“It is anticipated at this stage that while shallow foundations may be possible for the envisaged supermarket building, piling or some form of ground treatment should also be considered in view of the possible high level past disturbance of the soils and possible high water table.”
“I enclose a copy of the site investigation report prepared at our request by LBH. As you will see the news is not entirely good. Will you please let me know the implications of this from an engineering point of view as I am keen to establish whether the scheme remains viable given the ground conditions.”
“Full comment back to Peter. Be positive.”
“We have had discrete discussions with a geotechnical contractor to establish possible solutions to the problem encountered at the above. We can now report that we consider that the superstructure will require piling, probably driven cast insitu piles approximately 13m long. The slab can be ground bearing if we adopt vibro compaction of the subsoils. The vibro stone probes will be at approximately 2m centres in each direction.”
“The report basically indicates that the ground is peat/silt/clay. Piles will be required to a depth of 13m. These will be of the “vibro” type.”
“It was agreed that ground stabilisation would be done in the main contract.”
“Floors are to carry superimposed loadings, excluding weight of applied finishes as follows: Sales Area, entrance and preparation area 15.00 [kN/m 2] Warehouse 31.50 kN/m 2.”
“We note the slab imposed loads and would request the CRS consider the loadings in light of our correspondence of recent date. We have proposed vibro treatment for the slab on the understanding that increased loads will result in greater long term settlement. The specs call for an imposed load of 15kN/m 2 for the sales floor area. However the loading code indicates an imposed load of 2.4kN/m 2/m height of storage. The available height to the ceiling is 3.2m thus giving an imposed load of 7.68kN/m 2. We also note that the General Spec calls for a bearing pressure under the slab of 100kN/m 2. We believe this should relate to a minimum safe bearing pressure under foundation bases and not the slab It is rare for normal development to achieve a bearing pressure under the slab of the magnitude required.”
“With reference to the floor slab loadings, I have not received any correspondence regarding slab loadings from yourself and would be obliged if you could clarify this point. Your comments are noted and will be looking for recommendations from yourself as to an acceptable and institutional slab loading, which we will then put to the tenant.”
“With reference to the floor loadings, we will need you to give recommendations on the proposed floor loadings, taking into account the use of the premises and the ground conditions. Your advice will then be put to the tenant for his formal approval.”
“Ground improvement process of vibrocompaction to be used to allow the construction of a ground bearing slab with an imposed loading capacity of 10kN/m 2 in the sales area and 25kN/m 2 in the storage area.”
“Floors are to carry superimposed loadings, excluding weight of applied finishes as follows: Sales Area, entrance and preparation area - 15.00 kN/m 2 Warehouse - 31.50 kN/m 2 ” (2) At paragraph 1.2 Foundations:“All foundations shall be in accordance with the Structural Engineers details with the works inspected and approved by the Engineer, the Architect and the Local Authority and comply with the following: (a) Current Building Regulations (b) B.S. 8004: 1986 Foundations (c) B.S. 8110: Parts 1 & 2 Structural use of Concrete (d) Engineer’s report information abstracted from site investigation survey. The foundation design shall take into account foundation settlement criteria. Besides traditional or fully piled foundations, other geotechnical improvement treatments such as vibroflotation shall be subject to Co-operative Retail Services Limited’s agreement.” (3) At paragraph 1.3 Ground Floor Slab:“To be reinforced concrete screeded as necessary to receive finishes as described later. The Sales Area to be designed to receive superimposed loading of 15KN/m 2. Storage Area to be designed to accept a superimposed floor loading of 31.5KN/m 2. 33. The design shall ensure that any vertical movement is within B.S. design tolerances.”
“The Contractor shall include zone loading tests to model the working behaviour of slabs and foundations to demonstrate that settlements will not exceed 10mm with differential settlement not greater than 2mm to 4 m, all to be agreed with the Supervising Officer and the Local Authority.”
