“19. The fact that the Claimants have issued both Part 7 proceedings and judicial review proceedings reflects the fact that the conduct of the franchise competitions engages both public and private law rights and obligations. It would be wrong to view this area of law through a purely public law prism or a purely private law prism. Public and private law coexist as elements of English law and there is no a priori reason of principle that demands primacy for one or the other. It is beyond the scope of this judgment to try to set out the history of the development of either; but that history demonstrates the flexibility of the common law and its ability to recognise rights and fashion remedies to meet particular situations. It also shows the willingness of Parliament to set the bounds of the law which the judges are to interpret and apply where and when it considers it appropriate to do so.”
“36. Pausing at this stage, I summarise the position as follows: i) When dealing with duties such as are alleged in the present litigation, the same facts and matters that are alleged to constitute breach of duty may give rise to both public law challenges and private law claims; ii) There is no legislative requirement that private law claims be brought by judicial review proceedings, though judicial review proceedings may in some circumstances be used as the vehicle for claiming private law remedies such as damages, declaratory relief and injunctions as well as public law remedies; iii) By ss. 2 and 5 of theLimitation Act 1980 the limitation period for an action founded on tort or on simple contract is six years; iv) ByCPR Rule 54.5 , an application for judicial review must be brought promptly and in any event within three months; v) There has been legislative intervention to impose specific time limits for claims arising under the PCR and the UCR. Despite the longstanding existence of Regulation 1370/2007, it has not been implemented by regulations or otherwise in the United Kingdom and there is no specified legislative time limit for bringing private law claims to which Regulation 1370/2007 might apply; vi) The principle of effective protection requires the Court to operate domestic law provisions such as those considered in Uniplex in a way that allows a claim based on EU law grounds of challenge to be brought by reference to the date when the claimant knew or ought to have known of the alleged breach of EU law.”
“47. During submissions the Defendant articulated his submission in relation to the Claimants' private law claims concisely on a number of occasions of which two will suffice. The first was adopting an image for which credit appears to be due to Professor Finnis: see R (Miller) v Secretary of State for Exiting the European Union[2017] 1 WLR 1373 at [63]-[65]: ‘The point we are making is if the initial phase of proving breach is precluded as a matter of public law, then the reservoir of rights in the EU doesn't contain a right to damages and so nothing flows down the conduit pipe. That's the basic point.’ The second, in reply, was: ‘What we are saying is that in these circumstances a successful public law challenge is a pre-condition for a successful private law claim for Francovich damages.’ 48. I am unable to accept this submission, however phrased. In my judgment it reflects a view through a purely public law prism that is supported by neither principle nor authority. 49. The starting point must be the established fact that a claim for damages arising from breach of duties derived from EU law should be regarded as a claim for breach of statutory duty, albeit one that is subject to Francovich conditions: see [15] above. That being so, s. 2 of the Limitation Act is directly applicable and provides a limitation period of 6 years. It is therefore necessary to see if there is any reason to disapply that limitation period and to apply another one. 50. The Defendant's arguments that rely upon the time limits laid down in instruments concerning procurement law are, in my judgment, misconceived. The submission (set out above) that the UK legislator has "consistently" applied a much shorter limitation period to reflect the particular character of the EU-based claim is factually incorrect, since the UK legislature has declined to implement the Railway Regulation and has chosen to exclude railway franchise procurements from the scope of the PCR and the UCR. The Court does not know why the legislature has decided to treat railway franchise procurements differently, but it has. There is therefore no basis for either transposing the time-limits laid down by the PCR and UCR or relying upon them by way of an analogy. Those regulations, where they apply, provide carefully calibrated and balanced bundles of rights and obligations including, for example, the automatic suspension provisions at regulation 95 of the PCR and regulation 110 of the UCR. Given the carve-out which excludes railway franchise procurements from those regulations, it would be impossible to describe provisions for automatic suspension as being "consistently" applied in procurement cases or to argue that they are to be implied in railway franchise procurements. Thus, in the circumstances prevailing at present, all that can be said is that procurement cases are not all treated the same and that railway franchise cases are deliberately treated differently from other categories by the legislature of the United Kingdom. 