“In view of recent discussions we wish to clarify baselines as we move into the combined North and South construction packages as it is clear to us that the more than one programme and set of expectations are in circulation within the construction and engineering teams at large. For reference purposes we have attached the Area Release Register based on the Area Release Notifications issued by Aker Solutions and our Rev. 1 Programme. This shows delays in release of areas to us virtually across the worksite as a whole. We understand there are a number of reasons for these delays, which are outside of [Redhall] control, mainly relating to incomplete civils and structural steelwork which clearly prevent access to allow us to work in an efficient manner. … Reverting to our first point regarding more than one programme being discussed, we are currently in the process of completing Rev.2 of the Contract Programme which will cover M & P North and South and it is our intention to incorporate changes to Area release dates within this plan. This will show that we are not significantly behind site mobilisation at this specific point in time and that we are making all reasonable endeavours to minimise any delay in the performance of our obligations under the Contract.”
“1. You refer to Redhall “Revision 2 programme” submitted4th May 2010 , for approval. As stated in your letter this programme was based upon “latest known information” and hence appears to plan for the recovery of a shortfall in the rate of progress to date. Therefore this programme does not accord with the requirements of the Contract and cannot be approved as a base ('at award') Approved Programme. Redhall are required to submit a programme that accords with the requirements of the Contract no later than17th May 2010 .”
“….We require that Redhall submit as a matter of urgency, a base (at award) programme for the record. Redhall are reporting progress against the approved Rev 2 Programme, these reports show that after two weeks, that is at week ending14th May 2010 , Redhall were 1.4% below planned progress. In the absence of the base (at award) programme, Aker Solutions have now derived from the Redhall Labour Histogram dated4th March 2010 contained within the Contract (Schedule 11, Exhibit 5), a progress S Curve, a copy of which is enclosed. This will be used and referenced until the base (at award) programme is received from Redhall.”
“It is now some three weeks since our respective organisations committed to taking actions to accelerate project progress. As advised in our letter dated5 July 2010 the actions [Redhall] committed to making have advanced and are producing the desired results. However if the increasing levels of progress required to complete the project to time are to be achieved whist maintaining a reasonable degree of productivity and avoiding industrial unrest, the actions which [Aker] committed to deliver must also be progressed with urgency. We must remind you that achieving the revised Milestone completion dates is wholly dependent as conditional upon [Aker] meeting the commitments made. [Redhall] are now experiencing delays, additional costs and losing opportunities to further accelerate progress as a result of your actions remaining outstanding or incomplete. Site morale is also low and there is an increased threat of industrial action if the site conditions issues are not resolved. It should be noted that site productivity is now running seventeen percent lower than the average to date and this is directly attributable to the restricted site conditions that [Aker] undertook to resolve as part of the agreements made in Bristol. [Redhall] have embraced the intent of the agreements made and acted with urgency in implementing agreements made to maximise the benefits to the project but we will not absorb further additional costs, loss of productivity or programme impact resulting from [Aker] failure to implement the agreements they made. In particular [Aker] undertook to resolve issues surrounding site agreements, working patterns and site accommodation.”
“As we have previously advised, you are behind in populating the tracker and you promised that this work would be complete in early July to enable the revised programme to be available by mid-July. You have categorically failed to complete this and as a clear result you have no proper or effective planning function in place to enable you to properly control your works. This is the primary cause of your failure and not the spurious reasons you are attempting to suggest. To reiterate previous points, your lack of site coordination and planning are causing you to supply us with last minute requests for scaffolding and despite numerous requests you are still unable to provide us with basic four week look ahead for scaffolding requirements to enable us to plan these works ahead. This problem is further exacerbated by the fact that you site operation does not know which particular spools are going to arrive at site for incorporation in to the permanent works on any given day. Furthermore, the general position that you are attempting to portray in your letter is as a result of poor general overall organisation, lack of planning, extremely poor site coordination of the work faces and deficient supervision.”
