"Power to construct works 4. - (1) The Company may construct and maintain the scheduled works. (2) Subject to article 5 below, the scheduled works shall be constructed in the lines or situations shown on the deposited plans and in accordance with the levels shown on the deposited sections."
"4. (4) Subject to paragraph (5) below, the Company may carry out and maintain such other works (of whatever nature) as may be necessary or expedient for the purposes of, in connection with or in consequence of, the construction of the scheduled works."
" Work No. 2 A railway (1050 metres in length) mainly on a new viaduct commencing by a junction with the termination of Work No. 1 (railway) passing in a south easterly direction on the new viaduct passing over Holywell Lane and Shoreditch High Street by means of new bridges and across the site of the disused Bishopsgate Goods Yard passing over Wheler Street and Brick Lane and then passing over the Great Eastern Railway by means of new bridges and passing over Work No. 7 (new street) and Work No. 3 (railway) of the Crossrail project (if constructed) and joining the course of the East London Line between Shoreditch station and Whitechapel station and terminating at a point 20 metres north west of the junction of Selby Street with Vallance Road."
"that planning permission be deemed to be granted for the development for which provision is included in the Order subject, in relation to Work Nos. 1 to 2 and 4 to 7 as described in Schedule 1 to the Order, to the conditions set out in Part I of the Annex to this direction and, in relation to Work No. 3 as so described, to the conditions set out in Part II of the said Annex."
"(1) The development shall be begun before the expiration of five years from the date the Order comes into force (that is, no later than10 February 2002 )."
"(12) No work shall commence on site until full particulars of the location and method of measures to be taken to minimise the effect of vibration from the operation of the Line on adjacent listed buildings have been submitted to and approved by the relevant local planning authority."
"(21) The development shall not commence until the exchange land described in article 30 of the Order has been made suitable for use as open space by: (i) the removal of redundant viaduct arches and other buildings; (ii) contouring the land to appropriate levels; (iii) providing a suitable depth of soil to support vegetation; and (iv) providing landscaping in consultation with the relevant local planning authority."
"(23) No development shall commence on the land bounded by Bethnal Green Road, Wheler Street, Shoreditch High Street and the proposed Bishopsgate station or on land in Allen Gardens until a landscaping scheme for those sites has been submitted to and approved by the relevant local planning authority."
"(C&D) listed building consent for the partial demolition of the former Bishopsgate Goods Yard, Shoreditch High Street, E1 and the construction of a length of boundary wall, in accordance with your application Nos. LRP270/E5990/052 & LRP270/U5360/014 to the Councils of the London Boroughs of Hackney and Tower Hamlets dated3 December 1993 and submitted drawings and revised drawing 116B subject to the following conditions:- a. No demolition works shall commence until full particulars, including detailed drawings, of the measures be taken to safeguard and where necessary consolidate the structural integrity of the gates and associated structures and the former Bishopsgate Goods Yard, both during the works of demolition of the adjacent structure and subsequently, have been submitted to and agreed by the local planning authority and the appropriate measures have been implemented. The gate mechanisms within the forecourt shall be retained in situ. c. No demolition shall commence until details of the precise location, height and materials of the screen wall shown on drawing E/HR 0721/P/24/A/0116/B, and of the ground surface treatment of the area to the north of this wall and of the area to the west of the retained structure, have been submitted to and approved by the local planning authority. The screen wall shall be constructed before the Line is brought into use."
"Forecourt Wall and Gates to Old Bishopsgate Goods Station"
"5.23 In its present condition the former goods station detracts from the character and appearance of the area and represents a far from optimum use of a valuable inner city site. 5.24 From the extract from the statutory list it is clear that only the forecourt wall and the gates to the former goods yard are listed … . 5.26 The works proposed would retain the features of interest that are specifically mentioned in the list description and would facilitate a scheme that would bring substantial benefits for the community and would contribute both to economic regeneration and the environmental enhancement of the area. As such I consider that the partial demolition would accord with the statutory provisions … ."
"6. English Heritage were still of the opinion that the specific interest of the structure relates to the entrance gates and ornamental stone work only. They consider that part of the Goods yard which lies within the London Borough of Tower Hamlets is not listed and is not of special architectural or historic interest."
"8. On balance it appears to him that the curtilage of the listed structure includes the ramp and wall adjacent to Bethnal Green Road, which extends continuously as far as Wheeler Street as shown in stippled tone on the Appendices to the application. He has therefore proceeded to determine all the listed building consent applications submitted."
