“The generators shall be located within the level –1 designated plant area, contained within their own rooms. Each generator room is a 1 hour fire compartment and a separate designated fire zone.”
“The generators shall be located within the level –1 designated plant area, contained within their own room within the main plant room area.”
“The Consultant shall be deemed to have notice of and shall observe the Employer's Requirements and/or the Project Agreement and/or the Principal Agreement to the extent the same shall have been issued to the Consultant by the Contractor and to that extent shall be deemed to have full knowledge of the terms and conditions of the Employer's Requirements and/or the Project Agreement and/or the Principal Agreement. To the extent of the obligations of the Consultant as set out in this Agreement, the Consultant shall ensure that no act, default or omission of the Consultant shall cause or contribute to any breach by the Contractor of any of its obligations contained in the Employer's Requirements and/or the Project Agreement and/or the Principal Agreement.”
“In consideration of the Consultancy Fee set out in the First Schedule, the Contractor appoints the Consultant as the Structural and Services Engineer on the terms set out below for the provision of Consultancy Services referred to in the Second Schedule and in particular, in connection with the Principal Agreement to be entered into with the SPV by the Contractor at Financial Close.”
“The calculations, drawings, specifications, plans, advice, submissions and other documents prepared by the Consultant in accordance with the Second Schedule.”
“The team comprising the Contractor, the Consultants with design responsibility and all Subcontractors with design responsibility.”
“The Consultant warrants that he has exercised and will exercise all reasonable skill care and diligence in conformity with the normal professional standards of a consultant holding himself out as a competent consultant experienced in the provision of such services for projects similar in scope and complexity to the Works and having regard for the dates and periods stated in the Contract Programme and Design Service Programme and duties herein described and will comply in all respects with the requirements of the local authority, statutes, regulations, and codes of practice in force and relevant to the design of the Works, including but not limited to fire, health and safety. Notwithstanding any other clause in this Agreement or the Principal Agreement or term implied by statute or common law, the Consultant shall not be construed to owing any greater duty in relation to this Agreement than the use of necessary reasonable skill, care and diligence pursuant to this Clause 4.01.”
“The Consultant shall act upon all written instructions issued by the Contractor as soon as reasonably practicable, including but not limited to any variation in relation to an addition, modification, deferment, omission, reduction from or substitution of any of the Consultancy Services. Any adjustment to the Consultancy Fees for any such variation shall be ascertained in accordance with Clauses 5.13 or 5.14 as appropriate.”
“6.04 The Consultant shall exercise all reasonable skill, care and diligence to see that there will not be recommended or selected in relation to the Consultancy Services, or post completion commissioning or in the rectification of any defects which are required under the Contract to be carried out, materials which are generally known to be 6.04.1 deleterious to health and safety or the durability of the building and/or other structures and/or facilities and/or finishes and/or plant and machinery forming part of the Works in the particular circumstances in which they are used or 6.04.2 which are otherwise not in accordance with the Building Research Establishment Digest, British Standards, equivalent European or International standards recognised in the United Kingdom, Codes of Practice or 6.04.3 which do not otherwise accord with established and accepted UK building and/or established and accepted UK engineering practice or techniques current at the date of recommendation or selection as the case may be.” “6.05 The Consultant shall inform the Contractor forthwith in the event of the Consultant becoming aware that any materials which are not in accordance with Clause 6.04 above. This clause does not create any additional duty for the Consultant to check the work of others which is not required by this Agreement.” 6.04.1 deleterious to health and safety or the durability of the building and/or other structures and/or facilities and/or finishes and/or plant and machinery forming part of the Works in the particular circumstances in which they are used or 6.04.2 which are otherwise not in accordance with the Building Research Establishment Digest, British Standards, equivalent European or International standards recognised in the United Kingdom, Codes of Practice or 6.04.3 which do not otherwise accord with established and accepted UK building and/or established and accepted UK engineering practice or techniques current at the date of recommendation or selection as the case may be.”
