“The mine operated successfully in the past at the same levels of throughput that are now proposed by [ARM] on completion of Restart Plan, described in this report”
“The capital investment required to restart and upgrade the plant, mobilise and commence contract mining services and establish other facilities necessary to achieve and sustain a production rate of 7.5 Mtpa is estimated at£23.2M (€33.3M or US$46.6M ).”
“The ore is drawn through slots into a tunnel underneath the fine ore stockpile and discharged by feeders onto a belt running to the concentrator building where milling and flotation sections are located. With a throughput of 4.8 Mtpa, two milling trains need be employed… To achieve a throughput of 7.5 Mtpa, additional milling capacity will be required… With a throughput of 4.8 Mtpa, three banks of rougher flotation cells will be employed. Each bank contains eleven 500 cubic foot Wemco cells… When operating at a throughput of 4.8 Mtpa not all of the existing flotation cells are required but all will be brought into service to achieve a throughput of 7.5 Mtpa... The scavenger cleaner bank contains ten 500 cubic foot Wemco cells but only seven are required for 4.8 Mtpa. For 7.5 Mtpa, all ten will be used… ibid p. 290-291. 5.9 Summary Two levels of annual throughput have been considered for the Rio Tinto Project namely 4.8 million tonnes and 7.5 million tonnes, the plant has proven capacity to achieve these production rates; annual throughputs of 5.2 and 7.1 Million tonnes having been achieved in 1996 and 1997 respectively. Therefore there is little doubt that, after refurbishment of the equipment, these production levels can be achieved once more and the Restart Plan successfully implemented… Assuming that an EPCM management team is appointed for the start-up phase and the necessary permits are obtained, it is estimated that about 24 weeks (see Schedule, Appendix 5.4) will be required to bring the plant up to point of mechanical completion to allow it to be operated a rate of 4.8 Mt. The cost of this exercise is estimated to be€9.4M including EPCM and first fill but excluding contingency. Expansion to a rate of 7.5M will require a further 20 weeks and will require an estimated additional expenditure of€ 5.1M on the same basis. Following the base case mining schedule, the plant operating cost when the plant operates at 4.8 Mtpa will be€3.48 /t milled and€3.12 /t milled at 7.5 Mtpa Ibid, p. 300. .”
“Given that demand for copper metal is predicted to continue in the near term there is also a compelling business case to increase mill throughput to 9.6 Mtpa and to consider plant expansion following exploration success.”
“Rio Tinto Mine: production planned to restart at same level as in late 1990’s”
“Euro 26.35 Under Schedule 2 to the Master Agreement this was reduced to Euro 17.53m. (twenty six point three five) million shall be paid by EMED Mining to Shorthorn upon mining permits granted by the Andalusian government and availability of the senior debt facility. Euro 13.175 (thirteen point one seven five) million shall be paid by EMED Mining to Shorthorn on the 12th month following mine restart. Euro 13.175 (thirteen point one seven five) million shall be paid by EMED Mining to Shorthorn on the 24th month following mine restart. Mine restart is defined once 3 months of continuous 400,000 mt/month of ore processing has been reached Which equates to 4.8Mtpa. . Any excess cash after paying approved project needs (operating expenses and sustaining capex), project debt service and USD 10 million/year in non Spain expenses) shall be used to repay Shorthorn debt earlier than above. No dividends can be paid by EMED Mining until the above mentioned amounts are fully repaid to MRI.”
“the Consideration Shares, the Deferred Consideration and the consideration payable under the Share Purchase Agreement and the Loan Assignment, as described more fully in Clause 6” and “Deferred Consideration” as: “up to€43,883,382.70 payable by [ARM] to [Astor] in accordance with Schedule 2”. ii) Clause 6(a) provided “the Consideration shall be up to€63,300,000 consisting of the following: a)€3,430,000 payable under the Share Purchase Agreement; b)€9,116,617.30 payable under the Loan Assignment; c)€6,870,000 to be satisfied by the allotment of the Consideration shares; and d) the Deferred Consideration of€43,883,382.70 .”
“[Astor] consents, for the purposes of Clause 6(g)(iv)(A) and (B) of the Master Agreement (as hereby amended) to: a) the issue by [ARM] of loan notes to EMED Holdings (the “Loan Notes”); b) the borrowing of monies by [ARM] from EMED Holdings pursuant to the Loan Notes; and c) the repayment by [ARM], from the proceeds of the borrowing under the Loan Notes, of loans of£7,671,598 outstanding by it to EMED as at the date of this Deed.”
