"2. The contract period will be 50 weeks commencing March 2003. 3. Firm contract. 4. Liquidated & ascertained damages will apply at the rate of£30000.00 per week or part thereof. 5. Payment terms will be 4 weeks from the end of the month. 6. Your tender will be deemed to include 2.5% Main Contractors Discount. 7. The defects liability period will be 12 months from the date of practical completion of the main contract. 8. Insurances: clause 21.1.1.£5,000,000.00 10. Retention 5% 13. The Supporting Documents for the purpose of your tender include extracts from the Preliminaries, relevant Preamble pages, Specification pages, and relevant pages from the Pricing Schedule upon which you should base your tender."
"In response to your enquiry we have pleasure in submitting our present prices as follows, subject to our standard terms and conditions overleaf and the particular conditions set out below. Supply and Fix Rigidal standing seam roof system all as specification H31. ... We return herewith one copy of your Bill of Quantities duly priced. The total amount of our priced items is£445,528.22 net plus VAT. All contract and subcontract orders or agreements placed with us on or after the1st May 1998 shall incorporate the provisions of theHousing Grants, Construction and Regeneration Act 1996 . Our tender will be held open for 3 months from the date of submission thereafter it will be subject to review and adjustment with respect to fluctuations in the price of labour, materials and plant. ... Day work rates Labour RICS + 250% Materials and Plant Costs + 25% ..."
"1.2 The Subcontractor agrees to waive his standard terms and conditions in favour of the DOM/1. Agreed. 1.3 Valuations will be monthly with payment being due for payment within 28 days of Architects Certificate. Agreed. 1.4 The sub-contract order will be placed in the sum of£404,628.22 and is fully fixed until September 2004 and including 2.5% MCD. Agreed. 1.5 Retention of 5% to be held until practical completion of the project, when 2.5% will be released and the remaining 2.5% within 28 days of receipt of the making good defects certificate. Agreed. … 3.0 PROGRAMME AND METHOD STATEMENT. 3.1 Period required for production of working/design drawings A/B 4wks 3.2 Period to be allowed for approval of working/design drawings. ½ wks. 3.3 Period required for manufacture from approval of drawings. 3/4wks. 3.4 Total period required for design 8-10 wks from placement of order. 3.5 Total period required for works on site. 3.6 RR agreed to work to programme as detailed below. Area of Works Earliest Start Date Latest Start Date Duration Block A (Roof) 07.07.03 28.07.03 9-10 wks Block B (Roof) 21.07.03 9-10 wks Block D (Roof) 3 wks Block C (Roof) 6 wks Cladding 6 wks 3.8 Total number of visits required Roof - six visits Cladding 3 visits ... 9.0ADMINISTRATION9.1 Subcontractor's Insurance Cover: Employers Liability Public Liability 9.4 Day works [all rates described as "
"Please accept this letter as notification of our instructions to proceed with the manufacture, supply and installation Roofing, Lead and Aluminium Flashings, Rainscreen, Cladding, Rainwater Pipework and Gutters, and Drawings at the above project, in accordance with the contract documentation listed on attached documents, for the sum of£401,666.58 less 2.5% Discount. It is the intention that a formal sub-Contract will be entered into between us in accordance with the contract documentation listed on attached document. On a formal sub-Contract being entered into, the provisions of this letter shall cease to have effect and the works carried out and payments made pursuant to this letter shall be treated as having been carried out and made under the formal sub-Contract. If at any time subsequent to the issue of this letter we give you written notice by fax or post, either that the project will not proceed for whatever reason or otherwise requiring you to cease work or part thereof, you shall immediately cease all services hereunder, in which case your entitlement would payment [sic] in accordance the provisions of DOM/1, save for loss of profit. Pending the conclusion of a binding formal sub-Contract, payment for all work properly carried out will be fully in accordance with the terms and conditions of the sub-Contract. Please acknowledge your acceptance of the above and your undertaking to commence now and proceed diligently with the execution of this instruction by signing and returning a copy of the letter only."
