“Nevertheless I am satisfied that this is the correct route and that the court not only possesses a discretion to grant a stay in cases such as the present but also that this is a remedy which ought to be exercised in the present case. …. This is not the case of a jurisdiction clause purporting to exclude an ordinary citizen from his access to a court and featuring inconspicuously in a standard printed form of contract. The parties here were large commercial enterprises, negotiating at arms length in the light of a long experience of construction contracts, of the types of disputes which typically arise under them, and of the various means which can be adopted to resolve such disputes. It is plain that clause 67 was carefully drafted and equally plain that all concerned must have recognised the potential weaknesses of the two-stage procedure and concluded that, despite them, there was a balance of practical advantage over the alternative of proceedings before the national courts of England and France. Having made this choice I believe that it is in accordance, not only with the presumption exemplified in the English cases cited above that those who make agreements for the resolution of disputes must show good reason for departing from them, but also with the interests of the orderly regulation of international commerce, that having promised to take their complaints to the experts and if necessary to the arbitrators, that is where the appellants should go. The fact that the appellants now find their chosen method too slow to suit their purpose is to my way of thinking quite beside the point.”
“It seems quite plain that in such cases Lord Mustill took the view that generally the courts would require the parties to pursue the alternative dispute resolution to which they had bound themselves by the terms of their contract. That is, I think, the explanation of his use of the word ‘presumption’ …. I take the view, therefore, that even where there is no arbitration clause, in the light of the observations of Lord Mustill in the Channel Tunnel Group case and in the light of the changing attitudes of our legal system, the court plainly has a jurisdiction to stay under its inherent jurisdiction, where the parties have chosen some alternative means of dispute resolution. I also take the view that where there is some such clause which is contractually binding, there is a burden on the person opposing the stay to show grounds for opposing it. It seems to me that, insofar as the word ‘presumption’ used by Lord Mustill has any application to cases such as the present, it should reflect simply the burden of persuasion in the way in which I have just stated that burden.”
“If Parliament had intended that a party should not be able to refer a dispute to adjudication once litigation or arbitration proceedings had been commenced, I would have expected this to be expressly stated. The relationship between adjudication on the one hand and litigation and arbitration on the other, was what informed the content of section 108(3) of the Act. The aggrieved claimant should not have to wait many months, if not years, before his dispute passed through the various hoops of a full blown action or arbitration.”
“Any dispute, question or difference arising under or in connection with the subcontract shall, in the first instance, be submitted to adjudication in accordance with the Association of Independent Construction Adjudicators (AICA) Adjudication Rules and thereafter to the exclusive jurisdiction of the English Courts. If the parties fail to agree on the indemnity [identity?] of the adjudicator within two days of the dispute, question or difference arising, the adjudicator shall be appointed by the AICA.”
“I have found above that Cubitt’s notice of5th December 2006 fulfilled the requirements of clauses 8.1 and 8.3 of the subcontract and therefore, for the purpose of this adjudication, I am unable to find any other sum than that assessed by Cubitt. The validity of Cubitt’s deductions have not been referred to me.”
“During the course of a construction contract, many claims, heads of claim, issues, contentions and causes of action will arise. Many of these will be, collectively or individually, disputed. When a dispute arises it may cover one, several or many of one, some or all of these matters. At any particular moment in time it will be a question of fact what is in dispute. Thus the dispute which may be referred to adjudication is all or part of whatever is in dispute at the moment that the referring party first intimates an adjudication reference.”