“Where necessary the Consultant shall comment upon such drawings, specifications, agreements and the like as may be received by the Consultant from other Consultants, the Contractor, Subcontractors or other specialists which touch or concern the Consultancy Services and provide such comments within 5 Working Days of receipt by the Consultant, or as otherwise agreed with the Contractor. The Consultant's comments shall not relieve the party who has produced or caused to be produced on their behalf the drawings, specifications, agreements and the like in respect of the Works of any liability in respect of the same, and the Consultant shall not be liable for the same.”
“6.12 In performing the Consultancy Services, the Consultant shall: 6.12.1 insofar as it is within its control or the control of any specialist subconsultant, subconsultant or other person engaged by the Consultant in connection with the provision of the Consultancy Services, provide advice, documents (including designs, drawings, information and specifications), consents, comments, approvals, instructions, certificates and reports promptly, efficiently and in good time in accordance with the Construction Programme and the Design Service Programme (as developed from time to time) and advised by the Contractor. The Consultant shall not be responsible if the Consultancy Services are not completed within the required timescales to the extent that the same is due to the negligence or default of others, save for any specialist subconsultant, subconsultant or other person engaged by the Consultant in connection with the provision of the Consultancy Services. If the performance of the Consultancy Services is delayed, the Consultant shall use its best endeavours to expedite the provision of the Consultancy Services in order to recover the delays without any additional cost to the Contractor save to the extent that the the performance of the Consultancy Services is delayed due to the negligence or default of others, in which case the provisions of clause 6.01 shall apply, and the Consultant shall be entitled to payment in accordance with clause 5.13, but in doing so the Consultant shall at all times comply with its obligations under this Consultants Agreement. For the avoidance of doubt the Consultant's liability in respect of delay related costs shall only apply if and to the extent that the Consultant has failed to exercise reasonable skill and care as set out in clause 4.01 or the Consultant has committed an error or omission.; and 6.12.2 The Consultant shall have due regard to the Employer's Requirements (as developed or amended from time to time) and shall immediately advise the Contractor (with reasons) if the Consultant considers that any of the objectives and requirements in the Employer's Requirements are not reasonable or attainable.”
“The Consultant shall advise the Contractor in writing in accordance with the Contract Programme and Design Service Programme whenever it is necessary for the Trust SPV Contractor to make applications for approval under Building Acts, Regulations and other statutory requirements as are necessary for the performance of the Works, provided always that the Consultant shall advise the Contractor of the need to make such applications on a date which, having regard to the Completion Date is neither unreasonably distant from nor unreasonably close to the date on which it is necessary for the Contractor to receive such approvals. Following advice from the Consultant, the Contractor shall instruct the Consultant to make the necessary applications for approval under Building Acts, Regulations and other Statutory Requirements.”
“The Architect shall be responsible for the co-ordination and integration of all design Information provided by the Design Team the Contractor pursuant to the Principal Agreement including the issue of all drawings and other detail and will be deemed to be the Lead Designer.”
“Design Activity”, “Responsibility”, and “Additional Explanation”
“6.1 Regularly review and update a Design Programme for the issue of information and submissions for approval including all builder's work requirements throughout the duration of the Contract. Issue a schedule of all building services drawings and other information to be provided for the Works, including a building services design drawings register.” 6.2 Update the information provided in the previous Stage so that the building services designs and specifications are compliant with those defined in the Contract. 6.3 Re-evaluate the building services design and consider alternative products and materials and value engineer the design with the other members of the Design Team, sub-contractors carrying out design and the Contractor to ensure the most economical design solution, subject to the constraints imposed by the Accommodation Output Specification. Participate in Value Engineering workshops if required. 6.4 In conjunction with the Contractor and other Consultants, agree and confirm design and co-ordination responsibilities for each proposed sub-contract element. … 6.6 Provide when required relevant drawings, specifications and schedules for the tendering and/or placing of sub-contract orders for the building services works. 6.7 When required certify compliance of the design and specifications with all relevant current legislation. Advise on and assist the Contractor to obtain any necessary derogations. 