“If the Employer shall enter and expel the Contractor under this Clause he shall not be liable to pay to the Contractor any money on account of the Contract until the expiration of the period of Maintenance and thereafter until the costs of completion and maintenance damages for delay in completion (if any) and all other expenses incurred by the Employer have been ascertained and the amount thereof certified by the Engineer. The Contractor shall then be entitled to receive only such sum or sums (if any) as the Engineer may certify would have been due to him upon due completion by him after deducting the said amount. But if such amount shall exceed the sum which would have been payable to the Contractor on due completion by him then the Contractor shall upon demand pay to the Employer the amount of such excess and it shall be deemed a debt due by the Contractor to the Employer and shall be recoverable accordingly.”
“They simply acted as if they were validly appointed receivers, dismissing employees, terminating contracts, disposing of assets and settling claims. It is not alleged that they had any particular intent other than to do that which they did.”
“In my judgment there was no realistic prospect that a settlement with NWW could have been achieved on or after 9 June nor any prospect that NWW would finance an administration. Any such prospect can only be described as fanciful. Far from providing any form of funding for an administration NWW would have withheld funds in order to achieve a termination of the contracts on the grounds of liquidation or abandonment.”
“The final figures therefore will be: 1. Freehold property 97,000 2. Other debtors 16,000 3. Plant and equipment 147,000 4. Trading surplus 0 5. Cash 74,000 6. Contract debtors, stock and WIP, NWW 1,400,000 7. Contract debtors, stock and WIP non NWW 420,000 8. Novation premium 0 Total 2,154,000 Less Liquidator’s costs and expenses 300,000 1,854,000” and WIP, NWW 1,400,000 and WIP non NWW 420,000 Total 2,154,000 1,854,000”
“The tort is an economic tort designed to place limits on the self-interested rough and tumble of the business world. Its philosophical basis appears to be that contracts should be kept rather than broken. Where, as here, A (Latco) procures B’s (Latreefers’) breach of his contract with C (the yard), adopting it as his own because he is interested to do so, seeking a benefit for himself or a fortiori a detriment for C, and does so deliberately, knowingly and intending the breach to take place, then A puts himself in the way of incurring a liability, even though not himself a party to the contract, unless (i) he does not directly procure the breach, and (ii) he uses no (relevant) unlawful means, or (iii) he can claim some justification. The significance of (i) is that where A directly procures a breach of contract he makes himself as it were directly privy to the breach. The significance of (ii) is that in the absence of making himself privy to the breach, he cannot be faulted as long as he acts as he is entitled to act, but if (deliberately, knowingly and intending the breach to take place) he commits an unlawful act, by which I have in mind an unlawful act of sufficient causative relevance, then he renders himself liable. It may be that unlawful means ought to be necessary even where there is direct procurement (see the wide-ranging work by Hazel Carty, An Analysis of the Economic Torts, 2001, at 82). The significance of (iii), an area which has not been clearly worked out in the cases, appears to be that there may be moral or perhaps economic factors which may mitigate even to the point of justifying conduct otherwise incurring a prima facie liability.”
“He who maliciously procures a damage to another by violation of his right ought to be made to indemnify; and that, whether he procures an actionable wrong or a breach of contract.”
“Validity of office-holder’s acts The acts of an individual as …. Administrative receiver, liquidator or provisional liquidator of a company are valid notwithstanding any defect in his appointment, nomination or qualifications.”