“In the event of our quotation proving of interest, and before accepting an order for this work, we will require to examine trial pits over the site to confirm the soils are suitable for improvement by our proposed process.” (b) In relation to Treatment Proposals they stated: “We note the specified settlement restrictions which, with respect, we consider are excessively low for the type of building proposed and are also low for the type of soil present at this site. After treatment we estimate that under the action of the dead load of upfill and slab and assuming the long term average live loading is of the order of 8kN/m 2, the long term settlement should not exceed 50mm at the centre of the loaded area and 25mm to the edge. Differential settlement should therefore not exceed 1:500. We anticipate that this would be within normally acceptable limits for the type and usage of the building proposed. Your foundation design should take into account the likely differential settlement between the treated floor slab and piled frame. We have allowed for treatment to support a superimposed floor loading of up to 15kN/m 2. Prior to construction of the floor slabs it is essential that the formation be regraded and rolled.” (2) Roger Bullivant Limited in a letter dated4 September 1995 said that: “With regard to vibrocompaction beneath floor areas, we do not consider this technique would be cost effective due to the presence of soft recent deposits to a depth of some 7.0m. In our experience ground treatment to that sort of depth is uneconomical and we would advise you to consider pilling as an alternative option of vibrocompaction. We would be pleased to discuss this further if you so require.” (3) Bauer Foundations Limited sent a letter dated26 September 1995 in which they said this: “From an appraisal of the site investigation information received with your enquiry, we are of the opinion that the site MAY NOT be amenable to ground improvement by the vibro displacement method. This is due to the very low cohesion values reported in the Site Investigation Report (15kN/m 2). In order to ascertain the suitability of the site for ground improvement by vibro displacement technique, we would need to inspect trial pits and carry out in situ tests. If inspection of the trial pits suggested ground improvement to be beneficial, then we would offer you the following budget estimate: Install stone columns beneath the main internal ground bearing slab, 217 No approximately 3.0m depth to enhance ground bearing pressures to values in the order of 15kN/m 2. Install stone columns beneath warehouse area, 32 No. to an average depth of 4.0m to enhance the nett ground bearing pressures to values in the order of 31.5kN/m 2.”
“Prior to completion of the Development Agreement, I must be able to report with certainty to the Food Division on the overall project cost. If this figure is to exceed that for which we have Board Approval, then it may be necessary to obtain further approval before completing the Development Agreement. You will understand, therefore, my concern that this task is undertaken urgently.”
“I refer to our recent discussions on the subject of the increased costs. As you know I indicated to you that in my view the proposed development would not stand up with the level of increased costs involved. At the Executive Meeting last Monday the proposal was discussed once again and the cost analysis examined in relation to the profitability having regard to the new costs. I regret to advise that the Executive decided that the proposal did not warrant proceeding with based on the inadequate return likely to be forthcoming from the development. In my view at least£300,000 needs to be removed from the equation if the matter is to proceed.”
“We agreed that you will seek authority to exchange contracts, that are already agreed, at a price of£250,000 or thereabouts below the present figure. Once this has been done I will approach the Receiver on the basis that he either accepts the drastic reduction in his price or else the transaction fails and he is left to pick up the pieces. I need not repeat that there is only a slim chance that he will go along with this, however, we see this as our only opportunity to salvage something from the situation.”
“I confirm that the Food Division have in principle agreed that the project can go ahead quickly if£250,000 is reduced from the purchase price of the land.”
“Alternative vibro compaction method - subject to JAA review.”
“As per our telephone conversation last Friday we have allowed for treating on an approximate 2.0m grid pattern to a maximum depth of 7.3m as per the Engineers requirements. We enclose under item 7.0 a Method Statement on the ‘Vibroflo’ ™ bottom feed process which should be submitted to the Engineer for his appraisal. Whilst we do not anticipate the need to modify either our proposals or prices our tender must remain subject to confirmation until we have inspected trial pits on this site to assess whether the upper firm clays can be penetrated without the aid of pre-boring techniques. [At] the moment our price is exclusive of pre-boring but we have given rates under item 6 of our Bill of Quantities.”
“Total settlements will be in the order of 30mm not 10mm as the Specification. This has been accepted by the Engineer.”
“Further to our telephone conversation regarding the use of Messers Vibroflotation Ltd as the ground treatment company for the above project: We confirm the long term total settlements on the floor slabs on a bearing pressure of 15 kn/sq.m would be in the order of 30 mm at the centre and 15m on the edge and this is acceptable to you and we are to proceed with the use of Vibroflotation Ltd for the works.”