“It’s very unusual to find a company saying under budget and ahead of schedule. Usually the maximum you can hear is ‘on budget’ or ‘on schedule’, which usually is not right, but anyway, here we are. More unusual is to have the money, especially in this market. We are very lucky now. People said, “You diluted a lot in June”
“Amongst other things, Atalaya now contends that, as part of its calculations of 'excess cash', it is entitled to make an 'operating cash headroom’ deduction, equivalent to the trade creditors due in the first three months of the following financial year, and a deduction for 'sustaining capital expenditure headroom', equivalent to one quarter of the sustaining capital expenditure budgeted for the next financial year. Notwithstanding the fact that Atalaya provided their calculations of 'excess cash' in August 2019 – in purported compliance with a consent order requiring them to do so, and having spent over 7 months with the benefit of external accountants to produce them – those calculations did not include these 'headroom' deductions.”
“Until the Consideration has been paid to Astor in full: (1) Does clause 6(g)(iv)(B) of the Master Agreement limit (until payment to Astor of the Consideration in full) ARM’s entitlement to spend available cash to payment of those items of expenditure identified in parentheses and oblige ARM to apply the balance as excess cash to pay Astor (as Astor contends)? Astor SoC ¶5.1, 34 {A/18/157, 169}; Astor Skeleton Argument ¶76-80. (2) Or does clause 6(g)(iv)(B) refer to the cash balance held by ARM at the end of the financial year, less allowances for anticipated payments of operating expenses incurred but not yet paid for, sustaining capital expenditure and EMED Group Expenses (as Atalaya contends)? Atalaya SoC ¶6(3), 9-10 {A/18/128-129}; Atalaya Reply ¶6 {A/19/187}; Atalaya Skeleton Argument ¶29-31. ”
“… mining operations commenced In the sense of “re-started” at the Mine once it reached ‘commercial production’ (i.e. in February 2016), when the copper produced by the Mine could be sold to the market and the Mine started to produce revenue from mining operations (as opposed to relying solely on external or intragroup funding). This is consistent with the Memorandum of Understanding dated11 June 2008 , which defined ‘mine restart’ as ‘3 months of continuous 400,000 mt/month of ore processing” (broadly equivalent to 5 Mtpa), and the original definition of ‘restart of mining activities’ in the “now superseded 2008 Master Agreement at Schedule 2, namely “the date on which the mining facilities at the project meet continuous 400,000 tonnes/month production of ore processing”
“Sustaining capital expenditure” is the capital expenditure required for a company to sustain its current level of operations through the repair and replacement of capital assets used in a company’s business. It is to be contrasted with what is referred to as “expansion”, “growth” or “investment” capital expenditure, which is capital expenditure for the purposes of growing the business of a company.”
“Operating Costs means all costs and expenses incurred by the Borrower in operating, maintaining, protecting and implementing the Project and the Project Assets including mining, milling … or marketing activities in relation to the Project, including: … Taxes and Royalties…”
“77. The effect of delaying the operation of the Excess Cash Clause until1 February 2016 (as Atalaya contends) is radical. (1) First, it excludes from consideration all of the cash available to ARM in 2015, including some of the€103m intragroup borrowing some of which Mr. Dearman accepted (if ARM was not permitted to expand without paying Astor) was “surplus to ARM’s needs in 2015”. {Day2/114/10-116/16}. (2) Secondly, it means that the first assessment date is not until 11 months later (on31 December 2016 ) by which time ARM had moved far beyond mere restart of the Project, having achieved not only Phase I expansion to 7.5 Mtpa, but also Phase II expansion to 9.5 Mtpa. 78. In circumstances where the Excess Cash Clause has no start date and there are a range of possible events which might naturally prompt the first assessment of excess cash, it is reasonable to adopt the earliest and not the latest of those events. The Court may well wish to be guided by the only person to have given evidence who actually knows how these things work in practice: Mr. Webb. In his experience, a reasonable point at which to start assessing cash would have been31 December 2015 .”
“For the purposes of this Schedule, the "First Payment Date" shall be the date on which (i) the authorisations from the Junta de Andalucia to restart mining activities in the Project are granted to EMED or any other member of the EMED Group ("Permit Approval") and (ii) EMED or any other member in the EMED Group secures senior debt finance and related guarantee facilities for a sum sufficient to restart mining operations at the Project (hereinafter the "Senior Debt Facility") and the relevant member of the EMED Group is entitled to draw down funds pursuant to the Senior Debt Facility.”
“The Master Agreement and this Deed shall together constitute and be read as one and the same written instrument” save as amended by the Deed of Amendment. Clause 3.1 and 3.2. I note that the actual wording of clause 3.2 is less than clear: “Except as otherwise amended by the foregoing, the provisions of this Master Agreement shall be and continue in full force and effect and are hereby confirmed”
“[T]he wording is “cash” not “income” or “receipts”
“Assume the company has 95 in cash on 31 December, does not expect any income on 1 January but has a bill of 100 to pay on 1 January. Does it have any excess cash? It can hardly have excess cash if the foreseeable result of paying out the excess cash on 31 December is that it is unable to pay its bills.”