“The Adjudicator’s decision is binding on the Parties unless and until revised by the tribunal and is enforceable as a matter of contractual obligation between the Parties and not as an arbitral award. The adjudicator’s decision is final and binding if neither Party has notified the other within the time is required by this contract that he is dissatisfied with a matter decided by the Adjudicator and intends to refer the matter to the tribunal.”
“4. The Adjudicator's decision shall be binding until the dispute is finally determined by … arbitration… or by agreement. 5. The Parties shall implement the Adjudicator's decision without delay whether or not the dispute is to be referred to… arbitration”
“12.3 That Rok shall be paid in the additional sum of£204,465.14 plus VAT in relation to interim payment application 13 in respect of the compensation event arising from the flooding on the site… 12.5 That Celtic shall pay interest on the sum awarded in the sum of£1470.47 and which continues to accrue at a daily rate of£14.00 from and including8 September 2009 , until judgement or sooner payment.” 12.6 That Rok shall pay 25% of my costs and expenses in the sum of£5371.88 plus VAT; that Celtic shall pay 75% of my costs and expenses in the sum of£16,115.63 plus VAT…”
“In such circumstances, should the sums found due in adjudication decision number 3 give way to the disputed valuation in the final certificate? In my judgment, they should not for the following reasons: First, for the reasons set out above, I consider that the binding nature of the adjudicator's decision and the agreement of the parties to comply with that decision means that, prima facie, the adjudicator's decision should be enforced. Secondly, if payment of an adjudication decision on the sum due on an interim certificate had to be subject to the view of the Contract Administrator/Quantity Surveyor in a subsequent certificate, then the intention of parliament and the purpose of adjudication would be defeated. Each successive certificate would defeat the decision by an adjudicator on the previous certificate.”
“A notice of adjudication has to be put in its context. I have done so briefly. I agree with what was said in FastTrack Contractors Ltd v Morrison Construction Ltd[2000] BLR 168 . His Honour Judge Thornton QC said: “During the course of a construction contract, many heads of claims, issues, contentions, and causes of action will arise. Many of these will be collectively, or individually disputed. When a dispute arises, it may cover one, several or many of one, some or all of these matters. At any particular moment in time, it will be a question of fact what is in dispute. Thus, the “dispute” which may be referred to adjudication is all or part of whatever is in dispute at the moment the referring party first intimates an adjudication reference. In other words, the "dispute" is whatever claims, heads of claims, issues or contentions or causes of action that are then in dispute which the referring party has chosen to crystallise into an adjudication reference. A vital and necessary question to be answered, when a jurisdictional challenge is mounted, is: what was actually referred? That requires a careful characterisation of the dispute referred to be made. This exercise will not necessarily be determined solely by the wording of the notice of adjudication since this document, like any commercial document having contractual force, must be construed against the background from which it springs and which will be known to both parties.”