that these calculations were also based upon Form A (Approval in Principle) which was dated5 March 2004 and drafted by RWC. (iii) In the section of the Calculations dealing with Design Parameters Section 3.2) Phi specifically identified that the work relied on by them was the URS Report. (iv) Section 3.3 of the Calculations dealt with “soil nail design parameters” and the ru value is specifically identified by Phi as 0.05. The covering letter stated: “...we have as requested based our design on the soil parameters as specified in the Approval in Principle ...”
“i) We have always been under the impression from various site meetings that aesthetics were not the highest priority for the design of the stabilisation works ...” (ii) We confirm that the design of the facing is 120 years... (iii) We believe the factor of safety of 2.0 in this instance is inappropriate. We assume you are referring to CP2:1951 earth retaining structures, which has been superseded by BS8002:1994. This latest code is a limit state design using partial factors to achieve a factor of safety of greater than 1.1. We are following general working practice, and in accordance with BS6031, achieving a minimum factor of safety of 1.3 ... (iv) The three types of construction are as required by yourselves due to site conditions”
“Whereas:- (1) The Contractor has entered into a contract ("the Main Contract)" particulars of which are set out in the First Schedule. (2) The Consultant having been afforded the opportunity to read and note the provisions of the Main Contract…has agreed with the Contractor to execute the Design described in the Second Schedule ("the Design") upon the terms hereinafter appearing, and to act as the Designer if so defined under the Main Contract.”
“A The Design Civil Engineering Works (1) Upon award of the Main Contract, develop the outline proposals to a fully detailed scheme. This will include: (a) Advise on further site investigations to verify ground (b) Building substructure (including retaining walls)… (f) External works including building and track drainage (belowground) Civil Engineering Works (a) Advise on further site investigations to verify ground (f) External works including building and track drainage (belowground) (2) Provide working drawings and specifications for the above… (4) Attendance at design team meetings (assumed 6 no.)… Once construction has commenced the following brief: (1) Allowance for technical support including approval of fabrication drawings (2) Attendance at site meetings (assumed 10 no.) (3) Site visits (assumed 10 no.)…”
“We write to inform you that we have experienced a failure in the soil nail wall between the depot building and the Country End of the site. We have attached initial reports undertaken by Phi Group and our internal design manager which provides you with more detailed information. We believe the failure may be the result of inadequate design. As lead designer for the project we would therefore advise that you notify your insurance company accordingly. Phi Group are in the process of putting forward remedial work proposals and assessments of the long term stability of the wall. We will keep you advised of all future developments.”
“Whether this should/could have been predicted at the design stage will be a matter of debate. In any event Phi Group need to demonstrate that the slope has an adequate factor of safety with lower operating parameters. Consideration should be given to both the residual state (c’= 0, phi = 12) and a fully softened state (c’ = 0, phi = 18 to 20).”
“I think we know where we are and where we have got to get to. We know we have a failure(s) of the cut slope and that future failures can not be ruled out by any party. We need to put in place a design, design check and approval of remedial works and we then need to install them before handing the sidings over to the client for his safe use. The question is how do we get from where we are to where we want to be. Perhaps Jason [Smith of Carillion] can give us a lead here. Which parties are going to be involved? I assume the contract as setup should deal with this. Phi I assume will need to be the designers of the remedial works. Will Robert West need to be the checkers? Do Laing Rail sign off any design check certificates? As with all the other main elements of the permanent works designs the principles of the design first need to be agreed (Form A or AIP). The original design assumptions I suggest now need to be revisited and agreed. If additional SI [site investigation] is required to achieve this then that will also need to be designed, agreed and carried out. At this stage I assume we…or CL associates are not required to do any number crunching but only to review that the above procedures are being followed and that the correct design brief, design assumptions and methods are being employed… The starting point of any design is the design brief. We need to know our position as to whether our original (or any revised) instruction (brief) was correct. Are they prepared to design the remedial works to the same brief or do they now require us to instruct them to work to make changed brief? (80/90° slope angles and are now known fact that pre-existent slips are present).”