6.8 Review, comment upon and liaise with the Lead Designer to assist him co-ordinating the building services subcontractors' designs and production information, and advise on non-compliance with the brief and design programme requirements. Review and comment upon whether the detailed design developed by the design and install sub-contractors complies with the construction sequence, temporary works requirements and methodology as determined by the Contractor's Construction Programme and is within the cost allowance in the Contractor's Proposals. Encourage value engineering by Sub-contractors. … 6.10 Advise the Contractor of any variations arising from the sub-contractors' designs, assist in their evaluation, and advise on their impact on the other building elements. 6.11 Liaise with the Lead Designer to assist him co-ordinate and ensure that sub-contractors' designs are fully co-ordinated with the design by the other Consultants and respect the tolerances defined by the lead Consultant at trade and zone interfaces. … 6.13 Continue discussion with Statutory, Fire and other Regulating Authorities and advise the Contractor and other Consultants regarding the placing of orders for incoming Statutory Services. Provide the necessary information to enable the Architect to secure the clearance of Town Planning matters, Building Regulations and any other regulatory approvals. 6.14 Provide such further information as is reasonably requested to enable sub-contractors to complete their design and installation drawings. 6.15 Comment on the sub-contractors' design progress and attend meetings with the Contractor, Sub-Contractors, the Design Team, the SPV and/or the Trust as reasonably necessary … 6.22 At suitable intervals inspect the Works by performing a construction quality audit role and report to the Contractor on areas of non-conformance to the specified standards and in addition, when required, advise on the progress of the Works. … 6.26 Maintain awareness of the site developments and check and confirm that the Operating and Maintenance Manuals and As-Installed Drawings prepared by sub-contractors are in accordance with the requirement of the Planning Supervisor for inclusion in the Health and Safety File and EC requirements. … 6.28 On completion of the Works or each phase of the Works prepare in conjunction with the Contractor and other Consultants a schedule of defects and inspect/approve the making good of such defects. …”
“The [Aecom] design brief currently allows for providing the lead and assisting the Architect in designing the fire safety strategy to comply with the brief. The further advice covers specialistadvice relating to its application, and liaison with Building Control to ensure that the design approach adopted is compliant with the latest recommendations of HTM 81 and ApprovedDocument B.”
“Liaise with Building Control or their approved Inspectorate to assist with HTM 81 and the AD issues raised during detailed design. Attend meetings with Building Control during detailed design to clarify design principles. Assist the team with the submission of the Part B compliance documentation and comment on the proposed content. Respond to queries raised by Building Control during the detailed design and construction period relating to HTM 81 and the AD.”
“(2) An instrument shall not be a deed unless – (a) it makes it clear on its face that it is intended to be a deed by the person making it or, as the case may be, by the parties to it (whether by describing itself as a deed or expressing itself to be executed or signed as a deed or otherwise); and (b) it is validly executed as a deed by that person or, as the case may be, one or more of those parties…” (a) it makes it clear on its face that it is intended to be a deed by the person making it or, as the case may be, by the parties to it (whether by describing itself as a deed or expressing itself to be executed or signed as a deed or otherwise); and (b) it is validly executed as a deed by that person or, as the case may be, one or more of those parties…”
“maintain Professional Indemnity Insurance from commencement of the provision of the Consultancy Services until 12 years after the Actual Completion date for the works for a limit of Indemnity of not less than [ 20,000,000 ] Twenty Million Pounds for each and every claim against any legally enforceable costs, claims, charges or expenses including but in no way restricted to liability of the Contractor to the SPV and the SPV to the Trust arising from any breach by the Consultant of the Consultant's obligations pursuant to this Agreement or other act, omission, neglect or default by the Consultant in relation to or in any way connected with the Works …”
“No action or proceedings under or in respect of this Agreement in contract or for breach of statutory duty shall be commenced against the Consultant after the expiry of 12 years after the Completion Date for the Works.”
“Notwithstanding any other clause in this Agreement or the Principal Agreement or term implied by statute or common law, the Consultant shall not be construed to owing [sic] any greater duty in relation to this Agreement than the use of necessary reasonable skill, care and diligence pursuant to this Clause 4.01.”
“AECOM was, and should have been, involved in the process of what was being built within plantroom 2, which was the product of their design development, and their obligations as fire engineer meant that they should have been involved in making sure that what was built was compliant with the Applicable Standards.”
“AECOM was required to do the detailed design of the substation and its configuration, to make itself familiar with what was being installed in the substation to ensure that it was compliant with Applicable Standards and to review and validate that it was compliant or if not to advise and warn Lendlease. AECOM’s obligations were continuing ones right up to Practical Completion.”