"(a) any object or structure fixed to the building; (b) any object or structure within the curtilage of a building which although not fixed to the building , forms part of the land…"
"7.3.5. All that remained of the goods yard was the ground floor structure, the first and second floors having been demolished following a major fire in 1964. LUL had not glossed over the history of the structure, and very extensive records were available. The goods yard, which LUL proposed partly to demolish, largely dated from the 1880s, and did not comprise the earlier structure which formed the passenger station of the 1840s. So far as is known, that no longer exists."
"The condition can not be regarded as discharged as there has been no formal application to the Council. However given the circumstances an application under Section 73 would be the way forward."
"(4) This section does not apply if the previous planning permission was granted subject to a condition as to the time within which the development to which it related was to be begun and that time has expired without the development having been begun."
"Although the development has to be commenced by this date, the conditions do not expressly require the approval to be obtained by this date. There is, however, a clear implication that the developer will have applied for permission before that date. As long as the developer has applied for the approval, I would not draw the implication that the approval must be obtained by this date. It must have been reasonably obvious to Parliament that there would be many situations where although a developer had made a timeous decision to apply for approval, that approval, through no fault of the developer, could not be obtained until after the expiration of the time limits for implementing the permission. Where this happens and the developer had already implemented the permission by commencing operations pending the outcome of approval, it could be grossly unfair to the developer to regard him as being time barred. Indeed, the operations which took place to comply with the time-limit may be a matter which would not be affected by the terms of the approval, although they would still contravene a blanket prohibition the commencement of operations. Alternatively, they may be of no significance from a planning point of view so no reasonable planning authority would contemplate enforcement action. I cannot accept that it was intended that in these circumstances a planning permission should be of no effect … ."
" … I take the view that it can accord with the intent of the legislation if the approval is obtained after the expiration of the time-limits as long as the application has been made before the specified time-limits and either the operations which have taken place are immune from enforcement or the approval is obtained prior to enforcement action. If the operations can be and are the subject of enforcement action the position is different, since in the context of the enforcement proceedings the question of whether an approval, and if so what approval, should be given can be decided by the Secretary of State, the Secretary of State using if necessary his powers to grant a fresh planning permission."
"It is in these circumstances that I consider that the third candidate provides the correct solution to the question and that whether the planning permission has been implemented has to be tested by examining the situation in an enforcement context by considering whether enforcement action is possible and if it is leaving the outcome to be determined in the enforcement proceedings. This is a sensible and practical solution to the possible problems in obtaining approval. Obviously, if the planning authority or the Secretary of State does not regard it as desirable, where a time-limit has expired, to give approval to reserved matters they are not under a duty to give approval. They can take the stand (as long as they act reasonably) that the developer has lost his chance. If, however, they give approval, no purpose would be served in requiring a fresh application for planning permission."
"If it is not already clear, I make it absolutely clear now, that if a developer does not comply with a condition he can have enforcement action or any other available action taken against him. The only consequence of the approach indicated in this judgment is that when the merits of the enforcement proceedings come to be considered, it is necessary to take into account the situation as it exists at that time and, in particular, whether or not at that time any approval required by condition has been obtained. The result is therefore that in this case, the operations having been commenced and the application for approval having been made before the expiry of the time-limits, the relevant operations no longer being enforceable against the approval having been obtained prior to the enforcement action, the developers' appeal to the Secretary of State should have been allowed."
"But it seems to me that there must be some flexibility in the manner in which the conditions precedent to an extensive development can be approved. There could be no conceivable prejudice to the purpose of the conditions in what was done. The construction of the spur road did not and could not in any way affect the need for the compliance with the conditions for any further development. This was not a case of waiver but of the Council exercising a proper and sensible discretion in the manner in which it dealt with he conditions. I am satisfied that the works were lawful, as all concerned intended and believed, and that the principle in Whitley is not applicable."
"Thus Condition 11 was in substance complied with. The report had been approved. All that is missing was the formality of a written application and written notice of approval. Furthermore the actual work was in conformity with the plans that had been expressly approved by the council in June 1991, and it was carried out with the full knowledge and co-operation of the planning authority and the highway authority. In these circumstances, in my view, looking at the matter in 1997, it was not only reasonable for the authority to hold permission had been implemented, it would have been wholly unreasonable for them to have decided otherwise."