“Thank you for your letter of22 November 2005 relating to a problem you have encountered with some of the soil nailing on site. We would like to remind you that the soil nailing design and installation was done under a separate design contract between Mowlem and Phi Group. Robert West Consulting were not a party to this contract. Any discussions on costs arising from this alleged failure should be addressed to the contracting parties (being Mowlem and Phi Group). Further it is our understanding, from the submitted correspondence, that Phi Group are accepting responsibility of the remedial works to the wall, in which case, we are unclear as to what additional costs you refer to.”
“Please find enclosed a report prepared by Phi on the retaining wall failures. My understanding of the report suggests that works are required to some of the RW designed external works in order to facilitate the repairs to the walls. I would request that Robert West provide their response to this report and confirm their approval to the remedial measures proposed. Could you please provide this as a matter of urgency.”
“A basic analysis of the old slope at around 22 deg does not show an initial failure outcropping the crest as far back as we are trying to demonstrate that once the first failure has happened then further failures will ‘progress’ back into the slope with time. I have added further comment in the report to explain this. I have also clarified the position with regard to Alan’s query on pore pressure assumptions. With regard to Robert West comments I have annotated their e-mail in red below...”
“Comments are as follows: • The recommendation to areas 1 & 2 do not seem very robust. There is no statement confirming whether the nails have moved or not (only that theoretically they are O.K.) We would expect a survey of the nails to check if any are out of place, which would signify pullout. The fronts of the nails have moved downwards with the face and this is stated. We do not believe that there has been any pull-out and we have added this point to the report. We could monitor the nails for pull-out from here on but we have no reference to make any meaningful measurement of pull-out since construction. • There is no mention/justification of the existing steel plate remedial as one of the final recommendations. They looked to be very much a temporary work solution. As the mesh has already sheared in this area, we are surprised by the statement on the mesh around plates would expect some upgrading here. As the mesh has already sheared in this area, we are surprised by the statement on the mesh around plates and would expect some upgrading here. The steel plates may look a little untidy in Area 2 but they are extremely competent structurally, but we could extend the shotcrete across Areas 1 and 2 which would give more continuity of appearance, avoid the need to replace the stone face and enhance further the structural capacity. We have explained why the mesh is adequate in the report. In those areas where the mesh is damaged we could replace it with a higher spec but we obviously do not want to replace all the upper level rear mesh unless it is necessary. • Where a shotcrete solution is specified, some form of filter drain would also be required. Agreed. • Pre-existing slips-Phi should be aware of this possibility and account for it within their design especially after encountering a slip during construction. We are accounting for them in the remedial work designs. • Crack sealing-This is not really viable as it could occur anywhere. It is implied within the report that hydrostatic pressure from tension cracks had not been taken into account for the design. We would query the validity of ignoring this effect in calculations. We don't believe that significant tension cracks exist with the soil being put largely into compression by swelling and the downward movement of the failure wedge reacting against the face and nails. We do have ‘in contact’ failure planes which will weaken if water is able to percolate down them. This is accounted for in the design but any measures that can be taken to reduce this effect would be wise. • There is a durability issue with the size of stone used in the facing. Whilst this does not affect wall stability, it may well come up as an issue with Laing Rail again following the other issues. We think that the staggered extra layout of the mesh is the best solution year. • With regard to changing the design of other elements with in our design remit, the only real suggestion in the report is the LUL cable troughs. It is not possible to effectively seal these, and I do not imagine it would be possible to move the troughs. In addition, the pathway generally slopes down the side, and water would drain down the slope (along the line of the troughs) before permeating into the clay material. Also refer to crack sealing above. As far as the practicality of sealing them goes we can't comment. • No mention is made of lifespan of the structure after the remedial works this was an important issue at the time of design, and Phi need to be very clear on proposals for this. Providing a remedial solution equal in durability to the original scheme is our intention and we have included a comment about this in the revised report.” • The recommendation to areas 1 & 2 do not seem very robust. There is no statement confirming whether the nails have moved or not (only that theoretically they are O.K.) We would expect a survey of the nails to check if any are out of place, which would signify pullout. The fronts of the nails have moved downwards with the face and this is stated. We do not believe that there has been any pull-out and we have added this point to the