“requested that before additional vibro calculations are sent the Sub-contractor checks them; a number of silly errors have come through. ”
“It has been witnessed on site by the Project Engineer the amount of skew that some of your piles are being placed at. His concern has resulted in a request that you carry out load testing of a group of your piles.”
“Pennine confirm that all stone columns have been installed within verticality tolerance as stipulated by the ICE Specification. Previous correspondence to yourselves have highlighted the dense upper layers. During penetration of this layer, the flot is ‘worked’ to make the void. However, when the flot has penetrated this strata, it is straightened up.”
“a) You will provide calculations for the warehouse area to confirm the increased imposed load requirements. b) You are satisfied that the piles were formed in accordance with the specification and that the piles meet required tolerance in terms of position and verticality. c) You are satisfied that the technique adopted is the dry replacement bottom feed system as required by us and discussed prior to the sub-contract order being placed. We would also ask that you accept responsibility for the installation should any of the above criteria not be met.”
“Hopefully if testing is required the instructions can be received by return as Pennines will be leaving site tomorrow.”
“With regards to your fax of30 July 1996 and Pennine’s enclosed calculations we comment as follows: 1) We note that the thickness of the firm clay layer has been taken as 3m. 2) Earlier calculations and the site investigation gives this material as being approximately 1.5 m thick. The effect of this is that the later calculations predict a lesser settlement by reducing the effect on the softer underlying clay. Without evidence to support the figures adopted, the calculations are not acceptable.” 1) We note that the thickness of the firm clay layer has been taken as 3m. 2) Earlier calculations and the site investigation gives this material as being approximately 1.5 m thick. Without evidence to support the figures adopted, the calculations are not acceptable.”
“Vibro-pilling: Steve Brunswick (Senior Mowlem’s Civil/Structural Engineer) has discussed/checked work and calcs. from Pennine and is satisfied with work. Mowlems are prepared to underwrite Pennine’s work. They are willing to organise independent testing if it is considered necessary by JAA. JAA to consult further with Mowlems and report conclusion.”
“Following the receipt of the plate load tests, we have calculated the coefficient of consolidation (Mv). These can be seen in Appendix A. For Test No.1, Mv=0.075 Test No.2, Mv=0.095 For our design, we have used a value of 0.25 for the upper 3.0m. From on site experience, we know this is conservative.”
“Vibropiling - JAA do not intend to pursue the issue on the understanding that the works are underwritten by the Contractor and that they respond directly to our letter of29th July 1996 .”
“All stone columns have been constructed within the verticality stipulated in the I.C.E. Specification for Ground Treatment. Stone column installation method was undertaken by the dry bottom feed method.”
“The damage seen here, particularly the patch of diagonally fractured tiles, indicates a degree of stress seldom encountered in terrazzo floors - where normally defects are confined to minor imperfections in joints - and, in the light of 50 years’ experience, the writer’s opinion is that it is attributable to movement in the base or structure. However, we cannot offer suggestions as to possible causes, and only physical investigation can provide a solution.”
“The possible scenarios for full reinstatement should movement be continuing are as follows: 1) Total removal of the slab and finishes, new vibro treatment if necessary, re-compact the subgrade and lay a new slab. 2) Total removal of the slab, introduction of “ mini piles” on a regular grid and the construction of a geogrid mattress then reconstruction of the slab. 3) Core drilling and insertion of mini piles to effectively “carry” the slab, re-level the slab with a structural topping. 4) Remove finishes, chemically grouting the subsurface material to stabilise it, screed to level. 5) Pressure grout under the slab to “lift” back to level.”
