“In summary, taking into account our completion date of the19th December 2003 , we calculate our revised completion date as follows: Items 1 – 7 inclusive + 23 weeks =27th May 2004 Item 8 – variations + 4 weeks =24th June 2004 Our revised completion date is therefore the24th June 2004 . We have not taken into consideration the works we are currently carrying out on site such as retail units, east elevation gutter, door installation etc. which are solely dependant on Furlong Homes Ltd allowing us access to these areas. Based on the above calculation you will see we are not in fact in delay as you have stated, your claims relating to your level of set-off against our account are therefore unfounded and without substance. We enclose our Final Account Schedule for your perusal and trust this matter can be settled amicably despite your Company’s reluctance to pay our account in line with our discussions in April 2004. It should be noted however, that the enclosed documentation excludes any loss and expense items incurred as a result of the additional works and resequencing/prolongation of our contract works.”
“As far as item 16 and extension of time is concerned, you have provided nothing that would add to the extension of time to the2nd February 2004 previously granted. You appear to be of the opinion that despite your various breaches previously acknowledged in correspondence and your progress reports, that you are entitled to an extension of time to completion. The works were delayed by you. We have recognised that you are entitled to payment for the period between the9th December 2003 and the2nd February 2004 .”
“In the event that we do not receive payment or payment proposals by the19th August 2004 , or you disagree with our account we will confirm that we are in dispute with you and refer the matter to adjudication and issue a Notice for Adjudication.”
“We are disappointed that despite waiting around six weeks for your response to our assessment you continue to issue generalised comments which totally lack any substantiation. We have previously stated that your own assessment is flawed, our own extension of time assessment has merely taken on board the lead-in periods stated within the Contract and the periods for each activity indicated on our November 2003 programme. Indeed until recently we had not even been given access to complete the remainder of our works.”
“2.32. Further additional costs have been notified to Furlong since the account statement and Furlong requests that the Adjudicator deals with that within this Adjudication in order to finally conclude the account. 2.33. The amounts are included in the summary of the accounts. The Adjudicator has been given jurisdiction to decide on any such other amount confirming requests that these additional costs are taken into account within the Adjudicator’s decision.”
“The response includes several items that are not part of the dispute and have not previously been seen by Furlong. Your jurisdiction is restricted to the crystallised dispute. Section D paragraph 62 – 132 of the response introduces a new extension of time claim. The headings may be the same but the narrative and dates are new. The crystallised dispute concerns Verry’s letter dated17th November 2003 , Furlong’s letter dated11th May 2004 , Verry’s letter dated2nd July 2004 , Furlong’s notes on extension of time and the Verry letter dated the24th August 2004 . Verry had no right to seek decisions from you on this Adjudication that had not been referred to Furlong. Verry are required to respond to the crystallised dispute.”
“Both the cases considered, and others, relate to the situation where the referring party is seeking to put forward a case which is arguably different from that which had crystallised at the time of the Notice of Adjudication. In this case however, it is the responding party’s case which is being considered. The Notice of Adjudication dated31st August 2004 refers to Furlong’s assessment of extension of time and states that “the Adjudicator will be requested to decide that the extension of time granted by Furlong to the2nd February 2004 is correct”
“The Adjudicator is requested to decide that the extent of time granted to Verry by Furlong was correct based on the information provided. The date is the 2nd February. Alternatively the Adjudicator is requested to decide the appropriate extension of time”
“If Verry wished to make a new extension of time claim outside of this Adjudication it would be considered by Furlong in the proper way.”
“The differences between the July claim and the claim brought in the Adjudication are as a result of:- 4.1. The fact that since the claim for extension time had been submitted on the 2nd July Verry had completed its work on site on the 31st July and was therefore in a position to finalise its claim 4.2. The fact that Verry expanded its narrative to enable the Adjudicator, who unlike Furlong was not familiar with the project, to understand the factual background to various claims of extension of time 4.3. The facts and basis of Verry’s claims for an extension of time did not change between the2nd July 2004 and the response document of the24th September 2004 and accordingly was not new.”
“Notwithstanding Furlong’s Notice of Adjudication asked you to decide whether the extension of time granted to the2nd February 2004 was [my emphasis again] correct and the Referral repeated this based on the information provided at the time of the crystallised dispute, we have followed your directions of the5th October 2004 to resolve entitlement on the basis of Verry’s submission on extension of time as if they were the Claimant, which they are not. In so doing that Furlong’s initial position in respect of extension of time was totally put aside by you, your letter dated4th October 2004 refers”
“However, when a party has had an opportunity to consider the position of the opposite party and to formulate arguments in relation to that position, what constitutes a dispute between the parties is not only a claim which has been rejected, if that is what the dispute is about, but the whole package of arguments advanced and facts relied upon by each side. No doubt for the purposes of a reference to Adjudication under the 1996 Act or equivalent contractual provision, a party can refine its arguments and abandon points not thought to be meritorious without altering fundamentally the nature of the dispute between them. However, what a party cannot do in my judgment is abandon wholesale facts previously relied upon or arguments previously advanced and contend because the claim remains the same as that made previously the dispute is the same.”