report. We could monitor the nails for pull-out from here on but we have no reference to make any meaningful measurement of pull-out since construction. • There is no mention/justification of the existing steel plate remedial as one of the final recommendations. They looked to be very much a temporary work solution. As the mesh has already sheared in this area, we are surprised by the statement on the mesh around plates would expect some upgrading here. As the mesh has already sheared in this area, we are surprised by the statement on the mesh around plates and would expect some upgrading here. The steel plates may look a little untidy in Area 2 but they are extremely competent structurally, but we could extend the shotcrete across Areas 1 and 2 which would give more continuity of appearance, avoid the need to replace the stone face and enhance further the structural capacity. We have explained why the mesh is adequate in the report. In those areas where the mesh is damaged we could replace it with a higher spec but we obviously do not want to replace all the upper level rear mesh unless it is necessary. • Where a shotcrete solution is specified, some form of filter drain would also be required. Agreed. • Pre-existing slips-Phi should be aware of this possibility and account for it within their design especially after encountering a slip during construction. We are accounting for them in the remedial work designs. • Crack sealing-This is not really viable as it could occur anywhere. It is implied within the report that hydrostatic pressure from tension cracks had not been taken into account for the design. We would query the validity of ignoring this effect in calculations. We don't believe that significant tension cracks exist with the soil being put largely into compression by swelling and the downward movement of the failure wedge reacting against the face and nails. We do have ‘in contact’ failure planes which will weaken if water is able to percolate down them. This is accounted for in the design but any measures that can be taken to reduce this effect would be wise. • There is a durability issue with the size of stone used in the facing. Whilst this does not affect wall stability, it may well come up as an issue with Laing Rail again following the other issues. We think that the staggered extra layout of the mesh is the best solution year. • With regard to changing the design of other elements with in our design remit, the only real suggestion in the report is the LUL cable troughs. It is not possible to effectively seal these, and I do not imagine it would be possible to move the troughs. In addition, the pathway generally slopes down the side, and water would drain down the slope (along the line of the troughs) before permeating into the clay material. Also refer to crack sealing above. As far as the practicality of sealing them goes we can't comment. • No mention is made of lifespan of the structure after the remedial works this was an important issue at the time of design, and Phi need to be very clear on proposals for this. Providing a remedial solution equal in durability to the original scheme is our intention and we have included a comment about this in the revised report.”
“I consider Robert West’s query is valid and in many respects they reflect my earlier comments to Alan [Sowden]. Phi have considered most aspects in their report and the proposed solution needs to be adopted consistently along the whole length of the West section of the wall, for both technical and aesthetic reasons. I am still concerned over the amount of potential movement that may occur in the soil nailed slope between nails leading to a visually if not structurally unsatisfactory situation. Based on Phi’s analysis I agree that the overall safety of the slope seems assured, however, the report still does not discuss their reasoning behind using ru = 0.05 (which is only a nominal level of pore pressure). There needs to be clear evidence for the long term pore pressure regime assumptions to verify that the slope is expected to remain stable. The control of surface water and potential ingress of water into the slope is vital if long-term problems are to be avoided.”
“We are unable to accept your understanding of the Contractual position with regard to the liability for the failure of the Soil Nailed retaining wall at the Wembley Depot. We note your comments with regard to the requirements of the Contract. We would wish to reinforce our understanding of the Contract in respect to these works. • The Subcontract requires Phi to design and construct a soil nailed wall with a minimum design life. • The Pre-tender minutes required Phi to ensure that the design took account of slip circles which were known about at the time of tender. The existence of counterfort drains within the embankment also demonstrated that the slope had been the subject of some instability. • Phi Group encountered a slip during the early stages of the construction of the works. Phi Group’s own drawings state that if ground conditions are found to be different to those anticipated by the design then the design would be reviewed. This procedure was not followed and resulted in the whole wall being constructed to the original design. • Phi Group are responsible for designing a wall that suits the ground conditions found on the site. It is contended that the design of the wall does not suit the conditions. We have determined the Mowlem costs associated with the original remedial actions carried out by Phi Group and enclose our calculation sheets… As stated in our meeting we wish to carry out the remedials for the wall in cooperation with both companies and seek to minimise the cost as far as is practical.”