“During the pre-contract period, we had discussions with a reputable piling subcontractor, who was given a copy of the soil report and who confirmed that subject to tests carried out at construction stage to ensure compliance of material indicated in the report, vibro piling could be adopted for the ground treatment for the slab area on this project. Main Contract tenders were sought and the Contractor was responsible for the selection of the piling subcontract, with our comment upon technical issues, and the main contractor was given our drawings and specifications. The main contractor initially selected a company called Vibroflotation to carry out the ground treatment and we scrutinised their calculations and accepted the subcontractor proposed on the provision that they operated a bottom dry feed replacement system. About a week to ten days before the subcontractor was due to commence, a substitute subcontractor, Pennine, was introduced. Again we scrutinised their calculations, commented that we believed the material properties used in the calculations were incorrect and after receiving revised calculations, again accepted the subcontractor provided they used a bottom dry feed replacement system, which we were informed they would. During operations on site it was reported, and we have photographs illustrating this, that the subcontractor was not using a bottom feed rig, nor were the piles being placed vertically. We wrote to the contractor requesting confirmation that they were using the equipment requested and that the piles were being installed vertically in accordance with our specification. We received this confirmation from the subcontractor. We also requested the main contractor accept all responsibility for the piling installation, which they did at a site meeting. It now transpires that there may be a failure of the ground improvement installation, leading to excessive settlement of the slab. As the contractor tendered for the work, having received drawings and specifications and has accepted full responsibility for the installation, we believe it is incumbent upon him to rectify any faults. The design of the ground improvement is the responsibility of the main contractor and it is concluded that the fault, be it a design failure or an installation failure, must rest with the main contractor. ”
“From the above, it would appear that the calculations provided by Pennine assume values for settlement post treatment which have not been achieved, either as a result of a variation in actual ground conditions, or treatment of the ground not being as effective as expected. The graphs also indicate that settlement should now be, in the main, complete.”
“13. In breach of warranty the Defendant failed to exercise reasonable skill care and diligence in the performance of its duties under the appointment with Cliveden. PARTICULARS 1. The Defendant chose a ground improvement scheme known as Vibro Replacement being the construction of vibro stone columns 2. That choice was inappropriate. It could never have worked on the site which was highly compressible and therefore was inevitably going to fail and the resulting building was bound to suffer from extensive and unacceptable differential settlement, which it did. 3. No competent engineer would have recommended the use of Vibro Replacement.”
“Particulars of the acts of commission or omission of Allen are set out in section 16(2)(a) to (l) of Dr. Stroud’s report. Allen was in breach of warranty by failing to exercise reasonable skill care and diligence in the performance of its duties to Cliveden in: a. Adopting vibro stone columns as a feasible solution for the improvement of the ground beneath the floor slabs; b. Continuing to recommend vibro stone columns after the results and circumstances of the tender for vibro specialist contractor became known; c. Failing to evaluate the technical suitability of Pennine for carrying out the vibro works; d. Not critically examining, prior to Pennine’s appointment, the basis upon which Pennine were maintaining that vibro stone columns would work successfully at the site; e. Not allowing for the weight of the slab and make-up fill in the design loading to be applied to the ground; f. Not carrying out adequate checks on calculations provided by Pennine; g. Not recommending that advice from others was needed if they, Allen, felt unable to check the calculations by Pennine; h. Overlooking the additional settlement that was likely to arise in soft clays due to secondary consolidation (so-called “creep settlement”); i. Not properly assessing the significance of effectively relaxing the specification in regard to settlement when Pennine’s settlement estimates of 28mm and 29mm became known; j. Not adequately assessing differential settlement where the ground bearing floor slab is supported around its perimeter and at internal columns positions; k. Not checking Pennine’s stone column layout in relation to the final positioning of the internal steelwork columns; and l. Not advising Cliveden that the use of stone columns would have been inappropriate at this project site, and that by adopting it the risks of substantial settlement developing with time were very high.”
“Furthermore, the Defendant: (a) Failed to undertake an independent evaluation of the feasibility and risks of the vibro solution at any material time or, if they felt unable to do so, to advise or recommend that other suitably qualified independent advice should be sought; and (b) Failed to appreciate that design input, independent of the specialist subcontractors, was needed on matters relating to the use, design and construction of vibro stone columns in very soft clay, and failed to recommend that if they, John Allen, felt unable to provide this independent assessment, then advice and design involvement should be sought from others with the appropriate expertise.”
“The store must be rebuilt with a piling solution to deal with the compressible ground. Whilst the work is being done, the Claimant will trade from temporary premises close to the site. The losses are the direct remedial works, the construction (and later removal) of the temporary store, the refitting of the new store and trading losses caused by the remedial works and store closure.”