51. A further submission that was made more than once and which appears fundamental to the Defendant's position was that: ‘We say that it's a basic principle of administrative law that a public law measure is valid if it is not challenged within the relevant time period and as such it cannot form the basis for an action for damages under EU law if it is in fact valid.’ 52. This submission is correct when viewed through a purely public law prism. However, as a matter of principle, it seems to me to ignore the fact that a public authority's acts or omissions may, at least in theory, give rise to enforceable private law rights and remedies without being unlawful in the public law sense of justifying judicial control of administrative action by judicial review. Furthermore, to suggest that a person may not exercise their acknowledged private law rights (which may themselves be contingent upon the continued existence of the behaviour that is criticised) without undertaking and discharging the burden of "invalidating" the offending act of the public authority seems to me to be grossly unfair, particularly if allied to the short time-limits of judicial review. I would not accept such a denial of access to justice unless compelled to do so by binding authority. The Defendant has not identified any authority in either English or European jurisprudence that begins to justify such a conclusion. 53. The submission also seems to me to confuse the purposes of public law and the private law of torts. At one point the Defendant submitted that a longer limitation period for private law claims was unsatisfactory because, with a limitation period of six years, the state would "have to take account of the court's views which may be in several years' time." I do not shrink from that prospect; but what an adverse finding in a tort claim in several years' time will not do is "invalidate" the underlying act as it may be "invalidated" after a process of judicial review. If and to the extent that either the prospect or the reality of an adverse tort claim discourages a tortfeasor from repeating the conduct that is held to constitute a breach of duty or persuades him to change his approach to a particular issue, it will be serving its intended and beneficial function, whether the tortfeasor is a public body or a private individual. This consideration is not, in my judgment, weakened by the fact that (as is often the case) the Defendant in the present case is charged bys. 4(1) of the Railways Act 1993 with promoting improvements in railway service performance or otherwise protecting the interests of users of railway services or otherwise acting in the public interest.”
“77. In the present proceedings, it appears to be at least arguable (for the purposes of the strikeout applications) that the principles laid down in Burkett and Eisai may have application in relation to the public law challenges now mounted by the Claimants against the decision to disqualify them from the franchise procurements. WCTP's skeleton argument puts the point succinctly for all Claimants. Its case is that it "complains here of a decision taken on the basis of a process which was itself unlawful. 78. The potential relevance of Burkett and Eisai was illustrated by Stagecoach in their oral submissions by reference to [30]-[60] of SSETL's Part 7 Particulars of Claim (which are, so far as I have been able to tell, replicated by [34]-[64] of SSETL's Statement of Facts and Grounds). The pleading portrays the process leading up to the disqualification decision as an iterative and ongoing discussion which, despite the apparently hard-edged terms of the ITT and Re-bid instructions, rendered the process fluid and, in Burkett terms, uncertain. One aspect of this approach that Stagecoach emphasised in oral submissions is that SSETL pleads that it had submitted a first rebid in August 2018 which was not compliant, but which did not cause the Defendant to disqualify it. 79. I am not in a position to rule at all on the facts and the case being advanced by the Claimants save to say that the Defendant has not shown to the necessary standard for a strikeout that the Claimants' case discloses no reasonable grounds for relying upon the principles established in Burkett and Eisai or that the Claimants' prospects of success in relation to those principles are fanciful. In reaching this conclusion I have regard to the fact that, in a not-entirely settled area of the law, the final determination of the Court will be fact sensitive and that it is plain from the materials now before the Court that there is evidence (on both sides) that can reasonably be expected to be available at trial that is not available now.”