“These comments are based on the second visit to site on17 January 2006 , CLA analysis of the current slope design…and an initial assessment of Phi Group’s Proposals for Remedial Works issued on3 February 2006 . The site visit on17 January 2006 revealed further evidence of movement in the soil nailed slope both at lower and higher levels in the slope… At the request of Mowlem, CLA had carried out an analysis of the soil nailed slope using an in-house program, SNAILS. For the purpose of analysis CLA adopted the section at CH 8330 which had a factor of safety of 1.3 as recorded in the Phi Group Report [of]15 October 2004 …The CLA analysis gave a factor of safety of 1.26 which is similar to that indicated by Phi Group and therefore if the design parameters are representative the slope should be stable with the current levels of soil nail reinforcement. However, if lower soil parameters more typical of those used to assess the long-term stability of London Clay slopes and factors of safety approach 1.0 and possibly lower. We calculate factors of safety of 1.0 for c´= 0, phi = 20. Phi Group have re-analysed this section of the as-built conditions and calculate a factor of safety of 1.41 for c´ = 0 kPa, phi = 21. On this basis CL are satisfied that there is an adequate factor of safety for the slope in the long term.. We consider that softening of the near surface clay is inevitable and this would lead to problems with the gravel filled facing and "quilting" of the ground between soil nails… We consider that the soil nailed slope (both sides of the maintenance shed) should have a stiffer facing capable of resisting bulging between the soil nails and effectively transmitting loads back into the slope… It is our opinion that Phi Group should not have relied on the reported peak design soil parameters alone for their design but as experienced geotechnical practitioners should at least have considered the possibility of softening of the clay and a reduction in strength. It is common knowledge that London Clay softens with time as it takes up water after excavation with consequent loss of c´ and phi. Such evidence has been described in many papers, eg Skempton’s Rankine Lecture…”
“Concerns were raised however regarding the durability of the existing rear mesh and its ability to support the stone facing over the full term of the design life. We wish to place on record that we believe this to be an entirely separate matter from dealing with the structural problems that are evident on site. This mesh has always formed a part of the stone facing solution, the design and specification of which was open to question through the whole design process. We believe that it is inappropriate to raise this issue now and cause further delay to the execution of the remedial works when reports from site are confirming the further deterioration of the cutting…”
“Please find attached our proposals for dealing with the water seepages observed on the London End wall. As discussed we believe that the observation of wet patches on the clay face does not indicate the presence of pre-existing failure planes as found at the Country end and that the previous conclusion of all parties in this respect remains valid. However water pressure was not taken into account in the original facing design because neither the AIP nor the soils information provided gave any indication of the need to do so…”
“RWC made the correct design assumptions for height of the water table and water pressure in its own design of the retaining wall for the Depot (and assumed it was about 4m above the toe of the slope). However, RWC failed to notice, or did notice but failed properly to consider the effect of, Phi’s unrealistic and negligent assumption in respect of water pressure and the value of ru in the Phi calculations.”
“RWC correctly considered in its own design for the retaining wall of the Depot that weathered London Clay was likely to be present at the site, and assessed in that design that there was likely to be weathered London Clay down to a depth of 2.5m below the surface. However, RWC failed to notice, or did notice but failed properly to challenge and/or consider the effect upon Phi’s design, that Phi had assumed that the presence of relic shear planes could be ignored. Relic shear planes are only found in weathered London Clay, and a specific difference in characteristics of weathered London Clay, and un-weathered London Clay, is the likely presence of relic shear planes in the former. The presence of relic shear planes would not have been ignored by a competent designer exercising reasonable skill and care.”
“as part of their ongoing duty as a reviewer of Phi’s design, RWC ought to have taken an interest in what was going on site during their periodic site visits and, had they done so, would probably have discovered the slips for themselves since the retaining wall works at the depot and the soil nailing works were being carried out contemporaneously”
“Q…assuming...[RWC] had the involvement of the4 January 2005 . But in the light of the January 2005 October 2005 failures, if [RWC] were carefully reviewing the design at that stage, re-reviewing it? A Yes. Q. Should a competent careful person in RWC’s position have picked up the potential of the deep-seated problem? A. Yes they should have done, but I recognise that the failures that had occurred on site didn't suggest a deep-seated problem. Therefore, I think they would have had to have gone the extra mile to realise, you know, to reassess the deep-seated instability issues, even though they were not apparently causing a problem on site.”