“I accept the proposition that, although it is necessary to look at the circumstances of each engagement, a designer who also supervises or inspects work will generally be obliged to review that design up until that design has been included in the work: see Jackson and Powell on Professional Negligence 4th Edition para 2-17. In a number of cases, it has been held that this duty continues until practical completion: see Chelmsford District Council v TJ Evers(1983) 25 BLR 99 , 106, Equitable Debenture Assets Corporation Ltd v William Moss Group Ltd [1984] 2 Con LR 1, 24 and Victoria University of Manchester v Hugh Wilson [1984] 2 Con LR 43, 73.”
“In my view, in the absence of an express term or express instructions, he is not under a duty specifically to review the design of the foundations, unless something occurs to make it necessary, or at least prudent, for a reasonably competent architect to do so. For example, a specific duty might arise if, before completion, the inadequacy of the foundations causes the building to show signs of distress; or if the architect reads an article which shows that the materials that he has specified for the foundations are not fit for their purpose; or if he learns from some other source that the design is dangerous. In such circumstances, I am in no doubt that the architect would be under a duty to review the design, and, if necessary, issue variation instructions to the contractor to remedy the problem. But in the absence of some reason such as this, I do not think that an architect who has designed and supervised the construction of foundations is thereafter under an obligation to review his design.”
“In my judgment, the duty does not require the architect to review any particular aspect of the design that he has already completed unless he has good reason for so doing. What is a good reason must be determined objectively, and the standard is set by reference to what a reasonably competent architect would do in the circumstances.”
“The continuing duty does not, however, give rise to a single and continually accruing cause of action. Rather, a different cause of action accrues at various stages. Thus, the cause of action for a failure properly to review the design is a different cause of action from a failure to provide a proper design in the first place. The causes of action will therefore accrue on different dates.”
“There used to be a suggestion that designers owed some sort of continuing duty to review their design, even after construction was complete. This so-called ‘duty to warn’ was almost always raised by claimants in order to try and avoid limitation difficulties. However the notion has fallen out of favour in recent years, and the duty has been said to arise only when something occurs to put the designer on notice that a review is required: see New Islington and Hackney Housing Association Ltd v Pollard Thomas and Edwards Ltd (2000) 85 ConLR 194 at 202,[2001] BLR 74 at 80. There is no continually accruing cause of action: see Oxford Architects Partnership v Cheltenham Ladies College[2006] EWHC 3156 (TCC) ,[2007] BLR 293 . In any event, Mr Hargreaves confirmed that this was not how he put BDW’s case on this appeal.”
“Just a reminder, you were going to email me to explain why I didn’t need to install the dampers to ductwork passing in and through this area.”
“LBS wanted the plantroom i.e. PR2 as a separate compartment. The electrical rooms are fire hazard rooms within the compartment and the ducts pass through the rooms with no take-offs and therefore do not require to be dampered. This was discussed and agreed with Nigel Brown, LBS.”
“Totally disagree with your comments, I could just amend the doc against the e mail as instructed but you are asking [Aecom] to advise you and when we do we do it with the intent that we are protecting the scheme, it is only [Lendlease’s] view we are in task avoidance mode. In two years time when the fan is full, and no one has an audit trail, [Aecom] are your first port of call, all we are doing is trying to apply something other than a knee jerk reaction. And quick cost fix. We have your overall interests in mind !!”
“… you have not revised sections 7.5 or 8.2.1 following Nigel's confirmation that the horizontal fire shutter separating B2/B1/ L0 and the generator rooms in B1 plant need not be in their own 1hr compartments. Please advise when you can revise and reissue.”
“The walls to the HV/LV/Generators are not fully fire stopped due to the amount and type of penetration. So we leave no room for being picked up on, it was agreed that the perimeter of the B1 plantroom would be the line of fire separation from the corridor, therefore please amend the document.”