“In accordance with the General Conditions of Contract Subclause 13.6 we hereby give notice as follows: The rate of progress by the Contractor in carrying out the Contract Works is likely to prejudice the Contractor’s ability to complete the construction of the Permanent Works and specified sections thereof, in accordance with the provision of Sub-clause 13.1, and this is due to a cause for which the Contractor is responsible.”
“On the 14th we must review developments since our meetings in Bristol of 14th - 18th June, together with the subsequent revised delivery strategy presented by David Kirby on 4th August. However you should be aware that the performance of Redhall on site has not improved noticeably and both Aker Solutions and our Client now doubt that Redhall possess the ability or commitment to deliver this contract. As you will appreciate, this is not a conclusion that has been arrived at lightly and we have taken into account all factors before calling you to attend this critical meeting. You will recall the conversations that you and I had during the bidding phase of the contract which were reiterated on the 4th February when you came to site with your senior management team and personally pledged the support of the wider Redhall Group to deliver the contract should that be required. You again advised myself and Duncan Anians on the 14th of June that if necessary you would not hesitate to bring resources to the project from beyond Redhall Engineering if that was required to fulfil your contract obligations. We see the meeting on the 14th of September as the last opportunity to convince us that these promises were not hollow. On the 14th September our Client expects to hear how the Redhall Group will overcome the deficiencies of Redhall Engineering to deliver their contractual obligations. I hope Redhall choose to seize this opportunity.”
“In respect of item 4 –[Redhall] were advised that [Vivergo] wished them to urgently consider redeployment of resources from Distillation 2 (Priority 4B) to ensure all available workfaces in the priority areas were fully manned per the Contract Schedule. [Redhall] should focus their resources on the Priorities 1, 2 and 3 including Pipe-Racks, Towers and Utility Systems that feed 1, 2 and 3. Also separately advise the impact this will have on Distillation 1 and 2. [Redhall] agreed to evaluate this and report back on what was possible and the potential consequences on other areas.”
“The intent of the Contract and Approved Programme (Rev3), was to focus on the Priority Areas 1, 2 & 3, this corresponds to your Contract obligations under Sub-clauses 13.1 and 13.6. Further this mitigates the effects of delays to Vivergo. We agree that you should focus available resources, as presented by Redhall on23rd September 2010 .”
“We presented on the23rd September 2010 , at the request of the Project Sponsors, the impact to schedule/programme, of redeployment of labour to concentrate effort on priorities 1, 2 & 3 including Pipe Racks, Towers and Utility Systems inclusive of those within Distillation 1 & 2. (Scoped W/C 27th September). As [Redhall] are still working within the restrictions imposed by the resource cap instruction we consider the phrase “we agree that you should focus available resources” within your letter as being open to misinterpretation and respectfully request that you formally instruct [Redhall] in the event you wish us to reschedule work and resources to reflect these priorities. We are already assessing the impact of the resource cap as part of [Redhall] claim for delay and disruption presently being formulated and will take into account and re-deployment of labour instructed as part of this exercise.”
“We remind you that you have already been issued with a Clause 13.6 notice for failing to make due progress and your response clearly evidences that you either do not recognise the Schedule 11 priorities and/or are not using your best endeavours to rectify the delay to the contract works as required following such notice. It is observed that your site management is directing your workforce to continually work out of sequence on less critical priority 4 areas. Your obligation to work to the priority areas is embodied both in the contract Schedule 11 and the Approved Programme Mechanism. The resource level is also derived from the Approved Programme. If you consider that you need to bring additional resources onto site, then if this breaches the level in accordance with the Approved Programme, our agreement is required. There is no contract obligation on Vivergo to provide site facilities above your programme level to accommodate increased resources. We trust that this clarifies the comment regarding focussing available resources on the priorities. There is no need for an instruction to simply reiterate what you are currently obliged to complete under the contract. We require that you demonstrate practically that you are using best endeavours to recover the programme and work in accordance with the contract to totally complete the project priorities 1, 2 &3 including pipe racks, towers and utility systems within Distillation 1 & 2.”