“29. The judge did not direct herself in such terms with the result that she did not articulate the particular rule or question to which the causal issue was relevant. Had she approached the matter in that way she would have inevitably been referred back to her own reasons for finding breach of contract and breach of duty on the part of Carford, as set out in particular in paragraphs 43 and 47 of her judgment which my Lord has already mentioned. In the light of that conclusion - that Carford were in breach of their contractual obligations by not installing the rotisserie in accordance with the manufacturer's instructions - the issue before her was therefore in what circumstances, if any, would it be possible for a notification or warning by Carford of its own breach discharge its continuing liability for damage caused by that breach. 30. For that to be achieved, any warning would as a matter of law have to be overwhelming and plainly effective before it could excuse Carford. Carford would in effect have had to make it its own business to ensure that the breach was nullified, and have been frustrated in that attempt by a lack of response by the building owner. The judge did not look at the question in that way. She seems to have assumed that the question was simply one of a breach of chain of causation looked at in general terms and that any warning that could be sufficiently described as such would suffice for that purpose.”
“Lastly, given the seriousness of the failure and the long-term lifespan required, it may be prudent to consult an independent specialist in the field of soil nailed walls to review the proposals made. This may be the most expedient way of providing Laing Rail with renewed confidence in the soil nailed walls. Oliver [Engleback] has mentioned Jamie Standing of GCG as a recognised expert in the field…”
“(1) The Consultant shall indemnify the Contractor (2) against every liability which the Contractor may incur to any other person whatsoever and (3) against all claims, losses, demands, proceedings, damages, costs and expenses made against or incurred by the Contractor (4) by reason of any breach by the Consultant of this Consultancy Agreement…”
"Once again one finds the court emphasising the central importance of reasonableness in selecting the appropriate measure of damages … So I cannot accept that reasonableness is confined to the doctrine of mitigation. It has a wider impact …"
"The fundamental basis is thus compensation for pecuniary loss naturally claimed from the breach; but this first principle is qualified by a second, which imposes on a claimant the duty of taking all reasonable steps to mitigate the loss consequent on the breach, and debars him from claiming any part of the damage which is due to his neglect to take such steps."
"It is important to appreciate the true nature of the so-called 'duty to mitigate the loss' or 'duty to minimise the damage'. The claimant is not under any contractual obligation to adopt the cheaper method: if he wishes to adopt the more expensive method, he is at liberty to do so and by doing so he commits no wrong against the defendant or anyone else. The true meaning is that the claimant is not entitled to charge the defendant by way of damages with any greater sum than that which he reasonably needs to expend for the purpose of making good the loss. In short, he is fully entitled to be as extravagant as he pleases but not at the expense of the defendant."
