“That the Certificates of Completion for Milestones 6-9 inclusive be set aside alternatively opened up, reviewed and revised and the relevant calculations performed again by reference to the actual Project Network Inventory.”
“You have to date withheld a total sum of£15,260,267.17 from the Monthly Payment otherwise due to ABHL on the basis that no Milestones beyond Milestone 5 have been achieved. … We therefore notify you pursuant to clause 45.4 of the Project agreement that, for the reasons set out above and as a result of the judgement, you have wrongfully underpaid ABHL the sum of£15,260,267.17 and that you are obliged to adjust the next Monthly Payment which falls 30 business days after the date of this notice, to account for this underpayment and interest.”
“You should note that this letter constitutes a formal demand within the meaning of limb (b) of the definition of an Authority Default in Schedule 1 of the Project Agreement. Failure topay within twenty Business Days of service of this formaldemand shall constitute an Authority Default.” (Emphasis in the original)
“We write further to your two letters of25 November 2016 , including the purported threat of Authority Default if the sum of£15,260,267.17 is not repaid by23 December 2016 … . We are disappointed that you have not taken up the suggested consensual way forward suggested in our letter of15 December 2016 . In the spirit of fostering a positive relationship between our two organisations, BCC has, without prejudice to its legal position that the sum is not payable, decided to repay the above amount under protest, but on condition that such monies will be repaid in the event of a successful appeal in relation to the judgment … . For the avoidance of doubt, we also reiterate that such payment is made on a pragmatic basis, under protest, and without any admission that the threat of Authority Default has been properly asserted by ABHL. …”
“You will be aware that BCC has deducted Disputed Sums of£4,724,945.60 between September 2016 and December 2016 on the basis that the MAF should be paid at Milestone 5 level (“Further Disputed Sums”). BCC’s position in relation to the Milestones achieved has not changed and we continue to dispute the basis for payment of the Further Disputed Sums. However, acting in good faith and in order to demonstrate our commitment to the on-going relationship, we are prepared to make payment of these Further Disputed Sums, together with interest of£21,360.63 (giving a total of£4,746,306.23 ). This payment is made on the same conditions as set out in our letter dated22 December 2016 , i.e.: these monies will be repaid in the event of a successful appeal in respect of the Judgment or a subsequent adjudication decision …;” these monies will be repaid in the event of a successful appeal in respect of the Judgment or a subsequent adjudication decision …;”
“… the law [should] be slow to hold that a creditor, who has been paid more than he is owed by a debtor who has made it clear in advance that he expects to receive the overpayment back if he turns out to be right, should be entitled to keep the overpayment.”
“ABHL contends that the dates upon which their performance necessary to the achieving of Milestones 6 to 9 was in fact achieved should be retrospectively calculated, such that there can be determined the dates on which each of the latter Milestones would have been certified, had ABHL made application in accordance with the terms of the Contract.”
“The Certificates of Completion for Milestones 6 to 9 should be set aside for manifest error and recalculated on the correct basis (i.e. using the Models as updated …) and the current condition should be calculated on the same basis.”
“MAF = 0.6 + Milestone step-up.” v) Milestone step-up is calculated in accordance with a further formula set out at [1.6] of Schedule 4, namely: “Milestone step-up = the sum of the relevant step up values specified by Table 1 below being attributable to the Milestone Completion or Partial Milestone Completion (as applicable) in accordance with clause 9.”
“Where the Independent Certifier has issued a Certificate of Completion in respect of a Milestone pursuant to the provisions of clause 13 (Certification) that Milestone shall, from the relevant Milestone Completion Date, be taken into account for the purposes of calculating the Monthly Unitary Charge in accordance with paragraph 1.4 of the Payment Mechanism.”
“In respect of each Milestone … the Milestone Completion Date shall be the date upon which the Certificate of Completion is issued for that Milestone, provided that if a Certificate of Completion is issued before the relevant Planned Milestone Completion Date, the Milestone Completion Date shall be the same as the Planned Milestone Completion Date; …” x) Clause 13.5 is entitled “Effect of Issue of Certificates of Completion etc”