"… If it had been necessary to do so, I would have expressed my agreement in principle with the view of Woolf J. (as he then was) in Etheridge v. Secretary of State for the Environment (1984) 48 P. & C.R. 35 that a development carried out without permission or commenced in contravention of conditions of a permission would not be development to which the permission related because it was development carried out in breach of planning control and so not permitted. However the importance and nature of the condition and the extent of and the reasons for breach may in some circumstances be relevant considerations and I would prefer to reserve an opinon on the question for a case in which it is necessary to decide it."
"We are not concerned directly with the situation, which undoubtedly can arise, when the planning permission is subject to a condition that the building must be built or the operations carried out in a particular way and yet what was done was at variance with what was foreseen. Those problems I would leave to be considered when they need to be considered."
"It can be seen that both those cases were narrow exceptions to the general principle, one arising where the planning authority had agreed to work starting without compliance and the other where the condition had been met in substance, although not in form. Both decisions accord with normal legal principles."
"The present case cannot, in my view, be brought within either of those two exceptions. It is argued that in standing by and doing nothing when the roadworks started to its knowledge, the defendant in this case was coming close to the position of the authority in Agecrest . I do not accept that. By itself mere failure to act, for example, by failing to serve an enforcement notice, is not to be seen as agreeing to work starting. Nothing in the evidence before me establishes any such agreement by the defendant. Nor patently does the decision in the Flintshire case have any application to the present facts."
"Thus, there is a considerable degree of "flexibility" and "common sense" built into the statutory code. Of particular importance, the procedures in the statutory code ensure that the interests of all parties, neighbours, other developers and landowners, statutory bodes (such as highway and water authorities) and the Secretary of State, are all taken into account at the appropriate stage. It is important at all times to remember the public nature of town and country planning. It is not a matter for private agreement between developers and Local Planning Authorities."
"27. Be that as it may, the important question, as Aldous LJ recognised, is whether the resolution counted as a determination under section 64. Such a determination is a juridical act, giving rise to legal consequences by virtue of the provision of the statue. The nature of the required act must therefore be ascertained from the terms of the statute, including any requirements prescribed by subordinate legislation such as the General Development Order. Whatever might be the meaning of the resolution if it was not a determination within the meaning of the Act, it did not have the statutory consequences. If I may quote what I said in the Mannai case [1997] AC at p776B- "
"In the light of these dicta the court should, in my judgment, be very slow to permit extra statutory "flexibility" or to countenance non-statutory "agreements" between developers and Local Planning Authorities that conditions need not be observed. Agecrest should now be confined to its own particular facts, an express agreement in writing reached in the context of a less comprehensive planning code. The decision is also explicable upon the basis that, on the facts of that case, a legitimate expectation had been created as a result of the Deputy County Planning Officer's agreement at the meeting on 10 th March 1967 and the Clerk of the Council's letter dated 5 th April 1967, from which it would have been an abuse of power for the Local Planning Authority to have resiled, bearing in mind the imminent deadline of 6 th April 1967. I will deal with the question of legitimate expectation under ground (3) below, but unless it can be established that an Agrecrest "agreement" has given rise to a legitimate expectation from which it would be an abuse of power for the Local Planning Authority to resile, I do not see how such an agreement can now be allowed to bypass the statutory code. Mr Elvin submitted that implementation of planning permissions was not dealt with by the statutory code. The code was silent, so judges had been obliged to supplement it, as in Whitley. Where one was dealing with judge-made rules rather then the provisions of the code itself, a measure of flexibility and common sense was both necessary and desirable But the code does address this issue.