“(A) Lend Lease appointed AECOM to undertake various civil, structural, mechanical and electrical and related services in connection with the development of new facilities and the consolidation of existing facilities at the Leeds Oncology Hospital PFI Project (the "Project") under an appointment contract dated on or around15 October 2004 (the "Appointment");” “(C) Lend Lease has made various claims against AECOM for loss and damage incurred due to alleged deficiencies in certain services performed by AECOM under the terms of its Appointment” “(D) AECOM has made various claims against Lend Lease in respect of unpaid fees owing by Lend Lease to AECOM for services performed under the Appointment;”
“(i) AECOM's claims for payment in respect of the consultancy services provided by AECOM pursuant to the Appointment, including AECOM's claims for fees set out in AECOM's fee claim breakdown dated August 2008 and AECOM's additional fee claim submission dated December 2010 (and updated/re-submitted in July 2011); and (ii) Lend Lease's claims relating to alleged deficiencies in certain services performed by AECOM, as set out in the claim documents submitted by Lend Lease relating to: the Haematology Ward; Chilled Beams; Kitchen Wards; Beverage Bay; Temporary Process Cooling; Plant Room Ventilation; Major Equipment Rooms Electrical Distribution; Fire Alarm Cause & Effect; Aseptic Pharmacy; Linac Chambers Electrical Distribution System; Medical Gases and Vacuum Services; Connections to Washing Machines, Tumble Dryers and Dishwashers; Extract Ventilation Systems - Dirty Extract Fans.”
“…any defects that may become manifest and/or are notified to Lend Lease after the date of this Agreement and which arise out of or in connection with AECOM's provision of services pursuant to the Appointment and in respect of which Lend Lease would be entitled to bring a claim up to the expiry of the limitation period in accordance with theLimitation Act 1980 . For the avoidance of doubt, Latent Defects excludes the defects notified to AECOM in the Notified Claims and any defects which are known or ought reasonably to have been known to Lend Lease as at the date of this Agreement.”
“The Parties agree that the terms and conditions of this Agreement are in full and final settlement of the Notified Claims and any other claims and counterclaims, liabilities or debts (of whatever nature) which are known to the Parties or which ought reasonably to have been known to the Parties as at the date of this Agreement arising out of or in connection with AECOM's provision of services pursuant to the Appointment. For the avoidance of doubt, AECOM shall remain liable in respect of Latent Defects.”
“In consideration of the payment of the Lend Lease Settlement Sum and the AECOM Settlement Sum and the Parties' compliance with the terms and conditions of this Agreement, the Parties agree to waive and unconditionally and forever release each other, their insurers, their parents, subsidiaries, affiliates and associate companies (included but not limited to their respective directors, officers, employees, agents, successors, assigns and heirs) from (a) the Notified Claims and/or (b) any other claims and counterclaims, liabilities or debts (of whatever nature) which are known to the Parties or which ought reasonably to have been known to the Parties as at the date of this Agreement arising out of or in connection with AECOM's provision of services pursuant to the Appointment. For the avoidance of doubt, this release shall not extend to AECOM's liability in respect of Latent Defects.”
“The appellants should be required to plead and prove all the elements of their case against the respondent that they have a beneficial interest in her property, in the same way as the claimants in Calyon were required to establish against the bank their title to the collection. Nothing in Patten LJ’s analysis of the legal effect of rescission in his judgment in Independent Trustee Services supports the appellants’ case that they can rely upon the Butcher Declarations against the respondent without having to plead and prove all the elements of their case against her that they have a beneficial interest in her property.” “Accordingly, applying both the rule in Hollington v Hewthorn and the wider principle enunciated in Gleeson v Wippell, I consider that the respondent is entitled to require the appellants to plead and prove all the elements of their case against her and that they cannot simply rely upon the Butcher Declarations against her.”