“Please find attached a chart showing the plan for the Process System Final Walkdowns (all disciplines) for the period week ending 17th October through to week-ending17th December 2010 This is the minimum requirement, if and when other systems become available for Walkdown, Aker Solutions are to be advised for programming the Walkdown. We will also be tracking the other systems and where necessary advise developments in this plan and in due course the plan for January 2011 on. This is to assist [Redhall] in planning preparation of testpacks for a system within an area completion, note Aker Solutions/Vivergo cannot handle all systems in the last week and it must be emphasised that systems are to be phased normally over the last 4-6 weeks of the area completion. [Redhall] should also be aware that the date shown is for Mechanical, Piping, Electrical and Instruments combined system walkdown, therefore [Redhall] must be complete a minimum of one week prior to the date shown on the chart, (includes testing, reinstatement and all QC documentation), to allow Electrical & Instrumentation to complete. We plan to hold a joint meeting with all interested contractors within the next two weeks. By return please advise your proposed attendees.”
“Following a number of letters recently between the parties this note is to confirm that at the extra-ordinary sponsors meeting in Wakefield on 13th October [Aker] advised [Redhall] that labour should be focussed to work on priorities 1,2 and 3 including the pipe racks, pipe rack towers and the utility systems that feed these priority areas. Only after ensuring that all available work faces on these key areas are fully and productively resourced should [Redhall] deploy other available resources elsewhere. The above will be confirmed within the notes of the above meeting.”
“We acknowledge receipt of your letter…dated19th October 2010 . As you are quite well aware, the email to which you refer (13th October 2010 -Focus on Priority Systems) was neither an instruction nor any communication giving rise to a variation under the contract. For the avoidance of doubt, we are treating your letter as a contractor’s proposal that it should be a variation. Accordingly, we have considered same request, but in accordance with Clause 17.1, our decision is not to order a variation. Your existing approved programme quite clearly requires you to work to the priorities as re-clarified in our email dated13th October 2010 . We remind you once again, that you are already under a clause 13.6 notice to rectify your progress default and it should not have to fall to us to continually remind you of your obligations nor have to suggest how you need to organise your workforce to attempt to work towards programme recovery. It is not unreasonable for us to expect any experienced and competent contractor to be able to do this of their own accord. Additionally, we would take the opportunity to remind you of your concurrent obligation in the contract (eg. Installation of Mechanical Equipment and Piping (South) Document 51203670-90-14.1-SPC-0004 clause 30.1.3) to ‘complete systems of the plant on dates mutually agreed between the Construction Contractor and the EPCM contractor in line with the Project Commissioning Plan’.”
“I have tried to call to discuss but I suggest that we should not be submitting the Rev 4 program in any form that enables [Aker]/[Vivergo] to accept it as the Approved Programme. I understand the practical difficulty of reporting progress against a plan you can’t achieve but we have not yet claimed or had accepted an EOT, relief from LD’s and additional costs. The draft rev 4 programme should only be tabled at this stage as part of the alternative scenarios and used to extract a contract amendment that is commercially acceptable to [Redhall]. (By the way-we are struggling to raise Jim to have a conversation with him about how he has constructed the plan)”
“We hereby confirm that the current restriction on labour recruitment is withdrawn. Please advise, at the earliest possible date, all proposed changes to your personnel strength that will be required to support the requested recovery programme in accordance with Clause 13.5. We would remind you that numbers are restricted by the site facilities which were sized to support the requirements of your Rev 3 programme. However we can potentially provide additional site facilities provided sufficient notice is given by yourselves.”
“With regard to the Approved Programme (Rev 3) it is obvious that the dates detailed therein are no longer attainable and we would therefore request that in accordance with Clause 13.5 you submit your recovery programme forthwith.”
“The programme was developed on the info available at the back end of November so the end date will have been impacted by the last few weeks of bad weather. Please also note that this programme has been forwarded to you without prejudice and is not to be interpreted as a revised contract programme.”