“86 However, the principle still stands that public law challenges to the validity of public acts, which are subject to the full force of the considerations outlined in O'Reilly v Mackman and [20] of Trim should be brought by judicial review and not otherwise. Once a degree of precision is introduced to discriminate between public law challenges and private law claims, this should pose no difficulty in practice. I would re-state the principle in [20] of Trim by saying that it would be an abuse of process to use private law remedies in an attempt to replicate the effect of a public law challenge that s. 31 requires to be brought by an application for judicial review without submitting to at least the substance of the judicial review procedure laid down byCPR Part 54 including, in particularCPR Part 54 's provisions as to time limits and permission. In the present case it may be said that the Court's case management decision to stay the judicial review means that it is neither automatically nor necessarily an abuse of process to pursue a public law challenge in the Part 7 proceedings; but the general principle is clear and is aimed at preventing the use of private law remedies to try to replicate and in that sense bypass the mandatory provisions of s. 31 andCPR Part 54 without submitting to the substance of the usual restraints of time limits and permission. 87 This does not mean that to include a claim for a declaration or an injunction as a private law remedy is necessarily or even probably an abuse of process in a case that engages both public law and private law rights and remedies. Two reasons support this conclusion. First, the cross-over remedies are discretionary and, provided their deployment is not merely an attempt to bypass s. 31 andCPR Part 54 , may prove to be useful (or not) at the conclusion of a case, particularly when it is a case as complicated as the present one. Second, it is clear that one reason why the Claimants have, to a greater or lesser extent, pleaded the kitchen sink and issued both Part 7 and judicial review proceedings is to avoid just the sort of jurisdictional wrangling that has ensued: see Clark v University of Lincolnshire and Humberside[2000] 1 WLR 1988 at [27]-[37] per Lord Woolf MR.”
“… must be started within 30 days beginning with the date when the economic operator knew or ought to have known that grounds for starting the proceedings had arisen.”
“26. Invitations to tender for franchises (1)Unless the Secretary of State otherwise directs, the person who is to be the franchisee under any franchise agreement shall be selected by the Franchising Director from among those who submit tenders in response to an invitation to tender under this section for the right to provide, or to secure that a wholly owned subsidiary provides, services for the carriage of passengers by railway under that franchise agreement. (2)The Franchising Director shall prepare any such invitation to tender and shall issue that invitation to such persons as he may, after consultation with the Regulator, think fit. (3)The Franchising Director shall not issue an invitation to tender under this section to (or entertain such a tender from) any person unless he is of the opinion that the person has, or is likely by the commencement of the franchise term to have, an appropriate financial position and managerial competence, and is otherwise a suitable person, to be the franchisee.”
“Where the High Court considers that there has been undue delay in making an application for judicial review, the court may refuse to grant – (a) Leave for the making of the application; or (b) Any relief sought on the application, If it considers that the granting of the relief sought would be likely to cause substantial hardship to, or substantially prejudice the rights of, any person or would be detrimental to good administration.”
“(A1) In this rule — 'the planning acts' has the same meaning as insection 336 of the Town and Country Planning Act 1990 'decision governed by thePublic Contracts Regulations 2015 ' means any decision the legality of which is or may be affected by a duty owed to an economic operator by virtue of regulations 89 or 90 of those Regulations (and for this purpose it does not matter that the claimant is not an economic operator); and 'economic operator' has the same meaning as in regulation 2(1) of the Public Contracts.Regulations.2015. (1) The claim form must be filed – (a) promptly; and (b) in any event not later than 3 months after the grounds to make the claim first arose. (2) The time limits in this rule may not be extended by agreement between the parties… (6) Where the application for judicial review relates to a decision governed by thePublic Contracts Regulations 2015 , the claim form must be filed within the time within which an economic operator would have been required by regulation 92(2) of those Regulations (and disregarding the rest of that regulation) to start any proceedings under those Regulations in respect of that decision.”