“In my judgment the following principles can, in summary, be derived from the authorities: (1) For C to be liable to A in respect of A’s liability to B which was the subject of a settlement it is not necessary for A to prove on the balance of probabilities that A was or would have been liable to B or that A was or would have been liable for the amount of the settlement. (2) For C to be liable to A in respect of the settlement, A must show that the specified eventuality (in the case of an indemnity given by C to A) or the breach of contract (in the case of a breach of contract between C and A) has caused the loss incurred in satisfying the settlement in the manner set out in the indemnity or as required for causation of damages and that the loss was within the loss covered by the indemnity or the damages were not too remote. (3) Unless the claim is of sufficient strength reasonably to justify a settlement and the amount paid in settlement is reasonable having regard to the strength of the claim, it cannot be shown that the loss has been caused by the relevant eventuality or breach of contract. In assessing the strength of the claim, unless the claim is so weak that no reasonable party would take it sufficiently seriously to negotiate any settlement involving payment, it cannot be said that the loss attributable to a reasonable settlement was not caused by the eventuality or the breach. (4) In general if, when a party is in breach of contract, a claim by a third party is in the reasonable contemplation of the parties as a probable result of the breach, then it will generally also be in the reasonable contemplation of the parties that there might be a reasonable settlement of any such claim by the other party. (5) The test of whether the amount paid in settlement was reasonable is whether the settlement was, in all the circumstances, within the range of settlements which reasonable people in the position of the settling party might have made. Such circumstances will generally include: (a) The strength of the claim; (b) Whether the settlement was the result of legal advice; (c) The uncertainties and expenses of litigation; (d) The benefits of settling the case rather than disputing it. (6) The question of whether a settlement was reasonable is to be assessed at the date of the settlement when necessarily the issues between A and B remained unresolved.”
“If this were a settlement case I would regard myself as bound to hold that the plaintiffs would have to prove that the amount for which they had settled was reasonable. It is not clear to me how far the Court of Appeal thought that the plaintiffs must go in establishing that fact. Nevertheless the Court of Appeal appears to have thought that it would not be sufficient merely to produce the settlement and that some examination of the underlying facts would be required….”
“Mr Davis’ evidence, which does not appear to be in dispute, is that `usually, where a riser shaft is provided, protection to adjoining floors will be provided by a fire resisting door at the floor of origin’. This means that for a fire successfully to spread via a riser it would have to enter the riser through a 60 minute fire-resisting door (so bypassing the 120 minute compartment floor) and exit the riser at another floor through another 60 minute fire resistance door – thus giving 120 minutes fire resistance.”
“The issue then, really, is not whether there was sufficient water capacity, but the fact that the design change has meant that the spatial considerations did not allow for replacement if something goes wrong.”
“11.1.7 Rotary installed the four 3000lt vessels, and these were put into service but were found to be suffering from corrosion problems, presumably/possibly from the chlorine dioxide22. A decision was made to replace the vessels, but I am advised that it was not possible to replace the vessels with ones of the same size owing to space constraints, mainly due to the amount of pipework above and around the vessels (the existing units had to be cut up in situ to enable them to be removed). The largest vessels that could be retrofitted were 1000lt…. “11.1.8 In summary, it is unclear why the stainless steel tanks were corroded. The levels of chlorine dioxide from the Trust’s water treatment system should not have caused corrosion sufficient to require the vessels to be replaced, especially in such a short time after being put into service. But the planning of the plant in the plant room ought to have allowed sufficient space for the replacement of the vessels without having to reduce the vessel capacity from 3000lt to 1000lt. The level of space planning of the plant to facilitate replacement was a pre-construction activity that ought to have been carried out by AECOM. …”
“From those decisions I consider that the following propositions can be derived: (1) That construction professionals do not by the mere act of obtaining advice or a design from another party thereby divest themselves of their duties in respect of that advice or design. In Moresk v Hicks the first argument was that it was an implied term of the architect’s employment that he should be entitled to delegate certain specialised design tasks to qualified specialist sub-contractors. That implied term was rejected as was the alternative that the architect had implied authority to act as agent for the building owner to employ the contractor to design the structure and that the architect did just that. It was not argued that if the architect remained liable for the design then it was possible for the architect to discharge a duty to take reasonable care by relying on the advice or design of specialists provided that such reliance was reasonable. (2) That construction professionals can discharge their duty to take reasonable care by relying on the advice or design of a specialist provided that they act reasonably in doing so. In London Borough of Merton v Lowe the architect’s decision to use Pyrok was reasonable. In commenting on the decision in Moresk v Hicks, Waller LJ distinguished that case on the basis that the architect has virtually handed over to another the whole task of design and “the architect could not escape responsibility for the work which he was supposed to do by handing it over to another.”