“Regrettably we have been unable to complete this task and apologise for this. We assure you that we consider the Project’s best intentions are served by taking the appropriate time to complete the task accurately rather than be pressured in to publishing prematurely.”
“Your continued failure to provide a programme to complete the works exacerbates the difficulties caused by your delays. This breach of your contract obligations denies us the most basic of project control tools required to mitigate the consequential impact of your delays.”
“We note your references to Clauses 13.5 and 13.7 and point out the Clause 13.5 allows for a revision to the Approved Programme to be required where a party falls behind the Approved Programme. Any such revision is to be made “in the light of the circumstances.”
“As previously confirmed, we are currently preparing our revised Contract Plan, which is being targeted to be provided to you7th March 2011 . By way of information, we confirm that we anticipate this Contract Plan will show a Contract completion date significantly later than that shown in the Completion Plan which we refer to below. Without detracting from this position and as discussed, we confirm handing to you in the above noted meeting a Completion Plan which is designed to expedite and maximise progress to an early completion and is one which indicates, subject to a commercial agreement a potential plan for early completion. This Plan consolidates the circumstances on site to date and considers that which may be potentially implemented to early completion. We have not taken into account, and have clearly not been able to include, any estimates or assumptions about future Variations, preventions or delays. It does not seek to allocate culpability and is not capable of being used to do so. It does not rely on Extensions of Time that the Contractor has claimed to date and which are due. It is not a Plan put forward nor is it capable of being accepted as an Approved Plan. It does however look to facilitate progress being maintained and maximised while the commercial and contractual position is resolved.”
“Redhall have failed to provide [Vivergo] with a recovery schedule and failed to provide [Vivergo] with a plan to tackle the key elements for underperformance.”
“[Vivergo] board agreed to remove Redhall Engineering Solutions Ltd ([Redhall]) as the M&P contractor because of their ongoing underperformance under the contract and their inability to provide any clarity on a plan for satisfactory completion of the contract scope.”
“We are in receipt of your letter reference…M069, dated15th February 2011 , subject Completion Plan. In your claim submission dated10th February 2011 , you stated that you were due a 19 week extension of time to complete the project by the end of July 2011. Such a representation is impossible to make credibly without at least a supporting programme, yet 4 days later, you reported that you are still preparing a revised "Contract Plan". We as Contract Manager are seriously disadvantaged in carrying out any assessment of your claim for an extension of time without reference to a programme submitted in accordance with the Contract. We record that you are now in breach of the contract conditions through your repeated inability to provide a revised Contract Programme (Clause 13.5). Your assertion that you are still preparing a "revised Contract Plan" is unacceptable. As you are aware we find it inconceivable at this late stage that you are still incapable of properly planning the Contract Works. We must record our opinion that you are failing to proceed regularly and diligently with the Contract Works, as reflected in your inability to produce a competent programme.”
“We refer to the above matter and previous correspondence in respect of programme and enclose for your approval programme revision 4 which has been produced to provide a programme (irrespective of responsibility for any delays to date) for the earliest practicable completion. The programme does not refer to or consider any existing or further claims for extensions of time that we are making and may be entitled to make for any delays. We also reserve our position in respect of any entitlement or instructions that may be required or requested in achieving this programme.”
“The Board supported continuing with the implementation of plans to terminate the [Redhall] contract either via Default or a negotiated termination. It appears most likely outcome will be via Default with a plan to serve the appropriate documents to terminate the Redhall contract on Friday at ̴ 14:00 after the workforce has left site at 13:30.”