“Now that those disadvantages to applicants have been removed and all remedies for infringements of rights protected by public law can be obtained upon an application for judicial review, as can also remedies for infringements of rights under private law if such infringements should also be involved, it would in my view as a general rule be contrary to public policy, and as such an abuse of the process of the court, to permit a person seeking to establish that a decision of a public authority infringed rights to which he was entitled to protection under public law to proceed by way of an ordinary action and by this means to evade the provisions of Order 53 for the protection of such authorities. My Lords, I have described this as a general rule; for though it may normally be appropriate to apply it by the summary process of striking out the action, there may be exceptions, particularly where the invalidity of the decision arises as a collateral issue in a claim for infringement of a right of the plaintiff arising under private law, or where none of the parties objects to the adoption of the procedure by writ or originating summons. Whether there should be other exceptions should, in my view, at this stage in the development of procedural public law, be left to be decided on a case to case basis — a process that your Lordships will be continuing in the next case in which judgment is to be delivered today [Cocks v. Thanet District Council[1983] 2 A.C. 286].”
“... But it is inherent in the scheme of the Act that an appropriate public law decision of the housing authority is a condition precedent to the establishment of the private law duty.”
“It is appropriate that an issue which depends exclusively on the existence of a purely public law right should be determined in judicial review proceedings and not otherwise. But where a litigant asserts his entitlement to a subsisting right in private law, whether by way of claim or defence, the circumstance that the existence and extent of the private right asserted may incidentally involve the examination of a public law issue cannot prevent the litigant from seeking to establish his right by action commenced by writ or originating summons...”
“The general rule of procedural exclusivity judicially created in O'Reilly v. Mackman[1983] 2 A.C. 237was at its birth recognized to be subject to exceptions, notably (but not restricted to the case) where the invalidity of the decision arises as a collateral matter in a claim for infringement of private rights. The purpose of the rule was stated to be prevention of an abuse of the process of the court, and that purpose is of prime importance in determining the reach of the general rule: compare Mercury Communications Ltd. v Director General of Telecommunications [1996] 1 W.L.R. 48, 57e, per Lord Slynn of Hadley. Since O’Reilly v Mackman decisions of the House of Lords have made clear that the primary focus of the rule of procedural exclusivity is situations in which an individual's sole aim was to challenge a public law act or decision. It does not apply in a civil case when an individual seeks to establish private law rights which cannot be determined without an examination of the validity of a public law decision. Nor does it apply where a defendant in a civil case simply seeks to defend himself by questioning the validity of a public law decision. These propositions are established in the context of civil cases by four decisions of the House of Lords: Roy v Kensington Family Practitioner Committee [1992] 1 A.C. 624; Chief Adjudication Officer v Foster [1993] A.C. 754; Wandsworth London Borough Council v Winder [1985] A.C. 461 and in particular at pp.509–510, per Lord Fraser of Tullybelton; Mercury Communications Ltd v Director General of Telecommunications [1996] 1 W.L.R. 48and in at p.57b–e, per Lord Slynn of Hadley.”
“Subsequent experience has shown that a clear division between public and private law is often difficult to maintain, and the rigidity of the rule has had to be relaxed accordingly. Wade & Forsyth, Administrative Law, 10th ed (2007), pp 570–581 gives a valuable description of this evolutionary process, leading to the emergence of “signs of liberality”, and to some abatement of the “rigours of exclusivity” under the new Civil Procedure Rules. A particular area of difficulty was in relation to private law disputes involving public authorities, for example employment and contractual relations: p 572. In.Roy v Kensington and Chelsea and Westminster Family Practitioner Committee[1992] 1 AC 624 , the scope for relaxation of the rule was acknowledged by the House of Lords, when they accepted that private law rights could be enforced by civil action, even though they might involve a challenge to a public law decision or action.”
