“I therefore find and decide that Mr Dykes was not entitled to serve Notice of Termination with immediate effect on8 November 2022 ”
“I do not believe that I have jurisdiction under the narrow wording of Clause 7.1 of the Agreement to make a decision on this point. Similarly, I do not consider that I have jurisdiction to decide on [sic] whether either or both of the parties failed to act in good faith.”
“Any dispute as to the interpretation of this Agreement or as to the wording of any document required to be entered into between the parties under the provisions of this Agreement shall be referred to determination by a solicitor (of not less than 10 years standing) experienced in the relevant matter to be agreed between the parties or (in default of agreement within 14 days) nominated on the application of either party by the President (or other available officer able to make such appointment) of the Law Society.”
“Each party agrees that the courts of England and Wales shall have exclusive jurisdiction to settle any dispute or claim arising out of or in connection with this agreement or its subject matter or formation (including non-contractual disputes or claims).”
“Subject to the validity or otherwise of the Notice of Termination, I order Mr Dykes to sign all future documents in accordance with the Agreement.”
“4. COUNTER SUBMISSION TO THE COMPANY’S SUBMISSION: THE CURRENT DISPUTE 4.1 AD agrees that the matters that fall with [sic] Ms Russell’s jurisdiction and which she is obliged to determine are: 4.1.1 As properly construed, whether the Company is in breach of clause 18 of the Agreement. Although the Company has artificially sought to restrict the breach that is purportedly in issue as being only Clause 18.5, that simply does not represent the scope of the dispute between the parties and the grounds upon which AD terminated the Agreement; 4.1.2 If so, was that breach “fundamental” within the meaning clause 21.1(a) of the Agreement, such that AD was entitled to terminate the Agreement pursuant to that clause; 4.1.3 In the alternative, was AD entitled to terminate the Agreement pursuant to clause 21.1(b) of the Agreement. 4.2 It is submitted that the above issues are matters of interpretation of the Agreement.”
“The animating principle of all kinds of estoppel is the prevention of the unconscionable repudiation of promises or assurances.”
“This line of argument could be used as a defence to a challenge to an expert’s jurisdiction. The other party may be able to argue that because both parties have acted on the assumption that the expert does have jurisdiction, the party disputing jurisdiction is precluded from denying that the expert has jurisdiction, or that a party has approbated the decision of the expert ……”
“Submission to Expert Determination 44. There seems to me little doubt that a party to a contract containing a clause providing for disputes to be decided by an expert can expressly or impliedly, by words or conduct, confer jurisdiction on such an expert where otherwise there would be none. 45. This, it would seem to me, was decided albeit obiter, in Rhodia Chirex Ltd Rhodia Chirex Ltd v Laker Vent Engineering Ltd[2003] EWCA Civ 1859 . by the Court of Appeal. The case concerned the mechanism for resolving disputes following a termination for convenience by the employer under the IChemE Model Form of Contract, 3rd (June 1995) edition. In short the Court of Appeal held that a dispute following the termination of the contractor’s employment under the contract had properly been referred to the expert. However the Judge at first instance had also held that the employer had submitted to the jurisdiction of the expert, reaching that conclusion on the basis that although the employer had reserved its position, it did so too late. In deference to the arguments put forward and because it disagreed with the Judge, the Court of Appeal considered a further ground of appeal on this point. 46. Having referred to a passage from the first instance judgment, Auld L.J., with whom Hale and Dyson L.JJ. (as they then were) agreed, said, at paragraph 36: “It may be that failure by a party expressly to reserve its position coupled with other circumstances could amount to a submission to the jurisdiction of an expert. But neither of the authorities upon which the Judge relied for that proposition, Fastrack v. Morrison(2000) 4 BLR 168 and Whiteways Contractors (Sussex) Ltd. v. Impressa Castelli Construction UK Ltd. [2001] 75 Con LR 92, are directly in point. More important is whether on the facts of this case, it can be said that Rhodia had no real prospect of successfully defending Laker Vent's claim that it had submitted to the jurisdiction of the expert. This is essentially a factual question. It turns largely on the documentary evidence before the Judge, the essentials of which I have summarised.” 