“On3 September 2010 ref 51203670/206B/CP/DR/037 the Contract Manager wrote to you giving notice that the rate of progress was likely to prejudice the construction of the Permanent Works, and required you to use best endeavours to remedy delays pursuant to clause 13.6. You were specifically reminded of your obligations under the clause 13.6 notice in Aker’s letters dated8 October 2010 ref 51203670/206B/CP/DR/047,1st November 2010 51203670/206B/CP/DR/053 and2 November 2010 51203670/206B/MH/DR/054.Notwithstanding these further letters, you have failed to take any steps to proceed regularly or diligently with the Works in order to achieve a satisfactory rate of progress and productivity levels have dropped rather than improved. The Completion Date in the Contract was11 February 2011 , extended to27 February 2011 , and the Works are only 67% complete. You have indicated in your letter of15 February 2011 0616/51203670/206/DK/069 that you will not complete until “considerably later” than July 2011, which was the date you had indicated the Works would be complete by in the “Completion Plan” you refer to in that letter. A further notification that you are not proceeding regularly and diligently with the works, as contained in Aker’s22 February 2011 ref 51203670/DR/108, has not been met with any attempt to remedy the situation. In fact, your response has been to deny that you are failing to proceed regularly and diligently (as stated in your letter dated1st March 2011 ref 0616/51203670/206/DK/076) and we have therefore no confidence in your ability to rectify the breach. Programming issues and material breaches of contract You have failed to provide an Approved Programme in accordance with clause 13.3 of the Contract notwithstanding repeated requests. These requests commenced on27th May 2010 in Aker’s letter reference 51203670/206B/JB/DR/017. Aker as Contract manager reminded you of this obligation (and the fact that you remained in breach) on2 November 2010 ref 51203670/206B/MH/DR/054. Aker was compelled to accept your rev 2 “Recovery Plan” as the working programme in the absence of an Approved Programme under clause 13.3 but we wish to make it clear that this did not relieve you of your original obligation under clause 13.3 or mean that your breach of this obligation was waived. This Rev 2 programme was produced in June 2010. You have been repeatedly requested to revise this programme pursuant to clause 13.5 of the contract, in particular in the Contract Manager’s requests dated24 November 2010 ref 51203670/206B/CP/DR/079 and22nd February 2011 ref 5120367/206B/DR/109. Your failure to comply with the programming obligations under clause 13 are in our view material breaches of contract which have caused and/or contributed to the delay to the Completion date and your failure to proceed regularly and diligently. Notification of Termination In the circumstances of your continued breaches, and your failure and/or refusal to take steps to rectify these breaches, we hereby terminate your employment under the Contract pursuant to clause 43. We require you to vacate the Site forthwith and we reserve the right to complete our Contract works using your Equipment and Contract Materials (which we are entitled to do pursuant to clause 43.3 (a)). We also require you to deliver forthwith all Confidential Information, Documentation and technical Information you have prepared in relation to the Contract. We shall notify you separately of which Contracts we require you to assign pursuant to clause 43.3(c). In an email sent by Mr Hornby to Mr Rousseau and Mr Anians at 2:50pm on Friday11 March 2011 Mr Hornby reported that all contractors were off site and off the village that all gates were locked. It was reported that all Redhall’s cards to the construction village had been blocked and all of Redhall’s card for G1, the main BP gatehouse, were being blanked at that time.”
“i. Vivergo did not give any valid notification for the purpose of Sub-Clause 43.2 in relation to the alleged failure of Redhall to proceed regularly and diligently with the works. Vivergo was, therefore, not entitled to terminate Redhall’s employment on this ground; ii. The letter of 22 February, 2011 did constitute notification of a failure to provide a revised programme, as required by SubClause 13.5); iii. Redhall was at the time of the giving of the notice, in breach of Sub-Clause 13.5; iv. Redhall’s breach was “material” for the purposes of Sub- Clause 13.5; v. Redhall had, at the date of termination of its employment, commenced and was diligently pursuing rectification of its breach of Sub-Clause 13.5, as required by Sub-Clause 43.2; vi. Vivergo was, therefore not entitled to terminate Redhall’s employment under Sub-Clause 43.2 on the grounds of material breach of Sub-Clause 13.5; vii. Redhall was not in repudiatory breach of contract as at the date of termination. Vivergo was, therefore, not entitled to terminate the Contract at Common Law; viii. By serving the termination Notice, Vivergo committed a repudiatory breach of contract; ix. By excluding Redhall’s workforce from the site on14th March 2011 , Vivergo again committed a repudiatory breach of contract; x. That repudiatory breach of contract was accepted by Redhall by its letter of14th March 2011 .”