“The loss of contribution, between 2003 and 2009, arising from a refit not taking place in 2003, and the subsequent reduced contribution levels achieved relative to those seen in stores that were subject to refit at around the same time (“Refit Delay”). The loss of contribution that is expected to arise as a result of using a smaller temporary store for six months, whilst remedial work is carried out to the main store (“Store Closure”).”
“Where a party has disclosed an expert’s report, any party may use that expert’s report as evidence at the trial.”
“…a court should be slow to find a professionally qualified man guilty of a breach of his duty of skill and care towards a client (or third party), without evidence from those within the same profession as to the standard expected on the facts of the case and the failure of the professionally qualified man to measure up to that standard. It is not an absolute rule … but, [un]less it is an obvious case, in the absence of the relevant expert evidence the claim will not be proved.”
“There may well be cases in which it would be not necessary to adduce such evidence - as, for instance, if an architect omitted to provide a front door to the premises. But it would be grossly unfair to architects, if, on a point of the type now under construction which relates to a special type of dwelling, the Court could without the normal evidence condemn a professional man.”
“It is submitted that the evidence should normally come from someone who is of equal experience or standing to the professional man in question, although evidence from the person who is acquainted with the standards may also suffice. For example, if the issue relates to a matter of structural design, evidence from a structural engineer may well be acceptable as to the standards expected of an architect who had undertaken the structural design. Such a course sometimes obviates a necessity of calling an additional witness to deal solely with the cause of the failure.”
“Expert evidence from suitably qualified professional persons is, in our judgment, admissible to show what competent architects in the position of Hamiltons could reasonably have been expected to know and do in their position at the relevant time. Indeed, in our judgment, there could be no question of the court condemning them for professional negligence on account of their failure to appreciate points (3) and (4) and to take the suitable consequential action, unless there were appropriate expert evidence to support the allegation that their conduct fell below the standard which might reasonably be expected of an ordinarily competent architect (cf. Worboys v Acme Investments Ltd(1969) 4 BLR 133 at 139 per Sachs LJ). The expert evidence before the judge consisted of evidence from three engineers and one architect, Mr Foster. The questions put to the engineers and answered by them included questions relating to the nature and extent of the professional duties owed by Hamiltons to Anglia. However, we think that little reliance can be placed on their answers to these particular questions, which related to a profession other than their own. The only directly relevant evidence in this context was that of Mr Foster...”
“What I am being asked to give a view on here is the professional responsibilities and actions of structural and civil engineers, particularly in relation to geotechnical matters. That I do feel qualified to advise on.”
“The Consultant warrants to the Client that he has exercised and that he will continue to exercise in the performance of the Services all the skill care and diligence as may be expected of a properly qualified and competent Structural and Civil Engineer experienced in carrying out work of a similar size scope and complexity to the Project.”
“The Consultant warrants that it has exercised and will continue to exercise reasonable skill care and diligence in the performance of its duties to the Client under the Appointment provided that the Consultant shall have no greater liability to the Company by virtue of this Agreement than it would have had if the Company had been named as joint client under the Agreement.”
“In my view an architect cannot escape his responsibility for the soundness of the design of the structure by delegating his work to any other person, still less to a contractor who is seeking to obtain the contract. If the defendant was not able, because this form of reinforced concrete was a comparatively new form of construction, to design it himself, he had three courses open to him. One was to say: “This is not my field”
“This reinforced concrete is out of my line. I would like you to employ a structural engineer to deal with this aspect of the matter.”
“The argument was that the defendants were responsible, as architects, for the design, and therefore they were responsible for the faulty design used by Pyrok, that is to say, putting the Pyrok mix of cement, lime, and vermiculite onto undercoats of weaker mixes of cement, lime and sand. It was submitted that the fact that Pyrok maintained secrecy was immaterial, and reliance was placed on the case of Moresk Cleaners v Hicks[1996] 2 Lloyd’s Rep 338 . I entirely agree with the judgment in that case. There the architect had virtually handed over to another the whole task of design. The architect could not escape responsibility for the work which he was supposed to do by handing it over to another. This case was different. Pyrok were nominated sub-contractors employed for a specialised task of making a ceiling with their own proprietary material. It was the defendants’ duty to use reasonable care as architects. In view of successful work done elsewhere, they decided that to employ Pyrok was reasonable. No witness called suggested it was not at the beginning.”