“In my judgment the approach in Halki is to be preferred [to the restricted approach in Nuttall]. I am guided by the straightforward analysis in that case. In Halki (in the context of theArbitration Act 1996 ) the Court of Appeal reminded us that the Courts have generally construed widely the word ‘dispute’ and they declined in that case to construe the word more narrowly in the context of arbitration.. Whilst I accept that the adjudication process involves short timescales and that there is a risk that the responding party might be ambushed, those are not in my judgment reasons to construe the word dispute more narrowly in the context of adjudication than in other contexts. I bear in mind the practical difficulties faced by an adjudicator whose jurisdiction is challenged on the ground there is no dispute. The Court should not add unnecessarily to those difficulties by giving a narrow meaning to the word dispute which would in turn permit a responding party to introduce uncertainties which might be difficult for an adjudicator to deal with. Otherwise there is the risk that the purpose of the 1997 Act may be defeated.”
“In my view each case must depend on the circumstances and the context in which the Referral is made. In some cases the issues referred are very specific. In other cases it is clear that the issues are more general and have been so treated by the parties and that there is significantly more room for the case to be developed. The test in each case is first what dispute did the parties agree to refer to the Adjudicator? And, secondly, on what basis? If the basis which is argued in the Adjudication is wholly different to that which a Defendant has had an opportunity to respond in advance of the Adjudication, this may constitute a different dispute not referred to the Adjudicator or, put another way, in so far as the Adjudicator reaches a decision on the new issues it is not responsive to the issues referred to him.”
“It is important that a Court should approach the question of what is a dispute with robust common sense which takes into account the nature of the dispute and the manner in which it has been presented to the Adjudicator. I bear in mind that having an award enforced against a party is a serious matter for that party and there are circumstances where there is no alternative to saying that the basis on which the dispute was referred to the Adjudicator was essentially different from than upon which the Adjudicator based his decision.”
“It follows from this that within the limits which I have described an Adjudicator is not confined to considering rigidly only the package of issues, facts and arguments which are referred to him.”
“The scheme [that is the Adjudication Scheme] gives the Adjudicator two powers: to take initiative in ascertaining the facts in the law… and to resign if the dispute varies significantly from the dispute referred to him… These powers show that it is possible that a dispute that has been validly referred to Adjudication can in some circumstances, as the details unfold during the Adjudication, become enlarged and change its nature and extent. If this happens it is conceivable that at least some of the matters and issues referred… which are not previously encompassed within a pre-existing dispute could legitimately become incorporated within the dispute that is being referred.”
“Both parties have made numerous submissions and have advanced a mass of documentary evidence in the form of witness statements, letters, programmes, progress reports, orders and delivery notes for materials and the like in support of their respective cases. Both parties have relied on this mass of evidence in support of their totally opposed assertions as to the reasons for delay in completion of Verry’s work until the27th July 2004 . In the timescale of Adjudication, even with the extension of time granted to me by the parties it has simply not been possible for me to make the full analysis of this mass of evidence which would be appropriate in litigation or arbitration where the analysis would in any case probably have been carried out by experts for both sides. While I have carried out as much analysis as has been possible my decision is therefore based to a large extent on an objective overall view of events, causes and effects.”
“I therefore ask Furlong and HCC on their behalf, to consider very carefully whether it is really necessary for the establishment of their case, although accurately the refutation of Verry’s case, for the volume of material which DCL has indicated involved, to be copied and sent to them and to me, process which itself would take some time and not inconsiderable costs, followed by the process of analysis and comment by HCC for Furlong. It is possible that DCL, for Verry, will then argue that they have a right to respond to Furlong’s submissions on this further evidence. They may well argue as DCL have already done in their letter, that delivery tickets etc. are not necessarily conclusive evidence that delays were due to later deliveries, as they may seek to show that deliveries were postponed because of previous delays, making it undesirable for materials to be delivered until they could be used. I understand that this whole process will take at least until the end of this week, and that it will require at least another week for me to finalise my decision.”
“My task is certainly to arrive at a decision which, so far as practically possible, is soundly based upon evidence so that the parties may accept it as being a reasonable resolution of the dispute.”