“The actual period[s] of delay from each window which are attributable to matters outwith the Contractor’s control will be collated for each area and form the basis of the Contractor’s claim for extension[s] of time.”
“this was a very open brain-storming session. If any party perceived that something was an issue, it was noted down on a flip chart. … These items were aspirational. They were things that the parties in the room felt that, if we could affect them, may assist in project execution. Not everybody in the room held the same view regarding the potential impact of the identified items, but in the spirit of open discussion/brain storming all items were noted down. Everyone also knew in my opinion that they could not be firm commitments as they were dependant in some cases on the agreement of third parties, (in particular the Trade Unions, and in some cases were so vague as to be totally incapable of recording any kind of commitment.”
“I can best describe this discussion forum as a joint “brainstorming session”, during which all parties put forward a ‘shopping list’ of ideas that they considered might assist Redhall in performing their obligations under the Contract. It is important to make it very clear that the ideas that were floated during the open discussion forum were not binding on the parties in any way, and in many cases could not possible have been binding on the parties even if they had intended them to be. It was my belief that all the parties understood this.”
“The EPCm Contractor shall provide all necessary lighting to the temporary facilities.” 1) At paragraph 16.0: “EPCm will provide safety lighting at construction areas. Such lighting shall in no way be construed as flood lighting or lighting of the Construction Contractor’s work face”
“Purchaser shall supply to the Construction Contractor the services of a Common Service Provider, who shall provide the access requirements of the Construction Contract, subject to adherence to the site rules prevailing.”
“All scaffolding work will be carried out by the ‘Common User Provider’, unless specifically stated to the contrary in the Scope of Work.”
“Scaffolding-we [Redhall] require sufficient scaffold to meet our ongoing requirements-core crew strength plus sufficient mod squads to give us required flexibility. Working session to be arranged”
“Subject to the provisions of Clause 14 (Delays), the Contractor shall complete the construction of the Permanent Works including meeting the criteria for completion of construction and takeover as set out in schedule 15 (Take over Procedures) on or before the date, or within the period , specified in Schedule 11 and shall also complete and specified section of the Permanent Works and do any other thing in the performance of the Contract on or before the dates, or within the periods Specified in the said schedule.”
“1.0 The Time of Completion for the work shall be in accordance with the overall Project Programme …… Contract completion Date 11th February 11 2.0. Dates for planning purposes are detailed in Mechanical and Piping Project Parameters dated 3rd march 10 (South rev 4 and North Rev3) refer Schedule 11 Exhibit1”
“If the Contractor fails to complete the Permanent Works or any specified section thereof or to do any other thing in accordance with Schedule 11 (Times of completion), the Contractor shall pay the Purchaser liquidated damages as prescribed in Schedule 12, but shall have no liability to pay damages in excesses of the maximum (if any) stated in Schedule 12.”
“ensuring that notwithstanding delays in any other areas that the key priorities to allow an effective start by commissioning are completed and handed over within the contract dates or asap thereafter.”
“[Redhall] were advised that [Vivergo] wished them to urgently consider redeployment of resources from distillation 2 (priority 4b) to ensure all available workfaces in the priority areas were fully manned per the Contract Schedule. [Redhall] should focus their resources on the priorities 1, 2 and 3 including Pipe-racks, Towers and the Utility systems that feed 1, 2 and 3. Also separately advise the impact this will have on distillation 1 and 2.”
“[Aker/Vivergo] have issued a letter to [Redhall] enforcing the instruction to work on Priorities 1, 2 and 3+ utilities and towers.”
“the Construction Contractor shall follow the programme priorities stated by EPCM Contractor for timely completion of all Works on Site.”
“Construction Contractor to take cognisance of the fact and allow in his contract rates that construction will convert to System installation at 60-65% completion.”