“36. Each side accepts that this claim could have been brought by an application for judicial review or by ordinary action; they differ in the appropriateness of one type of proceeding over another. In my view it was to just this situation that the judgments of Lord Woolf and Sedley LJ in Clarkwere directed. I conclude that the jurisdiction to which they referred exists where the remedies both of judicial review and of ordinary action are available. The choice of either may be an abuse of the process. How to exercise that jurisdiction will depend on all the relevant circumstances including matters occurring before the proceedings were instituted and which remedy is in the circumstances the more appropriate... 47. I start with a consideration of the nature of the proceedings. The decision of the Divisional Court in Factortame V to which I have referred in paragraph 12 was considered by the Court of Appeal ([1998] EuLR 456) and the House of Lords ([2000] 1 AC 524 ), but not with regard to the claim for exemplary damages which had been abandoned. In both those courts there was clear recognition that the effect of Francovich and subsequent cases was to subject Member States to an obligation under Community Law to compensate individuals who have sustained consequential loss if they satisfy the conditions identified by the ECJ in those cases. Such an obligation gives rise to a correlative right in one who has suffered such damage. Such a right is not discretionary. 48. Nor in my view can such a right be categorised as a public law right even though the Crown's obligations under Community Law and how to discharge them fall to be considered. As in the context of the Limitation Act, the remedy is for damages for breach of a statutory duty arising under Article 8.2 of the Rental Directive and s. 2(2) European Communities Act. This is recognised by the relief sought in the form of a declaration and damages. Counsel for PPL accepted that a declaration was a discretionary remedy but offered to abandon it if that mattered. 49. Neither party referred me to the provisions ofCPR Part 54 . Nevertheless it appears to me that though the nature of the proceedings might fall within the definition of a claim for judicial review in Rule 54.1(2)(a) if the claim for a declaration is abandoned it would be excluded by Rule 54.3(2). I do not suggest that the form of the proceedings can govern their substance but, to my mind, this confirms the view that the proceedings are essentially private law proceedings which can and prima facie should be brought by an ordinary claim.”
“15. Against this background we can express our reasons for dismissing the appeal in a very few words. The Irish Dairy Board's claim for damages is admittedly based upon alleged private law rights whether or not it is also based upon public law rights. If it can make good its case on the facts and the private law, the court will have no discretion whether or not to grant relief. The Order 53procedure is wholly inappropriate to any non-discretionary claim and the prosecution of such a claim by the procedure of an action is in no way an abuse, or as we prefer to style it 'a misuse', of the process of the court. It is a completely proper use of that process. The claim for an injunction does indeed enable the court to exercise a discretion, but only as to the choice of remedy, i.e. damages or injunction, not as to granting any remedy at all. Although the plaintiffs would, if necessary, have contended that there are no public law issues, we assume for present purposes that Neill J. was right to reject this contention. However, we can see no way in which they can be severed from the private law issues and, if they can, we do not think that they should be. As it was put in argument, the public and private law issues were not even collateral one to another. They are inextricably mixed— 'homogenised' is the term which springs to mind in the context of the subject matter of the dispute.”
“68. I should follow the decision of the Vice-Chancellor unless I were convinced that he was wrong, which I am not. On the contrary, I respectfully agree with his reasoning and the result, both of which were substantially endorsed in Energy Solutions. It reinforces my view that the Defendant is wrong in his submissions to characterise the Claimants' private law claims as “quintessentially a public law claim.”
“all the obligations on which the claimants rely, apart from the implied contract, are in substance binding on the Secretary of State as a public body performing the role that that public body is required to perform under Regulation 1370.”
