“1. REQUIRED OUTCOMES 1.1 The Service Provider shall comply with the provisions of this Performance Standard 1 and ensure that at the end of the Core Investment Period and thereafter until the expiry of the Contract Term in relation to the Project Network: 1.1.1 no Road Section Lengths in each of PFI Districts 1 to 12 (inclusive) are Failed; 1.1.2 no Road Section Lengths on each of the Network Route Hierarchies except the Local Access Route Network in each of PFI Districts 1 to 12 (inclusive) have an SRI of less than 1.2; 1.1.3 no Footway Section Lengths, Verge Section Lengths, Kerb Section Lengths or Cycling Track Section Lengths are Poor or below; …” 1.1 The Service Provider shall comply with the provisions of this Performance Standard 1 and ensure that at the end of the Core Investment Period and thereafter until the expiry of the Contract Term in relation to the Project Network: 1.1.1 no Road Section Lengths in each of PFI Districts 1 to 12 (inclusive) are Failed; 1.1.2 no Road Section Lengths on each of the Network Route Hierarchies except the Local Access Route Network in each of PFI Districts 1 to 12 (inclusive) have an SRI of less than 1.2; 1.1.3 no Footway Section Lengths, Verge Section Lengths, Kerb Section Lengths or Cycling Track Section Lengths are Poor or below; …”
“2.3 Project Network Model 2.3.1 Where the Authority notifies the Service Provider of a change to the Project Network in accordance with this Contract, the Service Provider shall ensure that all information provided to the Service Provider by the Authority relating to such change is input into the Project Network Model within five (5) Business Days of the date of such notification unless otherwise agreed between the parties. 2.3.2 On each occasion where the Project Network Model is updated in accordance with paragraph 2.3.1 the Service Provider shall provide the Authority with an electronic copy of the updated Project Network Model within one (1) Business Day of the date on which the Project 2.3.1 Where the Authority notifies the Service Provider of a change to the Project Network in accordance with this Contract, the Service Provider shall ensure that all information provided to the Service Provider by the Authority relating to such change is input into the Project Network Model within five (5) Business Days of the date of such notification unless otherwise agreed between the parties. 2.3.2 On each occasion where the Project Network Model is updated in accordance with paragraph 2.3.1 the Service Provider shall provide the Authority with an electronic copy of the updated Project Network Model within one (1) Business Day of the date on which the Project 2.3.3. The Service Provider shall, from the Service Commencement Date, notify the Authority on a monthly basis of any amendments it would recommend to be made to the Project Network Model specifying all details and the reasons for such recommendation.”
“1.1.1 NCImain in respect of a Road Section Length (“RSL”) on the Strategic Route and Main Distributor Network is calculated in accordance with the following formula: NCImain = PCImain + SRImain + SRImain where: PCImain is calculated in accordance with paragraph 3; SRImain is calculated in accordance with paragraph 4; and SCImain is calculated in accordance with paragraph 5”
“3.2.4 Where the survey undertaken in accordance with paragraph 3.1.1 reveals that the length of the relevant RSL is more than 5%, but less than 10% over or under the length for that RSL recorded in the Project Network Model, then, provided that the Service Provider can demonstrate the accuracy of its measurement to the satisfaction of the Authority then the Service Provider shall amend the Project Network Model accordingly and the existing survey data shall be used in the PCI calculation. 3.2.5 Where the survey undertaken in accordance with paragraph 4.1.1 reveals that the length of the relevant RSL is 10% or more over or under the length for that RSL recorded in the Project Network Model, then the RSL shall be resurveyed. Where the Service Provider can demonstrate the accuracy of its original RSL length measurement via the re-survey to the satisfaction of the Authority then the Service Provider shall amend the Project Network Model and align any associated condition data accordingly and the data from the resurvey shall be used in the PCI calculation.”
“PS8T = the sum of any Adjustments due in relation to Performance Standard 8 calculated in accordance with paragraph 3.10 of this Part 1 of schedule 4 (Payment Mechanism) in respect of the month that is three (3) months prior to the Month to which the MUC relates.”
“1. The Service Provider shall carry out those inspections, surveys, tests and assessments that it is required to carry out during the Contract Term, pursuant to clause 6 (Surveys and Inspections) of this Contract and in accordance with Method Statement 13 (Inspections, Assessments and Monitoring). 2. This schedule 11 sets out the specific Monitoring Methods required to monitor performance of the Services described in schedule 2 (Output Specification). In respect of each Monitoring Method set out within this schedule 11, the Service Provider shall carry out monitoring against the Performance Targets as set out in schedule 2 (Output Specification). In addition, in respect of certain Performance Targets as set out below, the Service Provider shall carry out monitoring as specifically described in this schedule 11. 3. Monitoring Method A The Service Provider shall carry out those inspections, surveys, tests and assessments to enable the Service Provider and the Authority to run the NCI Calculation Methodology, the FWCI Calculation Methodology, the KBCI Calculation Methodology, the VGCI Calculation Methodology and the CTCI The Service Provider shall carry out those inspections, surveys, tests and assessments to enable the Service Provider and the Authority to run the NCI Calculation Methodology, the FWCI Calculation Methodology, the KBCI Calculation Methodology, the VGCI Calculation Methodology and the CTCI Calculation Methodology at least once by 1 November of each Contract Year.”