“Highlighted P&ID and isometrics, a3 size, defining the scope of work contained in each test system dossier. …location of all test blinds and test spools used in testing in lieu of instruments or at test boundaries must be highlighted on the P&IDs and associated drawings, with a listing of all items.”
“For the sake of due progress on this project, we do not consider it unreasonable to finally require you to submit the revised programme by the close of play Thursday 27th January. If we have not received your programme by that date, we feel we will be left with no option but to implement the provisions of Contract Clause 13.7. This project, and particularly your element of the works, cannot afford any more unnecessary delays and decisive action must be taken.”
“We record that you are now in breach of the contract condition through your repeated inability to provide a revised Contract Programme (Clause 13.5). Your assertion that you are still preparing a “revised Contract Plan” is unacceptable. As you are aware we find it inconceivable at this late stage that you are still incapable of properly planning the Contract Works. We must record our opinion that you are failing to proceed regularly and diligently with the Contract Works, as reflected in your inability to produce a competent programme.”
“The ‘New York Skyline’ is in need of re-development to align with the Rev 4 construction programme. Currently the relationship between the Rev 3 programme and the completions skyline is proving difficult to align. The key difficulties appear to remain un-recognised and as such unresolved due to a lack of detailed plan which interfaces between construction, testing, completions, instruments/electrical, insulation and commissioning. … Schedule of system handovers needs to be generated as preChristmas handover skyline is now out of date. … The lack of alignment between [Redhall]/[Aker]/VFS planning systems and teams is hampering the ability to develop a meaningful completions plan. Proposal to work together to find a solution must be considered if we are to conclude work in the most time effective manner.”
“Delays in developing the Rev 4 programme have been encountered due to the continued complexities between bulk build, test packs and systems. There are a number of areas which remain unclear due to the lack of interface data between ourselves and the remainder of the project. … The key elements to developing the Rev 4 programme have been:- Clarifying system test pack relationships Defining the critical chain for each test pack/system Defining the interface milestones (such as civils release from [Aker]).”
“The constraint on issuing rev 4 is driven from a commercial/legal aspect aswe do not know what EOT we can prove, it is still work in progress.I was advised not to issue the programme last Friday which puts us, that is the site team, in a very difficult place….”
“The key issue is going to be the end date and the EOT. Vivergo are desperate and it all hangs on the date any alternative settlement is going to hinge on this.”
“The programme does not refer to or consider any existing or further claims for extensions of time that we are making and may be entitled to make for any delays. We also reserve our position in respect of any entitlement or instructions that may be required or requested in achieving this programme.”
“quite clearly requires you to work to the priorities as re-clarified in our email dated13th October 2010 .”
“The standard of reference is that of the reasonable man exercising his common sense in the context and in the circumstances of the particular case. It is not an absolute clarity or an absolute absence of any possible ambiguity which is desiderated. To demand a perfect precision in matters which are not within the formal requirements of the relevant power would in my view impose an unduly high standard in the framing of notices such as those in issue here. While careless drafting is certainly to be discouraged the evident intention of a notice should not in matters of this kind be rejected in preference for a technical precision. The test is an objective one…. The notices were expressed to be "pursuant to clause 7(13)." It is plain from that that the tenant intended to invoke that clause. It is also plain that the tenant wished to determine the tenancy and that clause is the only clause under which the tenant could achieve that result. The landlord would be expected to know the terms of the lease and the date on which the lease fell to be determined under that clause. He would also be expected to know that there was no formal requirement for the tenant to specify in the notice the date of termination of the lease. There was no evident reason why the tenant should specify 12 January rather than 13 January. The close proximity of the 13th makes it the more evident that it was erroneous and that the date intended was the date which the " parties had agreed for a determination of the tenancy under clause 7(13). While there is a discrepancy evident in the notices between the reference to the clause and the statement of the date it seems to me that the notices were sufficiently clear and unambiguous. No reasonable landlord would in my view be misled by the statement of a date which in the context of a clear intention to invoke clause 7(13) was inaccurate. The landlord would in my view recognise that in each case the reference to 12 January was to be read as a reference to 13 January and I would so construe the notices.”