“…as Lord Woolf M.R.... explains in his judgment, the CPR now enable the court to prevent the unfair exploitation of the longer limitation period for civil suits without resorting to a rigid exclusionary rule capable of doing equal and opposite injustice. Just as on a judicial review application the court may enlarge time if justice so requires, in a civil suit it may now intervene, notwithstanding the currency of the limitation period, if the entirety of circumstances – including of course the availability of judicial review – demonstrates that the court’s processes are being misused, or if it is clear that because of the lapse of time or other circumstances no worthwhile relief can be expected.” 107.In the same case, Lord Woolf said: “34. The courts approach to what is an abuse of process has to be considered today in the light of the changes brought about by the CPR. Those changes include a requirement that a party to proceedings should behave reasonably both before and after they have commenced proceedings. Parties are now under an obligation to help the court further the over-riding objectives which include ensuring that cases are dealt with expeditiously and fairly (CPR 1.1 (2)(d) and 1.3). They should not allow the choice of procedure to achieve procedural advantages. The CPR are as Part 1.1(1) states a new procedural code. Parliament recognised that the CPR would fundamentally change the approach to the manner in which litigation would be required to be conducted. That is why theCivil Procedure Act 1997 (Section 4(1) and (2) ) gives the Lord Chancellor a very wide power to amend, repeal or revoke any enactment to the extent he considers necessary or desirable in consequence of the CPR. 35. While in the past, it would not be appropriate to look at delay of a party commencing proceedings other than by judicial review within the limitation period in deciding whether the proceedings are abusive this is no longer the position. While to commence proceedings within a limitation period is not in itself an abuse, delay in commencing proceedings is a factor which can be taken into account in deciding whether the proceedings are abusive. If proceedings of a type which would normally be brought by judicial review are instead brought by bringing an ordinary claim, the court in deciding whether the commencement of the proceedings is an abuse of process can take into account whether there has been unjustified delay in initiating the proceedings… 38. Where a student has, as here, a claim in contract, the court will not strike out a claim which could more appropriately be made under Order 53 solely because of the procedure which has been adopted. It may however do so, if it comes to the conclusion that in all the circumstances, including the delay in initiating the proceedings, there has been an abuse of the process of the court under the CPR. The same approach will be adopted on an application under Part 24. 39. The emphasis can therefore be said to have changed since O'Reilly v Mackman. What is likely to be important when proceedings are not brought by a student against a new university under Order 53, will not be whether the right procedure has been adopted but whether the protection provided by Order 53 has been flouted in circumstances which are inconsistent with the proceedings being able to be conducted justly in accordance with the general principles contained in Part 1. Those principles are now central to determining what is due process. A visitor is not required to entertain a complaint when there has been undue delay and a court in the absence of a visitor should exercise its jurisdiction in a similar way. The courts are far from being the ideal forum in which to resolve the great majority of disputes between a student and his or her university. The courts should be vigilant to ensure their procedures are not misused. The courts must be equally vigilant to discourage summary applications which have no real prospect of success.”
“42. The core of the reasoning of the Court of Appeal is that “the impugned environmental impact statement was as necessary to the resolution as to any subsequent steps [and] the logic of measuring time from the resolution seems inescapable”
“69. That brings me to the question of relief. It is at this point that I must consider Mr Giffin's submission that Eisai should be refused relief unders.31(6)(b) of the Supreme Court Act 1981 on grounds of its delay in applying for judicial review. The argument is that the refusal to supply the fully executable version was the subject of a clear decision by NICE which was capable of being challenged at the time; yet Eisai waited some 18 months, until the end of the appraisal process, before mounting its challenge. There was a failure to apply within the time limit laid down inCPR 54.5 (1) ("promptly and in any event not later than 3 months after the grounds to make the claim first arose"), and there was therefore "undue delay" within the meaning of the statute. Had a prompt challenge been made, the court would have entertained it at that time, rather than allowing the appraisal process to continue for over a year in circumstances of doubt as to its lawfulness. 70. I do not accept that the court would have viewed an early challenge in that way. It is more likely that such a challenge would have been considered premature and inappropriate. At the time when NICE refused to release the fully executable version, it was uncertain what the outcome of the appraisal process would be. The Final Appraisal Determination might have proved to be acceptable to Eisai, in which case the issue concerning release of the fully executable version would have been academic. Further, and very importantly, Eisai had a right of appeal to the Appeal Panel against that determination, and the grounds on which such an appeal lay included procedural unfairness. That might well have been viewed as providing an appropriate alternative remedy, rendering a judicial review challenge inappropriate at that stage. 71. Even if there had been undue delay in applying for judicial review, it would only be a factor to be taken into account in the exercise of the court's discretion as to the grant of relief; and in the light of the matters set out below it would in my view be of no materiality.”
