“Following the completion of our level survey of the existing floor at the above address we wish to inform you that the slab is outside level tolerances for the new printing machine. The floor area where we are installing the print base is +/-60mm, which is well outside 20mm tolerance your machine requires. Unfortunately in order for us to achieve the required tolerances we will have to shutter the edges around your base using stainless steel, which will be installed to level, and therefore well within required tolerances. However this will then leave our slab protruding around 60mm above ground at one end. Any irregularity can be made good using proprietary epoxy floor repair mortar.… We trust the above is acceptable and we are progressing works as quickly as possible and aim to pour concrete on Friday 5th Sept.”
“I confirm we will pay an agreed final total payment of£15,000 (+VAT). This provided the work is carries out to our satisfaction with agreed tolerances + or - 10/20 mm. The remedial “dirty work” is completed by Friday afternoon allowing the new final finished surface to be applied on Saturday. This allows the Print engineers to commence building the press on Monday morning. Otherwise we will revert back to£12,500 + VAT. I must stress again the importance of this agreed schedule[as] we are moving from our existing factory in Romford to the Maldon site. We will have a large moving operation with cranes and heavy vehicles in place all weekend. It is our intention to be in production on Monday morning23rd September 2002 .”
“…we confirm that as instructed and agreed that we will trim the print base to current floor level and tolerances. We confirm as a result of your instruction that the new finishes will not protrude further than 10mm over existing ground levels and that we are now not required to achieve any level tolerances. Your print machine installation engineers will overcome and discrepancies in levels. We envisage all works will be completed by Saturday morning. Therefore we will require a representative from your company and one of your installation engineers to pass and sign acceptance of our works”
“he now informs me that he agrees with the Tri-tech print engineer that the floor will not take the press weight and needs to be taken up again. The two areas he checked clearly show that the Epoxy resin has not adhered to the concrete floor. I have asked Craig to provide me with a method statement for the further remedial work. I must reiterate that the continued delays and damage will and has involved consequential costs and subsequent claims. In an effort to solve the problem I must inform you, I am now seeking a second opinion from a representative of Heidelberg, the machine manufacturers.”
“With regards subsequent events, we have not acknowledged that the base is ‘moving’ but have noted comments from the installer that he believed there to be a movement of 5mm, although there is no evidence of this on the floor, either in the form of major indentations or settlement of the slab. We have acknowledged the installers comments that he has recorded a movement of 1/500mm upon placing the first section of equipment but we are not in a position to comment on the acceptability of this.”
“We would suggest that the only way to demonstrate the compressive performance of the slab is for installer to position all sections of the machinery allowing for the normal adjustments that are generally carried out at this stage.”
“Place all the print units in position on the base and then level After 24 hours check levels If results are satisfactory erect press If the results are unacceptable it is proposed to remove a strip of the existing epoxy finish down to the top of the structural concrete centred on the line of the machine legs and to re-finish, hoping to avoid the current delamination problem.”
“There is in our opinion a partial defence that can be brought to bear in this case and we would therefore suggest that it would be most appropriate for us to meet with the Loss Adjuster who is appointed in this case to talk tactics.”
“It is not admitted the floor beneath the Press had to be level and flat, within a small tolerance. The Defendant avers that the construction of the Press and the methods of installation allowed there to be a sizeable difference in the level of the floor on which the Press would be located.”
“as a matter of principle, such head of loss (i.e. the costs of wasted staff time spent on the investigation and/or mitigation of the tort) is recoverable, notwithstanding that no additional expenditure “loss”, or loss of revenue or profit can be shown. However, this is subject to the proviso that it has to be demonstrated with sufficient certainty that the wasted time was indeed spent on investigating and/or mitigating the relevant tort; i.e. that the expenditure was directly attributable to the tort - see per Roxburgh LJ in British Motor Trades Association at 569. This is perhaps simply another way of putting what Potter LJ said in Standard Chartered namely that to be able to recover one has to show some significant disruption to the business; in other words that staff have been significantly diverted form their usual activities. Otherwise the alleged wasted expenditure on wages cannot be said to be “directly attributable” to the tort.”
“the Court of Appeal has ruled that the claimant must choose between claiming for his wasted reliance expenditure and claiming for his loss of expected profits, holding that he is not entitled to recover both. This position is correct if it is interpreted to mean that the claimant should not recover his gross return or profits expected under the contract (or from the activity in question) and also the (now wasted) expenditure incurred in reliance of the contract which he had intended to meet from that gross return. But it is submitted that the ruling against a “split” claim cannot be justified if the claimant can show that there is no overlapping between the two claims.”
“…it follows that the value of the Liesbosch to the appellants, capitalized as at the date of the loss, must be assessed by taking into account: …compensation for disturbance and loss in carrying out their contract over the period of delay between the loss of the Liesbosch and the time at which the substituted dredger could reasonably have been available for use in Patras, including in that loss such items as overhead charges, expenses of staff and equipment, and so forth thrown away.”
“I think Lord Wright in the passage quoted was dealing with the expenses of retaining staff and hired equipment for the period for which they could not usefully be employed because there was no dredger available to carry on with the dredging contract…”
“Charlotte C was not a vessel for which Mr Davis normally had responsibility. Thus he must have been taken away from his usual work. It is likely that his usual work was of benefit to the claimant and so the claimant lost the benefit of that work whilst Mr Davis worked in respect of Charlotte C. However, it would probably be very difficult to identify the revenue which a superintendent would earn for his employer by his work as superintendent. This therefore seems to be to one of those cases foreshadowed by Stanley Burnton J in Admiral Management Services v Para-Protect Europe Limited where the cost of the employee time may be taken as an approximation for the loss of revenue.”
“I feel satisfied that in commercial cases the interest is intended to reflect the rate at which the plaintiff would have had to borrow money to supply the place of that which was withheld. I am also satisfied that one should not look at any special position in which the plaintiff may have been; one should disregard, for instance, the fact that a particular plaintiff, because of his personal situation, could only borrow money at a very high rate or, on the other hand, was able to borrow at specially favourable rates. The correct thing to do is to take the rate at which plaintiffs in general could borrow money. This does not, however, to my mind, mean that you exclude entirely all attributes of the plaintiff other than that he is a plaintiff. There is evidence here that large public companies of the size and prestige of these plaintiffs could expect to borrow at 1 per cent. over the minimum lending rate, while for smaller and less prestigious concerns the rate might be as high as 3 per cent. over the minimum lending rate. I think it would always be right to look at the rate at which plaintiffs with the general attributes of the actual plaintiff in the case (though not, of course, with any special or peculiar attribute) could borrow money as a guide to the appropriate interest rate.”