47. Auld L.J. returned to the point at paragraph 40: “As to whether failure by a contracting party to reserve its position on jurisdiction would amount to a submission to it is a more difficult question, and one that is highly fact sensitive. To succeed on such a basis at trial, a claimant would have to show that such silence, when considered with all the other material facts, amounted to a clear submission to the jurisdiction. See e.g. Project Consultancy Group v. The Trustees of the Grey Trust(1999) BLR 377 ; Nordot Engineering Services Ltd. Siemens Plc(unreported)14th April 2000 ; and Cowlin Construction Ltd. V. CFW Architects(2003) BLR 241 It would not be enough to conclude, as the Judge did at the beginning of the passage I have set out in paragraph 34 above, that Rhodia "did not make it clear what they were saying if it was that they were not abandoning any jurisdictional point." [my emphasis] Still less is that a permissible basis upon which to give summary judgment against it on such an issue. Given the history of the matter as contained in and illustrated by the documentation before the Judge, I would have held, had it been necessary, that Laker Vent had not shown that Rhodia had no real prospect of successfully defending on this issue, and would have allowed this ground of appeal.” 48. As I read these passages, the Court of Appeal was accepting that a party could submit a dispute to the jurisdiction of an expert under a clause such as Clause 17.1 of the Development Agreement; in other words there is no issue of principle which exempts expert determination clauses from such a doctrine. It is however a question of fact as to whether there has been “a clear submission to the jurisdiction”.” “It may be that failure by a party expressly to reserve its position coupled with other circumstances could amount to a submission to the jurisdiction of an expert. But neither of the authorities upon which the Judge relied for that proposition, Fastrack v. Morrison(2000) 4 BLR 168 and Whiteways Contractors (Sussex) Ltd. v. Impressa Castelli Construction UK Ltd. [2001] 75 Con LR 92, are directly in point. More important is whether on the facts of this case, it can be said that Rhodia had no real prospect of successfully defending Laker Vent's claim that it had submitted to the jurisdiction of the expert. This is essentially a factual question. It turns largely on the documentary evidence before the Judge, the essentials of which I have summarised.” “As to whether failure by a contracting party to reserve its position on jurisdiction would amount to a submission to it is a more difficult question, and one that is highly fact sensitive. To succeed on such a basis at trial, a claimant would have to show that such silence, when considered with all the other material facts, amounted to a clear submission to the jurisdiction. See e.g. Project Consultancy Group v. The Trustees of the Grey Trust(1999) BLR 377 ; Nordot Engineering Services Ltd. Siemens Plc(unreported)14th April 2000 ; and Cowlin Construction Ltd. V. CFW Architects(2003) BLR 241 It would not be enough to conclude, as the Judge did at the beginning of the passage I have set out in paragraph 34 above, that Rhodia "did not make it clear what they were saying if it was that they were not abandoning any jurisdictional point." [my emphasis] Still less is that a permissible basis upon which to give summary judgment against it on such an issue. Given the history of the matter as contained in and illustrated by the documentation before the Judge, I would have held, had it been necessary, that Laker Vent had not shown that Rhodia had no real prospect of successfully defending on this issue, and would have allowed this ground of appeal.”
“50. Although this formulation applies to adjudication, it provides a useful summary of the approach to be taken in a case such as the present and merely expands upon the formulation of the issue as expressed by the Court of Appeal in Rhodia Chirex Ltd.. However, at sub-paragraph (e) above, Akenhead J. goes further in finding that a waiver can also arise in such circumstances. Once again, I can see no reason in principle why, by words or conduct, a party to a contract might not waive a right to object to the jurisdiction of an expert under an expert determination clause. Once again, it is all a question of fact.”
“Accordingly, Faraday are estopped by representation and convention from now arguing that the Act and scheme did not apply and that the adjudicator was not entitled to make an adjudication [sic] which would be binding until the final determination of the dispute.”
“At the very least, (i) there would have to be some words or conduct unequivocally representing that the variation was valid notwithstanding its informality; and (ii) something more would be required for this purpose than the informal promise itself: see Actionstrength Ltd v International Glass Engineering IN.GL.EN SpA[2003] 2 AC 541 , paras 9, 51, per Lord Bingham of Cornhill and Lord Walker of Gestingthorpe.”
“I am aware of DHBL’s involvement in the development of the Kingswood site, however Mr Braund has failed to provide any underlying documents explaining why each of these payments was made.”