“The data entered into the approved Pavement Management Model is delivered from two streams and may consist of: • updated PCI, SCI and SRI survey data and/or • re-setting of PCI, SCI and SRI following completion of interventions to individual RSLs. For updated survey data the Independent Certifier shall validate through a 5% sample check of data that any updated survey results were obtained as follows: ... • SCI – DVI data collected in accordance with the latest version of the UKPMS Survey Manual using accredited DVI Inspectors … • The Independent Certifier shall run a report from the PMM to confirm that the most up to date data has been input to the PMM.” • updated PCI, SCI and SRI survey data and/or • re-setting of PCI, SCI and SRI following completion of interventions to individual RSLs. • SCI – DVI data collected in accordance with the latest version of the UKPMS Survey Manual using accredited DVI Inspectors … • The Independent Certifier shall run a report from the PMM to confirm that the most up to date data has been input to the PMM.”
“2.1.2 The Independent Certifier shall carry out the Initial Services set out in paragraph 2.2 (Certification of Milestones) in accordance with schedule 15 (Milestone Completion Criteria) of the Project Agreement, and in particular in respect of each criteria (as listed in column 1 of the table in schedule 15 (Milestone Completion Criteria) of the Project Agreement), the Independent Certifier shall carry out the relevant test (as detailed in column 3 of the table in schedule 15 (Milestone Completion Criteria) of the Project Agreement) in accordance with the relevant test procedure set out in column 4 of the table in schedule 15 (Milestone Completion Criteria) of the Project Agreement in connection with the certification of Milestones pursuant to clause 13.2 (Certification of Milestones) of the Project Agreement.” (Certification of Milestones) of the Project Agreement.”
“(i) That ABHL’s obligations to perform the Core Investment Works and meet the requirements of Performance Standard 1 extend to the Project Network as a whole and are not limited to the RSLs as recorded in the Project Network Model contained in DRD0626. (ii) That ABHL must update the Project Network Model and maintain a Project Network Inventory which accurately reflects the actual extent of the Project Network and the Project Road. (iii) That the Certificates of Completion for Milestones 6 to 9 inclusive be set aside, alternatively opened up, reviewed and revised and the relevant calculations performed again by reference to the actual Project Network Inventory.”
“i) That if the Adjudicator’s argument was correct then the first part of the clause was entirely otiose; ii) If there was a freestanding obligation to update the PNM then it would not be added to the end of the clause; iii) The Project Agreement was highly regimented and therefore it is possible to track the obligation to update into Schedule 2, PS8, paragraph 2.3.1 and 2.3.2 but not so for those additional words. iv) It was not in accordance with the thrust of the clause or indeed PS8. v) The need to update the MIS, was carefully prescribed in PS8 but the same was not true for the PNM. vi) No remedial consequences are provided for breach of clause 19.2.1 which is in the sole remedies list in Annexure 14 to the Project Agreement. vii) Reference can be made to clause 43.1.1.2 which requires ABHL to maintain and update the MIS. No similar provision is made in respect of the PNM. viii) As a basic inconsistency between the first part of those and those latter words. ix) Such a clause would also be inconsistent with Schedule 2, Part 11, which refers to the need to amend the PNM in certain limited circumstances. x) Those words at the end of the clause are not otiose and, thus, the meaning to be given to those additional words is read correctly to indicate that the obligation is to ensure the information is correct. xi) The obligation at the end of the Contract Term to return the PNM is referable to Schedule 8 and not clause 19.”
“On reflection I have come to the conclusion that for a party to rely on a manifest error in a certificate does not depend upon his ability to demonstrate the error immediately and conclusively. In the present case, the guarantors were able to recognise immediately that the certificate was based upon the interest rates as set out in the original loan agreement and not as varied in November 2004. They could see that it was manifestly incorrect. They could not immediately demonstrate that conclusively; they could not do so until the court had determined the issue of variation. But they were right, as this court has now held. I would hold that the certificate was manifestly incorrect and was of no effect.”
“Note: the actual indices achieved shown in Table 1.9b are calculated using the original Pavement Management Model. The Independent Certifier recognises that the Authority and the Service Provider are in dispute regarding the validity of the Project Network Model and Project Network Inventory and any change to the Project Network Model or Project Network Inventory could change the numbers in Table 1.9b.”