“The Charterers hereby undertake the obligation/responsibility to make thorough investigations and every arrangement in order to ensure that the last voyage of this Charter will in no way exceed the maximum period under this Charter Party. If, however, Charterers fail to comply with this obligation and the last voyage will exceed the maximum period, should the market rise above the Charter Party rate in the meantime, it is hereby agreed the charter hire will be adjusted to reflect the prevailing market level from the 30th day prior to the maximum period date until actual redelivery of the vessel to the Owners.”
“The charterer gives orders for the employment of the vessel which cannot reasonably be expected to be performed by the final terminal date [that is, the date by which the charterer is contractually obliged to redeliver the vessel]. He is therefore seeking to avail himself of the services of the vessel at a time when the owner had never agreed to render such services. It is accordingly an order which the charterer is not entitled to give … and in giving it the charterer commits a breach of contract (perhaps a repudiatory breach but that we need not decide). The owner need not comply with such an order because he never agreed to do so. Alternatively, he may comply with the order although not bound to do so: if he does comply, he is entitled to payment of hire at the charterparty rate until redelivery of the vessel and (provided he does not waive the charterers’ breach) to damages (being the difference between the charter rate and the market rate if the market rate is higher than the charter rate) for the period between the final terminal date and redelivery. In the further alternative, if (which we do not decide) the charterer’s breach is repudiatory, the owner may accept the repudiation, treat the charter as at an end and claim damages. … the charterer’s order is illegitimate because he was not contractually entitled to give it, and the voyage (whether performed or not) is stigmatised as illegitimate because it is one the charterer could not under the charter-party lawfully require the owner to perform.”
“If the charterer sends the vessel on an illegitimate last voyage – that is, a voyage which it cannot be expected to complete within the charter period, then the shipowner is entitled to refuse that direction and call for another direction for a legitimate last voyage. If the charterer refuses to give it, the shipowner can accept his conduct as a breach going to the root of the contract, fix a fresh charter for the vessel, and sue for damages. If the shipowner accepts the direction and goes on the illegitimate last voyage, he is entitled to be paid – for the excess period – at the current market rate, and not at the charter rate … The hire will be payable at the charter rate up to the end of the charter period, and at the current market rate for the excess period thereafter.”
“In awarding compensation for breach of contract various interests may have to be considered, such as expectation, reliance and restitution. Here the relevant interest is the owners’ expectation interest. That expectation was always to receive no more than the charter-party rate until April 14 if the charterers availed themselves of the optional tolerance. To award the owners a higher market rate for the period up to April 14 is to confer on them an unwarranted windfall.”
“Whatever the charterer may order, a service which falls outside the range encompassed by the owner’s original promise is not one that he can be compelled to perform; and this is so as regards not only the duration of the chartered service, but also all the other limitations imposed by the charterparty on the charterer’s freedom of choice. There is thus to be a measuring of the service called for against the service promised. As a matter of common sense, it seems to me that the time for such measurement is, primarily at least, the time when performance falls due.”
“The fact which distinguishes this case from The Olanda is that, in the words of Bailhache J, “it is not and could not be pretended that in loading general merchandise the charterers thought that they were within their contractual rights. They knew that they were not. They did not load under the charterparty, and as they did not and knew that they did not” the charterparty rate for steel did not apply. The position in law seems to me to be this: an offer of this cargo by the charterers to the shipowners with a request that they will carry for a reasonable remuneration so much as is not within the charterparty and the remainder on the terms of the charterparty so far as applicable. The owners were at liberty to accept that offer and to sue for reasonable remuneration for carrying the cargo other than the steel billets. The principle of this case is not distinguishable from a well-settled principle of the law as to the sale of goods. If I order from a wine merchant twelve bottles of whiskey at so much a bottle and he sends me ten bottles of whiskey and two of brandy and I accept them, I must pay a reasonable price for the brandy. That is the position here.”
“[Owners’] expectation was always to receive no more than the charter-party rate until April 14 if the charterers availed themselves of the optional tolerance. To award the owners a higher market rate for the period up to April 14 is to confer on them an unwarranted windfall”
“If the orders are accepted and the last voyage overruns, the owner is entitled to be paid for the overrun at the market rate. All this is well known to the parties.”
“The essence of a penalty is a payment of money stipulated as in terrorem of the offending party; the essence of liquidated damages is a genuine covenanted pre-estimate of damage. … The question whether a sum stipulated is a penalty or liquidated damages is a question of construction to be decided upon the terms and inherent circumstances of each particular contract, judged as at the time of the making of the contract, not as at the time of breach. ... To assist this task of construction various tests have been suggested, which if applicable to the case under consideration may prove helpful, or even conclusive. … It will be held to be a penalty if the sum stipulated for is extravagant and unconscionable in amount in comparison with the greatest loss that could conceivably be proved to have followed from the breach.”
“… whether a provision is to be treated as a penalty is a matter of construction to be resolved by asking whether at the time the contract was entered into the predominant contractual function of the provision was to deter a party from breaking the contract or to compensate the innocent party for breach. That the contractual function is deterrent rather than compensatory can be deduced by comparing the amount that would be payable on breach with the loss that might be sustained if breach occurred.”
“I have also have found valuable Colman J's further observation in Cine Bes at pp.763g-764a, which indicate that a dichotomy between a genuine pre-estimate of damages and a penalty does not necessarily cover all the possibilities. There are clauses which may operate on breach, but which fall into neither category, and they may be commercially perfectly justifiable. In the case before him, Colman J was concerned with a provision for prospective increase in the interest rate payable by a borrower, following the borrower's default. He said that, although the payment of liquidated damages is "the most prevalent purpose" for which an additional payment on breach might be required under a contract “…. the jurisdiction in relation to penalty clauses is concerned not primarily with the enforcement of inoffensive liquidated damages clauses but rather with protection against the effect of penalty clauses. There would therefore seem to be no reason in principle why a contractual provision the effect of which was to increase the consideration payable under an executory contract upon the happening of a default should be struck down as a penalty if the increase could in the circumstances be explained as commercially justifiable, provided always that its dominant purpose was not to deter the other party from breach.” “…. the jurisdiction in relation to penalty clauses is concerned not primarily with the enforcement of inoffensive liquidated damages clauses but rather with protection against the effect of penalty clauses. There would therefore seem to be no reason in principle why a contractual provision the effect of which was to increase the consideration payable under an executory contract upon the happening of a default should be struck down as a penalty if the increase could in the circumstances be explained as commercially justifiable, provided always that its dominant purpose was not to deter the other party from breach.”
“Finally, I come to the amount claimed on the basis of clause 101, noting that the award in this case was made by three very experienced maritime arbitrators (Mr Michael Baker-Harber, Mr Alan Burbidge and Mr Robert Gaisford). They were well placed to judge the nature of the provision in its commercial setting. They pointed out that if the vessel was redelivered only one hour late, the amount of the claim of$471,602.32 would be payable in full (Award para 27). They were, in my opinion, right to take the view that this would be an "unconscionable" amount within the meaning of the case law, and equally so in the case of a delay in redelivery of just over six days as in the present case. Like the arbitrators, I consider that the primary purpose of the clause was to deter the Charterers from breaching their obligation to redeliver the vessel in time, and whilst such a purpose may in a sense be understandable because of the limits to the Owners' knowledge about the likely length of the final voyage at the time of the order, the clause was in my view a penalty, and not a genuine pre-estimate of damage resulting from a breach of contract. I would dismiss the Owners' appeal, and confirm the Award.”