“2. By reason of their conduct purportedly as receivers now declared to have been unlawful, the Receivers have committed the following wrongs, actionable in damages at the suit of the Claimants: 2.1 on and after9 June 1992 , trespass over, and conversion of 2.1.1 all the businesses, assets and undertaking of the Claimants; 2.1.2 alternatively, all of the land and goods and chattels of the Claimants; as at9 June 1992 as described in the First Schedule. 2.2 further and in the alternative, on and after9 June 1992 , unlawful interference with the Claimants’ contracts as at9 June 1992 as described in the Second Schedule. 2.3 Further and in the alternative, on and after9 June 1992 , wrongful or unlawful interference with, and wrongfully taking control of, such of the businesses, assets and undertaking of the Claimants that may not be the subject of claims for trespass, conversion or interference with contractual relations under paragraphs 2.1 or 2.2 above. ….. Second Schedule Wrongful Interference with Contractual Rights of the Claimants as at9 June 1992 The Contracts 1. The building contracts described in Appendix 1 to the report of Naismiths, Quantity Surveyors and Construction Advisors, dated May 2002. ….. Particulars of the acts that constitute the trespass and conversion or wrongful interference 2. The taking of possession of the Claimants’ rights under these contracts and treating those rights as being available to them to realize for the benefit of their appointor, including the acts described in paragraphs 13(ii), 17(ii), 18, 19, 21, 23, 24, 25, 29, 32, 33, 34, 36, 38 and 39-41 of the Remuneration Case.”
“Settlement of the NWW Claims ….. 32. Between June 1992 and November 1993, the receivers and Robins conducted negotiations with NWW for the settlement of OBG’s remaining claims against NWW under the contracts identified in Schedule 11 and NWW’s claims against OBG. 33. On14 November 1993 , NWW made an oral offer, without prejudice and subject to contract, to pay£400,000 in full and final settlement of OBG’s claims. By a report to Mr Allan dated16 November 1993 , Mr Robins on behalf of Robins recommended that the offer be accepted. In reliance on that report, Mr Allan wrote to NWW on17 November 1993 confirming that the offer was acceptable. On1 December 1993 , Mr Allan wrote to Mr Robinson confirming that the offer had been made and that the Receivers had been advised to accept it. 34. In or about November 1993, the Receivers instructed DWS and NWW instructed Addleshaws to negotiate the detailed terms of the proposed settlement. Those negotiations lasted from November 1993 until about August 1997 when OBG acting by the Receivers, and with the consent of the Liquidators who were parties to the agreement, entered into a settlement agreement pursuant to which the sum of£400,000 was paid by NWW into a joint account held by DWS and DLA. ….. Claims under Non-NWW Contracts From about July 1992, the Receivers, with the assistance of Robins, Mr Swarbrick and the other quantity surveyors whose services were retained by the Receivers, negotiated with and settled the claims of OBG under the contracts specified in Schedule 12.”
“67. A preliminary point was taken that the original pleadings confined the damages claim to trespass and conversion in the narrow sense, and were inadequate in their allegations as claims for interference with contractual rights. I invited and received written submissions on this aspect in the course of the trial, but was satisfied that the Claimants were entitled to proceed. At the outset it was perfectly plain from para. 40 that the Claimants were seeking damages for the Receivers having dealt with the whole of the assets of the business of whatever nature. The question whether the allegations made are sufficient to support the wider claim are best considered in relation to the law, but there has never been any issue on the facts as to the actual conduct of the Receivers. They simply acted as if they were validly appointed receivers dismissing employees, terminating contracts, disposing of assets and settling claims. It is not alleged that they had any particular intent other than to do that which they did. The extent to which their conduct is actionable is the question of law to which I turn next. ….. Measure of damages – the Survival Claim 75. I have indicated the basis of this claim at the beginning of this judgment. The Claimants say that whatever the precise analysis of the legal causes of action in relation to the different assets comprised in the OBG business, whether land chattels or contracts and whether based on trespass, conversion or interference with contractual relations, the damages caused are the same: the loss of the whole of the Claimants’ business as an undertaking, against which they have received only the net proceeds of the receivership, for which, following the judgment on liability, the Receivers have accounted to the Liquidator. I accept that approach. It does not seem to me that any purpose would be served or any different result achieved by attempting to separate the claims in relation to land, chattels and contracts, or to look at each individual act by the Receivers and try to trace the damages attributable to that act. By whatever route it would all lead to the same result, as each act would have contributed to the result, which was the loss by ‘conversion’ of the business as a whole. It is that loss which must provide both the measure and the limit of the damages on whichever basis is appropriate on the facts.”
“there must be interference in the execution of a contract. The interference is not confined to the procurement of a breach of contract. It extends to a case where a third person prevents or hinders one party from performing his contract, even though it not be a breach.”
