“During the course of our Tender Preparation we have developed with our Temporary Works and Buildability Team a number of additionak Temporary Roof options which, if allowed to be developed, could prove to be both efficient and cost effective”
“….We desperately need this to commence in conjunction with John…” 59. Laings Mr Lye was unable to make Mr Webster available for the project. Mr York was reminded in cross-examination of a written comment he made to Laings on27 July 1997 . “Q. Charlie, Warewick is here and as usual doing an excellent job. We are just about to start demolition, scaffolding erection and enabling works package, not in that order. I must have more engineers than one. If we cannot resource a job I will not hesitate to close it down for lack of engineers. Please discuss with Jim Treharne if necessary”
“The erection of the Scaffold/Temporary roof was critical to this critical path from September 8th 1997 through April 30th 1998 a period of 167 calendar days in this window. The issues that contributed to this delay are not as easily distinguishable as they are in window 1. ”
“To provide such management, control, administration and planning the work of Trade Contractors, so as to ensurefull compliance by the Trade Contractors with all the requirements of their respective Trade Contracts. To inspect trade contractors methods of working and temporary works to ensured that the same was adequate and safe. To ensure that the clients directions in regard to the handling of materials and goods at the Development Site are complied with by the Trade Contractors. To ensure that Trade Contractors are supplied at all times with sufficient information about any risk to health and safety and any safety precautions to enable them to undertake their works faithfully. 2.9 To co-ordinate the work of trade contractors and to co-ordinate the work of statutory undertakers (including gas, water, sewerage and electricity undertakings) with the local trade contractors. To make inspections. To make inspections visits as necessary to the premises of the Trade Contractors and their supplies, whether the same are located in the United Kingdom or overseas, and conduct regular meetings with Trade Contractors so as to monitor all aspects of progress both on and off site, relevant to the latest agreed programmes and to review all information requirements and provide monthly written reports thereon to the client (with copies to the architect and the costs consultant) to ensure he is fully aware of the completed records of performance by each of the trade contractors.”
“What Laing should have done and what I am of the opinion a competent construction manager would have done bearing in mind that the demolition of the infill blocks originally programmed by Laing to be completed by early December 1997, was to have produced an outline construction manager’s method statement for the protection of the services prior to obtaining demolition tenders and should have made sure that the detailed methods statement for the protection of the existing Railtrack services was submitted and approved by no later than October of 1997.”
“The critical delay that occurred during this period amounts to 107 calendar days and was caused primarily by out of tolerance steelwork, additional corrective work instructed to correct it, the demolition and construction of roof level parapet walls, and adverse weather and the early removal of the temporary roof.”
“…There was no good reason why Laing could not have accurately reported both the extent and causes of delay on site. Laing were there on site and they had free access to all information. It was their job to investigate how the job was going, collate that information and present an accurate picture to the Clients. … If incorrect information was given by Laing simply because it did not understand the true delays being ………on site and/or made mistakes when altering its programme that was very remiss. If, in fact Laing deliberately submitted incorrect information on the delays and causes for the delays then this is mismanagement of the most serious nature”
“Item 2 Description material skipped Comment - SSL have had no responses as to their loss letters therefore pay the full amount on account.”
“We concur with the view that most appropriate basis of settlement of accounts is on the commercial basis if an acceptable level of settlement is achievable… however in the event that a recommendable level of settlement is not achievable by negotiation then subject to a detailed review of the performance of the trade contractors as set out above alternative resolution by reference to third parties is an option. The use of alternative resolution to accounts is in no way prevented by the level of information or records available”