"Secondly, and more importantly, I share the concern expressed by Dyson J in Powergen about the sidestepping of the statutory provisions of section 73, with their attendant procedures to protect the interests of third parties and the general public interest. The court should in my view be very slow to find that the principle of legitimate expectation operates so as to keep alive a planning permission that has on the face of it expired because there was no lawful commencement of the development within the time laid down; or, to pursue the matter to the conclusion sought by the claimant in this case, to find that it operates so as to require the grant of a certificate of lawful development in circumstances where on a proper analysis the development would be unlawful. There is nothing in the circumstances of the present case capable of achieving that result. It cannot possibly be said to have been an abuse of power to hold that the planning permission was not lawfully implemented." "
"The following structure shall be added to the list – BRAITHWAITE VIADUCT"
"The surviving 260 metres of a viaduct built by the Eastern Counties Railway Company between 1839 and 1842 to a plan by John Braithwaite, the company architect. It was designed to carry trains into the terminus of Shoreditch Station (later called Bishopsgate Station, then superseded in 1875 by Liverpool Street Station). It was originally about 2 kilometres long and carried two lines of track on a series of broad elliptical vaults. The surviving section contains 21 piers supporting 20 arches. It is built of stock brick from various sources, and the piers are decorated by stone impost bands and rendered plinths. The Gothic style of cross vaulting was an unusual choice, set against the Italianate style of the station building. The structure of the Viaduct is reminiscent of earlier canal architecture than it is of the more standardised railway architecture that was to follow. The piers are pierced by one, two or three pointed cross vaults which allowed pedestrian traffic to travel below the viaduct. This was intended to minimise the disruption to movement in the area and thus, lessen the impact of the railway line on local life. Shoreditch Station was remodelled between 1877 and 1881, and that new development encased the Viaduct between extensive vaults to north and south, the whole supporting a vast goodsyard on the upper deck. The surviving section of the Viaduct was reduced by approximately 2 metres before the bonding of the new vaults to its current width of 14 metres, although the foundations of the original piers survive to their full width. The Braithwaite Viaduct is a very early and rare example of a railway viaduct associated with a first generation London Terminus. Its unusual and individual design and use of materials set it apart both structurally and visually from the more standards forms of railway architecture. It is associated with an important phase of railway development and bridges the period between distinct canal and later distinct railway engineering forms. The Goodsyard was constructed some forty years after the Viaduct, a time from which many more buildings survive and, as PPG15 tells us, greater selection is needed, and that only buildings of definite quality and character are listed. The surviving structures were part of a much larger scheme, the bulk of which was destroyed by fire in 1964. Because of these losses, it too suffers from a lack of context. Ministers have concluded that these factors are so serious that they compromise the quality and character – and, therefore, any special interest – the buildings might have had; the Goodsyard will not be added to the list."
"This proposal is to list the entire structure in grade II. This is wholly appropriate for the bulk of the surviving fabric which dates form 1877-81. The earlier work is of exceptional interest and rarity and requires a greater degree of management control. Consequently, we are also recommending that the 1839-42 Braithwaite Viaduct be scheduled." "
"London Underground will need to obtain Listed Building Consent to demolish the structures adjacent to the Braithwaite."
"All these considerations, and the general tenor of the second sentence of section 54(9) satisfy me that the word "structure" is intended to convey a limitation to such structures as are ancillary to the listed building itself, for example the stable block of a mansion house, or the steading of a farmhouse, either fixed to the main building or within its curtilage. In my opinion the concept envisaged is that of principal and accessory."
"It seems to me that if I were to deny standing to Greenpeace, those it represents might not have an effective way to bring the issue before the Court."
"132. That leaves the issue of standing. As to that, it seems to me that there is an important distinction to be drawn between, on the one hand, a person who brings proceedings having no real or genuine interest in obtaining the relief sought, and on the other hand a person who, whilst legitimately and perhaps passionately interested in obtaining the relief sought, relies as grounds for seeking that relief on matters in which he has no personal interest. 133. I cannot see how it can be just to debar a litigant who has a real and genuine interest in obtaining the relief which he seeks from relying, in support of his claim for that relief, on grounds (which may be good grounds) in which he has no personal interest. 134. It seems to me that a litigant who has a real and genuine interest in challenging an administrative decision must be entitled to present his challenge on all available grounds."
"We have no difficulty in agreeing that the exercise of the court's discretion does not depend on whether it will attract popular support. If Mr Walters' rights have been breached the unpopularity of granting relief to him will not deter the court from granting it. However when there are other genuine interests which will be adversely affected, the court is not prevented from analysing precisely the rights of which a single or a few individuals have been deprived, and their consequent loss (in whatever form it takes) and the consequences of upholding their right contrary to the interests of many others. As the grant of judicial review may have substantial adverse consequences for a large number of blameless individuals beyond he applicant himself, in an appropriate case, of which this is one, the exercise of discretion permits account to be taken of these conflicting interests… .". "
"The real effect of my conclusions is more limited than it would be were I to declare the development of the route or the demolition to be unlawful."