"The following is a brief summary of the items included within the Sub-Contract Works but it is not exhaustive. The scope of the Sub-Contract Work is everything which is shown or described or can be inferred from the documents contained or referred to within this Sub-Contract Agreement together with anything which could reasonably have been foreseen generally including inter alia: 1.1 Developing the design of the Mechanical and Electrical works to suit the ongoing scheme. The Sub-Contractor shall take ownership of the design concept prepared by Hoare Lea. 1.2 Supply, delivery, off-loading of all necessary plant, equipment, materials (including all fixtures and fittings) and to provide all required labour and supervision to carry out the installation of the Mechanical, Electrical, Public Health, Plumbing Works associated Builders Works, to include but not limited to the following… Cold Water Supply including Cold Water Tanks, Booster Sets, Isolation Valves as necessary… Booster Pumps… Testing Commissioning and final Certification… Preparation and submission of fully compliant O and M Manuals…" (Emphasis supplied)
"Q: …is there any ambiguity or difficulty with the words 'free from'? A: No. Q: When it says 'metal filings', are those precisely what are produced by these processes on site that you refer to? A: Yes. Q: So in a sense Mr Newbery, it is less about a hand lens and a light source, and rather more about not letting metallic debris in there in the first place, isn't it? A: Ideally there should be no metallic debris, I agree." 6.3.2 Over-Tightening (a) Mr Newbery originally said there was no evidence of significant over-tightening but he ultimately agreed that it was "possible to cause over-tightening to cause damage to the thread while producing the tool marks seen on the incident nut"; (b) Although Mr Newbery originally suggested that over-tightening the nut would impart a pre-load which would render it more resistant to fatigue cracking, he appeared ultimately to accept that, whilst that might be true for a steel bolt, it was not true for a polymer nut like this; (c) Although Mr Newbery originally disagreed that over-tightening could cause a crack which grew over time, he ultimately conceded the point and accepted that he had not appreciated the speed at which brittle fractures could occur in this material; (d) Although Mr Newbery appeared to rely on the 200 or so visible progression ridges as indicating that the nut had been subjected to 200 or so high pressure events, he ultimately accepted Mr Cooper's explanation that up to 90% of the fatigue life of a plastic component would typically produce no progression ridges at all; (e) Although Mr Newbery originally stated that the over-tightening/debris theory could not explain the propagation or the final failure of the nut and that each would require more substantial loads than would be generated in the ordinary operation of this system, he ultimately abandoned both of those positions. 6.3.3 The Pump System and Pressure Surges 7. GMVL'S CLAIM AGAINST ESSEX ON CORE 3 8. THE CONSEQUENTIAL CLAIMS AGAINST HSE and ROBSON ON CORE 3 169. (a) Robson accepted that the over-tightening which I have found was a breach of contract. However, in connection with the debris, Robson did not accept liability, arguing that the training/instructions that they received from the manufacturer, Georg Fischer, related to the cleaning of pipe joints prior to gluing, rather than the cleaning of threads before the hand-tightening of nuts. However, that does not seem to me to offer Robson any sort of defence, given that the manufacturer's instructions about hand-tightening were available in writing, and given that precisely the same reasons for keeping the joints to be glued free from debris applied to the need to keep the thread of the nut similarly uncontaminated. As Mr Newbery, Robson's expert, confirmed, however a joint is being made, "you wouldn't want them [the particles] in there." (b) In my view, this evidence (and similar views expressed by other experts) makes clear that the damage to the nut, and therefore the risk to the joint, was wholly foreseeable, an issue not raised by Essex or HSE, but raised by Robson. Furthermore, although Mr Ter Haar QC asserted, by reference to The Heron II[1969] 1 AC 350 at 385, that the type of damage which was foreseeable as a result of the debris would only occur in a small minority of cases, and so could not be regarded as arising in the usual course of things, I consider that that submission too was contrary to the evidence outlined above. It was foreseeable that foreign material in joints may cause all sorts of problems, including consequential over-tightening and failure. That is why, amongst other things, the British Standard prohibits such contamination. 9. THE CAUSE OF THE CORE 2 FLOOD "
"As a general rule the "but for" test is a necessary condition for establishing causation in fact." "
"The classic example is where two persons independently search for the source of a gas leak with the aid of lighted candles. According to the simple 'but for' test, neither would be liable for damage caused by the resultant explosion. In this type of case, involving multiple wrongdoers, the court may treat wrongful conduct as having sufficient causal connection with the loss for the purpose of attracting responsibility even though the simple 'but for' test is not satisfied." "…the contractor cannot recover damages for delay in circumstances where he would have suffered exactly the same loss as a result of causes within his control or for which he is contractually responsible."