"We confirm acceptance of the contents of your letter dated29 May 2003 and confirm that we are now proceeding with all necessary resources to meet your programme requirements."
"WE HEARBY [sic]place the subcontract, as defined by our standard terms and conditions ref Cubitt/SC1 (copy attached) and as set out below. To carry out all works as detailed in our Letter of Intent to you dated 29/May 2003 ref DC/HWR/104 and as detailed in the attached schedule of numbered documents."
"Please accept this letter as notification of our instructions to proceed with the manufacture, supply and installation ... for the sum of£401,666.58 , less the 2.5% Discount."
"The Sub-Contract Order and the Terms and Conditions should be read and construed as a single document. In the event of any conflict between: 1.7.1 The Sub-Contract Order and the [standard Cubitt] Terms and Conditions, the Sub-Contract Order shall prevail"
“Reasonable sufficiency of notice. It is the third of these rules which has most often been to be considered by the Court. The question whether the party tendering the document has done all that was reasonably sufficient to give the other notice of the conditions is a question of fact in each case, in answering which the tribunal must look at all the circumstances and the situation of the parties. Cases where the notice has been held to be insufficient have been those where ... on documents sent by fax, reference is made to conditions stated on the back but those conditions were not in fact stated on the back or otherwise communicated ... It is not necessary that the conditions themselves shall be set out in the document tendered. They may be incorporated by reference, provided that reasonable notice of them has been given. Onerous or unusual terms. Although the party receiving the document knows it contains terms and conditions, if a particular conditions relied upon is one which is a particularly onerous or unusual term, or is one which involves the abrogation of a right given by statute, the party tendering the document must show that it has been brought fairly and reasonably to the other's attention …”
"Alternatively if, which is denied, the Subcontract contained an arbitration clause, Cubitt is nevertheless first entitled to an adjudication of the dispute pursuant toSection 108 of the Housing Grants, Construction and Regeneration Act 1996 and the Court has an inherent discretion to stay arbitral proceedings whilst such an adjudication takes place."
"Article 3.1. If any dispute or difference arises under the sub-contract either party may refer it to adjudication in accordance with Clause 38A."
"When pursuant to Article 3 a party requires a dispute or difference to be referred to adjudication then that party shall give notice to the other party of its intention to refer the dispute or difference, briefly identified in the notice, to adjudication ..."
"Subject to Article 3, if any dispute or difference ... shall arise between the Contractor and the Sub-Contractor ... then it shall be and is hereby referred to arbitration ..."
"A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section."
"I derive from the authorities noted above the following three principles which seem to me to be relevant and applicable to contracts containing a binding adjudication agreement: (a) the court will not grant an injunction to prevent one party from commencing and pursuing adjudication proceedings, even if there is already court or arbitration proceedings in respect of the same disputes ... (b) the court has an inherent jurisdiction to stay court proceedings issued in breach of an agreement to adjudicate ... just as it has with any other enforceable agreement for ADR ... (c) the court's discretion as to whether or not to grant a stay should be exercised in accordance with the principles noted above. If a binding adjudication agreement has been identified then the persuasive burden is on the parties seeking to resist the stay to justify that stance ..."
"Accordingly, even if I was wrong in my construction of clause 19, and it was not a mandatory adjudication provision Cubitt would still be entitled to assert their right to have any dispute referred, in the first instance, to adjudication. Because there was a binding adjudication agreement, they would still be entitled at least to ask the court for a temporary stay of the court proceedings. It would then be a matter of discretion as to whether or not the stay was granted. Therefore, after all this, it seems to me that perhaps the only substantive difference between the two potential situations (a mandatory agreement to adjudicate or one that is merely optional) is that if, as I have found, the adjudication provisions were mandatory, the court is likely to be even more willing to exercise its discretion in favour of the stay than will be the case if there was a simple right to adjudication."