“If the architects felt that they could not form a reliable judgement about a lining to the tank, they should have informed Holdings of that fact and advised them to take other advice, possibly from a chemist.”
“I think that figuratively all sorts of alarm bells must have been sounding for Mr Taggart, but instead of heeding them he put the ECC proposals to Mr Jackson without any warning whatsoever. He later wrote to Mr Jackson that all outstanding points had been met.”
“McHaffie Ltd appreciated that this use of vermiculite concrete was somewhat experimental, and that it was retained to consider the suitability of the product. Under the circumstances McHaffie Ltd must be taken to have agreed to make enquires beyond talking to Ocean Cement and looking at the pamphlet. It failed to do so.”
“His knowledge of instability in the Cloverdale soils placed upon him a duty to have appropriate investigations made by an expert. He knew that the consulting engineer that he selected was not qualified as a soil specialist. He knew that the plaintiff relied on him to supervise the construction of a useful, safe building on the site which the committee of which he was a member had recommended. He knew that the plaintiff would authorise the engagement by him of whatever competent specialists he needed. He knew that soils testing is a special branch of engineering in which some British Columbia firms specialise. He was not skilled in that specialty. By the contract and by his certificate of responsibility he assumed overall responsibility to design a building that was reasonably fit for the purpose intended and to “marry” the building to the site.”
“Having regard to both primary and secondary compression, I estimate that columns of 700mm diameter spaced in a triangular pattern 1.5 m apart could have restricted the total long term settlement of the floor slab to within 55mm. Calculations to derive this opinion are supported by published empirical data which embraces both primary and secondary compression (Greenwood & Kirsch ref 1). This arrangement would represent approximately doubling the number of columns actually constructed, and they would have needed multiple re-penetrations of the vibroflot to achieve the necessary diameter, preferably facilitated by additional “pulldown” capacity. Such a scheme would be at the limits of practicality due to uplift of the surface by soil displacement associated with high density of columns per unit area.”
“Thus total long term settlements would be about 35mm after one year with relatively slow increments thereafter; say to 40mm after 10 years and 60mmm at 2026 with this configuration of stone columns. Taken together with appropriate structural detailing of the floor slab to limit effects of differential settlements, the system should have been just feasible. Such a settlement regime would allow any building defects to be corrected inside the typical contract maintenance period with later settlements of about 25mm which are generally acceptable. It is unlikely that the building would ever be operated at the full specified loading over its whole life as assumed in the above calculation. This solution would therefore have been feasible but at the margins of practicality.”
“It should be noted that the above example is provided for guidance only and is not intended to constitute a firm recommendation with regard to pile type, diameter or founding depth. The advice of a specialist piling contractor should be sought in the formulation of a final pile design.”
“The measure of damage for breach of the design obligation will obviously differ widely according to the nature of the breach; it may be nominal if the error can be rectified simply at an early stage, or it may be for loss of value or loss of commercial profitability in the case of a non-structural suitability breach, which cannot be rectified. Where the design failure relates to the structure itself, the difficult question of cost of repair or diminution of value as the proper measure of damages may be raised. It has been authoritatively held in a leading case in the Court of Appeal of New Zealand that, applying the basic compensatory principle in breach of contract cases, the measure of damage will be the cost of rebuilding to a proper design, but less a credit for any higher cost which would have been payable for a proper design in the first place, on the assumption that the client would have proceeded with the properly designed project),and the “indemnity” or diminution of value basis of assessing damages (cost of demolition, return of abortive expenditure, etc), which had been earlier suggested in an Australian case, should be rejected in such a situation.”