"Q: The reason why the air can't get into the riser is because of the presence of the NRV which you are asked to assume was present? A: Yes that is right. Q: That's why you say, in your scenario, whether the IV is opened, it would have happened anyway, and the principal reason for that, the dominant reason, is because the NRV prevents any air getting in to provide the cushion effect, am I right? A: Yes that is right. … Q: A surge arrestor has been provided and it needs to do its job. Its job is to avoid water hammer, or at least deal with it, and it is prevented from doing its job, not because the key is being switched on or off, but because there is a non return valve there and that is preventing it from letting air in. It is effectively as if you have built a riser without surge protection, am I right? A: I think I see what you are saying. I don't know that it is really for me to say which is the predominant or the main cause. The fact is that either or both of these features would have prevented the anti-surge valve from working.
"Q: As you say in paragraph 2.9(a), the non-return valve would have prevented the anti-surge valve from allowing air into the riser? A: Yes. Q: So it would have prevented the anti-surge valve from doing what it was supposed to do? A: Yes. Q: In those circumstances, at paragraph 2.9(b), you agree that the water hammer that would have occurred would probably have caused a similar core 2 leak? A: That is correct."
"Q: With the NRV present below the surge arrestor, would you agree that air cannot enter the riser through the surge arrestor regardless of whether the isolating valve was open or closed? A: I would agree with that… Q: As far as the leak is concerned, the leak is going to occur when the riser fills, isn't it? A: Yes. As a result of the fast filling of the riser and the sudden abrupt halting of the water column. Q: So would you agree that it is not occurring because the IV is there but occurring because the riser has filled? A: Yes, that is correct. Q: When the isolating valve is closed, there are two blocks on the riser, aren't there? A: Yes. Q: So far as the air entering the riser is concerned, the first block is the non return valve? A: That is correct. Q: You would confirm that as a technical matter? A: Indeed." (e) Mr Hickey's cross-examination of Mr Newbery, in which (although Mr Newbery argued that there was no demand for air because the IV was closed), he also agreed that there were two blocks on the line and that the first physical block to air getting in was the NRV. Mr Newbery also agreed that, in allowing air to come in, the first step in that process may have been to open the IV, but that would not have made any difference, because of the presence of the NRV. 184. (a) Finally on the NRV, I accept Mr Stansfield QC's proposition that, since the experts' conclusion meant that the damage would have been the same whether the IV was open or closed, 'a degree of suspicion' (as he put it) must attach to the proposition that the closed IV was the sole effective cause of the flooding. To put the point a slightly different way, there was no leak at Level 8, where the relevant NRV and the IV were located; the Level 6 IV which failed would have failed whether the Level 8 IV was open or closed. (b) It seems to me that, for all these reasons, it would be idle to suggest that the NRV was anything other than an independent and effective cause of the flooding. This is particularly so given that the experts also generally agreed that, if the IV had been open at the time of the flooding then, not only would the NRV have been the sole cause of the flooding but also that, on the balance of probabilities, the same flooding and the same damage would have occurred on1 August 2007 . 10. GMVL'S CLAIMS AGAINST HL ON CORE 2 "