“if the sub-contractor… fails to proceed with the Works expeditiously or to the satisfaction of the main contractor or to remedy defective work and remains in default for seven days after being given notice in writing thereof by the main contractor.”
“On20 September 1985 , the defendants by letter gave to the plaintiffs notice that they required the plaintiffs to comply with condition 20 and work the full working day required by that condition. The defendants rely upon that letter as a notice of default under condition 8. I accept that it is such a notice despite the fact that it does not refer to condition 8 or to the consequences of non-compliance, although it would have been preferable if the threat of termination in the event of noncompliance had been made explicit.”
“Where, as often happens, a contract provides for termination of the contract by a warning notice followed by a termination notice, and two notices have been served, a party can only rely on that provision if an ordinary commercial businessman can see that there is a sensible connection between the two notices both in content and in time. Here there was no sensible connection in terms of either content or time.”
“In accordance with the General Conditions of Contract SubClause 13.6 we hereby give notice as follows: The rate of progress by the Contractor in carrying out the Contract works is likely to prejudice the Contractor’s ability to complete the construction of the Permanent Works and specified sections thereof, in accordance with the provisions of Sub-clause 13.1, and this is due to a cause for which the Contractor is responsible.”
“The rate of progress by the Contractor in carrying out the Contract works is likely to prejudice the Contractor’s ability to complete the construction of the Permanent Works and specified sections thereof, in accordance with the provisions of Sub-clause 13.1, and this is due to a cause for which the Contractor is responsible.”
“We remind you that you have already been issued with a Clause 13.6 notice for failing to make due progress and your response clearly evidences that you either do not recognize the Schedule 11 priorities and/or are not using your best endeavours to rectify the delay to the contract works as required following such notice. … We require you to demonstrate practically that you are using best endeavours to recover the programme and work in accordance with the contract…”
“We would again refer you back to our correspondence throughout this contract to date. You have been in breach of contract since inception, commencing with your fundamental failure to comply with the essential provisions of Clause 13.3 (Approved Programme). Our letter dated 27th May refers. From the outset of the contract, you have failed to programme in logical detail, adequately resource and organise your works to even a basic acceptable level, which puts you in breach of clause 3.6. Your failure to resource correctly is further evidenced by the discussions held at Bristol where we reasonably offered, without prejudice, to assist with additional engineers, without any contractual obligation to do so, to help you overcome some of your own resource deficiencies at our cost. In summary, your performance on this contract to date has been deficient since the start. We have tried various initiatives to assist you along the way but your response each time has to fall further and further away from the required contractual performance level. Your letter is therefore completely rejected. We would remind you that you are still under clause 13.6 notice.”
“We record that you are now in breach of the contract conditions through your repeated inability to provide a revised Contract Programme (Clause 13.5) … We must record our opinion that you are failing to proceed regularly and diligently with the Contract Works, as reflected in your inability to produce a competent programme.”
“Your continued failure to provide a programme to complete the works exacerbates the difficulties caused by your delays. This breach of your contract obligations denies us the most basic of project control tools required to mitigate the consequential impact of your delays.”
“We record that you are now in breach of the contract conditions through your repeated inability to provide a revised Contract Programme (Clause 13.5). Your assertion that you are still preparing a "revised Contract Plan" is unacceptable. We must record our opinion that you are failing to proceed regularly and diligently with the Contract Works, as reflected in your inability to produce a competent programme.”
“Contractor guarantees that the date of Completion stated in this Contract tobe a firm and final delivery date for completion by the Contractor of all of theWorks.”
“go so directly to the substance of the contract or, in other words, are so essential to its nature that their very nonperformance may fairly be considered by the other party as a substantial failure to perform the contract at all.”
“If the contract and the general law provide the injured party with alternative rights which have different consequences, as was held to be the case in Dalkia Utilities v Celtech, he will necessarily have to elect between them and the precise terms in which he informs the other party of his decision will be significant….”