“We now enclose the following further documentation to assist in your assessment of our entitlement and to enable you to fix a revised Completion Date. • Extension of Time Request; Narrative. • Schedule of Delays on Contract Works: orders. Our conclusion from the attached is that this document demonstrates that we have an entitlement to an extension of time for a period that we estimate to be 462 day [or 69 weeks] and we accordingly request that you revise the Date for Completion from12th February 2004 to9th June 2005 . Please note that above analysis refers to the activities as per the contract programme only and does not take into account other Architects’ Instructions and/or variations. This information will be forwarded to you in due course and we will of course keep you up to date with regards any material change in the above estimate.”
“The cause of the delay is the on going work being carried out by others, specifically the Employer’s marble and joinery contractors, which is preventing us from completing our works. The cause of this delay is a Relevant Event (25.4.8.1) and a Relevant Matter (26.2.4.1) under this contract. We do not currently know how long these contractors will be working on site and preventing us from progressing our works, because the Employer has not issued us with a programme. However, we make an estimation that they will be on site until1st July 2005 . Once the marble contractor has completed his works, we then have to complete the second fix electrical and sanitaryware installations. The contract programme allows 19 weeks for this activity. However, some of the work has already been done, and we estimate that we will require 9 weeks to complete this activity once the delay to our works ends. The contract programme shows a further 6 weeks of work after completion of this activity, to complete remaining works before Practical Completion. We therefore expect that the effect of this relevant event to be a delay to the completion of the works until 12 weeks after1st July 2005 . We therefore herewith apply for an extension of time such that the Date for Completion is revised to23rd September 2005 .”
“Notice of Adjudication We have been engaged by, and act for and on behalf of Vascroft Contractors Limited, in connection with the dispute that has arisen on the above project. As you are aware, and as is evidenced by records, Vascroft’s entitlement to an extension of time, its entitlement to be paid interest on late payments and its entitlement to be paid a mark up on employer supplied items and domestic sub-contractors are a matter of dispute between you and Vascroft. We are therefore instructed to serve upon you this Notice of Application. We append our Particulars of Notice of Adjudication. We have today applied to the President/Vice President of the Royal Institution of Chartered Surveyors for the appointment of an Adjudicator.”
“The Date for Completion is:-12th February 2004 . 2.6.1 VCL has notified the Architect of various delays during the course of the works. 2.6.2 VCL has applied for two Extensions of Time. 2.6.3 The Architect has failed to grant an Extension of Time in respect of either Application, or make a declaration that none is due, either within the periods stated within The Conditions, or at all. 2.6.4 Accordingly, the Date for Completion remains unaltered at12th February 2004 and is a matter of dispute between the Parties. 2.6.5 Practical Completion has not yet been achieved.”
“The Adjudicator is requested to Decide that VCL is entitled to an Extension of Time which revises the Due Date for Completion to23rd September 2005 , or any other such date as the Adjudicator shall Decide.”
“For the reasons set out above based on the evidence placed before me I find that Vascroft have failed to discharge the burden of proof placed upon them to evidence that they are entitled to an extension of time and I therefore decline to refix the date for completion as23rd September 2005 or any such other date.”
“1.(1) Any party to a construction contract (‘the referring party’) may give written notice (the ‘notice of adjudication’) of his intention to refer any dispute arising under the contract, to adjudication. (2) The notice of adjudication shall be given to every other party to the contract. (3) The notice of adjudication shall set out briefly – (a) the nature and a brief description of the dispute and the parties involved, (b) details of where and when the dispute has arisen, (c) the nature of the redress which is sought, and (d) the names and addresses of the parties to the contract (including, where appropriate, the addresses which the parties have specified for the giving of notices). …. 9.(1) An adjudicator may resign at any time on giving notice in writing to the parties to the dispute (2) An adjudicator must resign where the dispute is the same or substantially the same as one which has previously been referred to adjudication, and a decision has been taken in that adjudication. …. 23. …. (2) The decision of the adjudicator shall be binding on the parties, and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement between the parties.”
“Thus Mr. Miller did not decide that EDS was not entitled to any extension of time; he decided merely that EDS had not discharged the burden of showing that they were entitled to an extension of time on the ground of critical delay to the bedrooms.”
“Miss Randall submitted that in carrying out the review required by clause 11.7 and in reaching his decision Mr. Hough necessarily had to, and did, reconsider the facts and matters that had previously been adjudicated upon. The conclusion reached by Mr. Hough relative to those facts and matters was contrary to that reached in the first adjudication. Mr. Hough, accordingly, exceeded his jurisdiction, said Miss Randall. It may well be true that Mr. Hough did consider the facts and matters considered by Mr. Miller in reaching his conclusion. That in itself in my judgment is not objectionable. In my judgment Mr. Hough was not invited to trespass on Mr. Miller’s decision, nor did he do so. I reject this argument of Miss Randall.”