“It must be accepted however that usually a plaintiff in an action for damages for breach of contract against a builder is in an easier position, so far as the onus of proof is concerned, than a plaintiff claiming damages for breach of contract against an engineer. In the former case the plaintiff need only prove the builder’s contractual obligation to erect a building in accordance with the contract. If the builder has failed to do so then prima facie the plaintiff is entitled to be put, in terms of money, into the same position as he would have been in if the builder had duly completed the building. A plaintiff who is suing an engineer, on the other hand, must establish what his position would have been if the engineer had in fact exercised proper care and skill. There could be a case, as indeed was the position in the Auburn case, where on the probabilities the plaintiff would have proceeded to let a contract, on the basis of a properly prepared design, at a cost which would have been substantially higher than the contract price for the building erected in accordance with a defective design. This higher cost factor would be automatically taken care of when determining the amount of money required to put the plaintiff in the same position as he would have been in if he had let a contract on a design prepared with proper skill and diligence by the engineer. If it appeared, on the other hand, that proper skill and diligence by the engineer would have led to a situation where the owner would have completely abandoned all idea of building then the approach which I think to be the proper one would lead to the same result as found favour with Hutley JA.”
“However, it must be accepted that if Bevan Investments wished to obtain damages calculated by reference to the correct principles applicable in claims for breach of contract then it carried the onus of establishing, at least on the probabilities, that if Mr Struthers had used proper care and skill it would have proceeded with the erection of a building in accordance with his plans. Proof to that effect would in turn involve a question as to the probable price of a properly designed building. For that would be relevant to the question whether Mr Bevan would have gone ahead with the project and also the quantum of any damages.”
“there is a radical difference between a contract to produce a result and a contract to exercise skill with a view to producing a result, and I find difficulty in applying the formulae for the limitation of damages which is appropriate to contracts for the sale or carriage of goods to contracts to exercise professional skill.”
“I have not been able to find any reported case in which the total destruction of the buildings has been found to be necessary, but as a matter of principle it would seem to me that the total destruction of the building and the restoration of the site to its original state must provide the terminus of the engineer’s responsibility. Once that is done the consequences of his contractual liabilities are exhausted. In England it is established that a builder of a house which has to be demolished because it was erected in breach of contract is bound to pay by way of damages the values which the house properly built would have had at the time when the defective performance was discovered: Applegate v. Moss; Archer v. Moss;King v. Victor Parsons & Co. It might be argued that this measure of damages is applicable here. The structures erected for the respondent would not have market value in any real sense of the word but, instead of their market value, the cost of erecting equivalent structures at the date upon which it is proper to begin the new construction should be given. However, with some diffidence because the Court did not have the benefit of argument on this question, I do not consider that the argument should prevail. This would be equivalent to committing the engineer to providing the building rather than the design. The loss which the respondent experienced qua the appellant was not the loss of the building which it contracted to get, but the loss of money in a futile enterprise. In my opinion the claim for the cost of piling and for the cost of redesign should be rejected. It follows that the following items of damage which His Honour allowed should not be recovered, because they are items which follow from the assumed obligation to rebuild: …. The respondent, however, should have been entitled to recover the sums of money which it threw away on the useless construction.”
“Hutley JA approached the whole question on the assumption that the only possible measure of damages, in a case involving a completely useless building, was to be fixed by such an amount as would put the owner of the building back into the position in which he was at the time when he was induced by the negligence of the engineer to embark upon a futile enterprise.”
“There is ample authority for the propositions as put forward in McGregor as with great respect to the views expressed in the Auburn case, I can see no reason why the general rule that the plaintiff is entitled to be placed in the same position as he would have been in had the contract been performed should not provide the starting point in the case of an action for damages brought against an engineer for failing to carry out his implied contractual undertaking to use proper care and skill in the design and supervision of a building.”
“I am of the opinion that the commercial uses of the premises if sold in the open market with the existing defect is likely to be restricted to the use of the site. However with the Uretek and polystyrene scheme repairs this could be for lower value food and non-food discount retail or lightweight storage. It is not unusual for food store operators to change the layout of the premises on a number of occasions during their occupation and although it varies from retailer to retailer and property to property, at least one change in every ten years would not be unreasonable, in my opinion. The design life of premises of this nature is usually in excess of 40 years although it is not unusual for cladding to be replaced but where the frame and floor slab are expected to remain in situ without amendment. Given the design and nature of the subject property, it is unlikely that there would be any significant alterations undertaken to the property and, in my opinion, I would expect its design life span to be in excess of 40 years.”