“26. I cannot accept that the right of action alleged by Jobsin first arose on 17th November. In my view, it arose on or about 14th August. It is clear that, as soon as the Briefing Document was issued without identifying the criteria by which the most economically advantageous bid was to be assessed, there was a breach of regulation 21(3). I do not understand Mr Lewis to dispute this. Moreover, it was a breach in consequence of which Jobsin, and indeed all other tenderers too, were then and there at risk of suffering loss and damage. It is true that it was no more than a risk at that stage, but that was enough to complete the cause of action. Without knowing what the criteria were, the bidders were to some extent having to compose their tenders in the dark. That feature of the tender process inevitably carried with it the seeds of potential unfairness and the possibility that it would damage the prospects of a successful tender. 27. Mr Lewis submits that neither the loss nor the risk of loss was caused by the breach of regulation 21(3) until Jobsin was excluded from the tender process on 17th November. I reject that submission for the following reasons. First, it gives no meaning to the words "risks of suffering loss or damage" in regulation 32(2). It seems to me that those words are of crucial significance. They make it clear that it is sufficient to found a claim for breach of the regulations that there has been a breach and that the service provider may suffer damage as a result of the breach. It is implicit in this that the right of action may and usually will arise before the tender process has been completed. 28. That brings me to the second reason. It would be strange if a complaint could not be brought until the process has been completed. It may be too late to challenge the process by then. A contract may have been concluded with the successful bidder. Even if that has not occurred, the longer the delay, the greater the cost of re-running the process and the greater the overall cost. There is every good reason why Parliament should have intended that challenges to the lawfulness of the process should be made as soon as possible. They can be made as soon as there has occurred a breach which may cause one of the bidders to suffer loss. There was no good reason for postponing the earliest date when proceedings can begin beyond that date.”
“13. The vast majority of procurement disputes arise either from a challenge to the legality of the tender documents, or a challenge to the award of a contract following the tender process. If there is a challenge to the legality of the tender documents, then the challenger must commence proceedings within 30 days. Indeed, it is vital that such a challenge is made in that time because the challenger's cause of action accrues when the defective tender documentation is published, not when a contract is awarded on the basis of that unlawful documentation: see Jobsin … 15. Of course, from a procedural point of view, a party seeking to challenge the lawfulness of the tender documentation may have a difficult decision to make. Assuming its court proceedings challenging the tender documents are up and running within the 30 days, the challenger then has to decide whether or not to seek an injunction to prevent the process from continuing on the basis of documents which it contends are unlawful. In my experience, applications for interlocutory injunctions at that early stage are relatively rare. That may be because the challenger will often remain involved in the tender process and is content to await the outcome of that process before seeking urgent relief from the court, or it may be because the challenger has accepted that the alleged illegality has excluded him from the contract award process and is content to seek damages as a remedy. 16. The infrequency of applications for interim injunctions at the tender stage may also be explained by a more pragmatic factor. It is only in the more straightforward cases that a challenger will be able to demonstrate, on an interlocutory basis, the unlawfulness of the tender documentation and that very often, an interim challenge may face something of an uphill struggle.”
“78. The MOD submits it is not open to MLS to base its case on any ambiguity in the ITT because such complaint was not pleaded and would be out of time. However, that is a mischaracterisation of MLS’s case. MLS submits that it was unlawful for the MOD to reject its tender based on criteria that were not set out clearly, or at all, in the ITT.”