"Where the sufferer from a breach of contact finds himself in consequence of that breach placed in the position of embarrassment the measures which he may be driven to adopt in order to extricate himself ought not to be weighed in nice scales at the instance of the party whose breach of contract has occasioned the difficulty. It is often easy after an emergency has passed to criticise the steps which have been taken to meet it, but such criticism does not come well from those who themselves created the emergency. The law is satisfied if the party placed in a difficult situation by reason of the breach of a duty owed to him has acted reasonably in the adoption of remedial measures, and he will not be held disentitled to recover the costs of such measures merely because the party in breach can suggest that other measures less burdensome to him might have been taken."” "
“1. (1) Subject to the following provisions of this section, any person liable in respect of any damage suffered by another person may recover contribution from any other person liable in respect of the same damage (whether jointly with him or otherwise). (2) A person shall be entitled to recover contribution by virtue of subsection (1) above notwithstanding that he has ceased to be liable in respect of the damage in question since the time when the damage occurred, provided that he was so liable immediately before he made or was ordered or agreed to make the payment in respect of which the contribution is sought… (4) A person who has made or agreed to make any payment in bona fide settlement or compromise of any claim made against him in respect of any damage (including a payment into court which has been accepted) shall be entitled to recover contribution in accordance with this section without regard to whether or not he himself is or ever was liable in respect of the damage, provided, however, that he would have been liable assuming that the factual basis of the claim against him could be established…E+W+N.I. 2 (1) Subject to subsection (3) below, in any proceedings for contribution under section 1 above the amount of the contribution recoverable from any person shall be such as may be found by the court to be just and equitable having regard to the extent of that person’s responsibility for the damage in question. (2) Subject to subsection (3) below, the court shall have power in any such proceedings to exempt any person from liability to make contribution, or to direct that the contribution to be recovered from any person shall amount to a complete indemnity…”
“Section 2(1) of the Civil Liability (Contribution) Act 1978 provides that the amount of the contribution recoverable from any person“shall be such as may be found by the court to be just and equitable having regard to the extent of that person’s responsibility for the damage inquestion…There was some initial controversy as to the proper basis of apportionment but in Downs v Chappell Hobhouse LJ made clear that: “…it is just and equitable to take into account both the seriousness of the respective parties’ faults and their causative relevance. A more serious fault having less causative impact on the plaintiff’s damage may represent an equivalent responsibility to a less serious fault which had a greater causative impact.”
“This Act…enables a just and equitable apportionment, including a complete indemnity, to be made. The tribunal is therefore required to take into account not only the respective “causative potency” of the parties’ acts and omissions towards causing the damage in question but also their relative “blameworthiness”, although the first factor will be the most important. Where the party claiming contribution has settled its liability it is still open to the party from whom contribution is sought to challenge the amount of such settlement as unreasonable and therefore not the basis on which the apportionment should be based [J Sainsbury v Broadway].”
“The courts have adopted a rule of thumb in construction cases that an architect or engineer charged with supervising a contractor should be responsible for the contractor’s poor workmanship to an extent which ranges from 20 per cent to 33 per cent, except where the supervisor had been exceptionally slapdash in the discharge of his duties, or where the contractor has a duty to warn of unsafe works.”
“As between negligent construction professionals, e g architects and engineers, the apportionment of liability will obviously turn on therelative extent of their involvement and roles in the project.”
“I now have to consider, given that I have found each defendant to be in breach of statutory duty, the question of apportionment between them. The plaintiffs are entitled to Judgement in full against both defendants but as between each other, the question of responsibility has to be apportioned by this court. I bear in mind the test of culpability and causative potency that are relevant to this issue. As to the latter, it seems to me that there is nothing between the two defendants; each of their breaches was as causative of the problem as the other. However, when one looks at the question of culpability, it does seem to me that greater culpability is shown by the breach of duty of the builder. His breach, it seems to me, was one of commission rather than one of omission, which was the nature of the breach of duty, as I found it to be, by the architects. In those circumstances, having the opportunity directly when the work was proceeding to know what was going on, the first defendant should be held the more to blame. The proper apportionment seems to me, as between the two, is sixty per cent against the builder and forty per cent against the architects.”
“I am satisfied that the learned judge applied the right tests. He considered questions of causation and culpability. I have to say that in my view other judges may have taken a more sympathetic view of the degree of culpability on the part of the architects, but…I cannot interfere with the apportionment as made by the judge.”
“If EGP were liable its share of responsibility could not be regarded as minimal. Previous decisions on contribution have to be treated with caution as each case depends on its own facts. However it is not irrelevant that in Worlock v. Saws (1982) 22 B.L.R. 66 Robert Goff L.J. said that in cases where a building inspector had been negligent the “conventional approach” was then to attribute 75 per cent responsibility to the builder and 25 per cent to the local authority…In my judgment the role of EGP in relation to the design of the fire protection of the compartment wall ought not to be regarded as higher than that of a building inspector or clerk of works. EGP's negligence was essentially a failure to warn; it was required by BM to comment, not to redesign. However BM's failure to be specific, and its subsequent failures to pursue EGP for a reply, and above all, in 1991 to pick up the deficiency in the design in my view contributed as much as the original error.”