“the interference must be deliberate. The person must know of the contract or, at any rate, turn a blind eye to it and intend to interfere with it: see Emerald Construction Co. v. Lowthian[1966] 1 WLR 691 ”
“Must the conduct of the defendant, the alleged tortfeasor, be aimed directly at the plaintiff, the contracting party, who suffers damage, in the sense that the defendant intends that the plaintiff’s contract should be broken, or is it sufficient that that conduct should have the natural and probable consequence that the plaintiff’s contract is broken?”
“12. Alternatively, if the wrongful acts of the Receivers as described in paragraph 2 above have not caused the liquidation of the Claimants and the irrecoverable loss of the Claimants’ entire businesses, assets and undertakings as going concerns (which is denied), the wrongful acts of the Receivers have caused the deficiencies in the liquidations to the substantially greater than otherwise they would have been. 13. The deficiencies that would have resulted had the Receivers not acted wrongfully would have been£817,000 , particulars of which are set out in the Fifth Schedule. The present estimated deficiency in the liquidations of the Claimants (excluding any allowances for the damages and costs that will be awarded to the Claimants in these proceedings) is£5,373,900 . Particulars of how this figure is calculated are set out in the Fourth Schedule. 14. Further, the wrongful conduct of the Receivers has also caused delay in the completion of the liquidations and in the payment of a final dividend to creditors. Had the Receivers not acted wrongfully, a final dividend would have been paid to creditors by no later than1 June 1994 . The present estimate of the time for payment of a final dividend to creditors from any award in these proceedings is1 June 2003 . The Claimants therefore claim interest at the rate of 8% per annum on the sum of 4,556,900 for this period of delay, namely£3,280,968 . The Claimants claim this sum as: 14.1 damages; 14.2 alternatively, interest pursuant tos.35A of the Supreme Court Act 1981 . 15. The Claimants therefore claim£7,837,868 being: Estimate of actual deficiency£5,373,900 Less predicted deficiency in liquidations had (£817,000 ) the Receivers not been appointed Damages or additional interest to£3,280,968 compensate for delay in payment of dividends to creditors Total Claim£7,837,868 16. The Claimants will give credit for the sums received by way of interim payment pursuant to paragraph 8 of the Order of HHJ Maddocks QC dated31 January 2001 a follows: 16.1£295,00.00 on14 February 2001 ; and 16.2£471,263.67 on22 March 2001 ; and will give credit for any other interim payments received prior to judgment.”
“We consider that there are really two issues, firstly there is the question of whether the business had as a matter of fact, any value at all as at the9 June 1992 , having regard to all the circumstances, and in particular their financial position. We consider that this issue can be determined by the Court considering as a matter of fact what would have happened if the Receivers had not been appointed? Would any sum have been realised in all the circumstances in respect of the business of the companies? The second issue is, if so what was the value of the businesses which would have been realised.”
“21. It appears now to be accepted that the real basis of your claim to damages is the value of the companies’ businesses as at the9th June 1992 . 22. We consider that the liability of our clients is to be determined by finding as a matter of fact the degree to which their purported appointment as Receivers has caused loss, if any, to the value of the companies’ assets including the businesses.”
“The essence is that the claimants, at the time of appointment of the receivers, had a business which the claimants say was a going concern and which had a value as a going concern. It is also their case – although the degree of emphasis has varied in the course of the statement of issues and statement of case – it is said that a likely route by which that value would have been saved and realised is an administration order, followed, it may be, by a company administration order. That case appears to be clear enough but what is equally clear is that the essential question is one of the valuation of the company, given on the one side the fact that it was still trading at the time of the appointment, and on the other that it was plainly in financial difficulties and could properly be viewed as in a state of insolvency. ….. One can well see that a company which is in a situation where it cannot presently pay its creditors as they fall due is necessarily forced into some form of insolvency procedure, but again the consequence of that may not necessarily be that the value of its assets are [sic] not realised so as to at least pay its creditors in full.”
“Once it is established that the matter turns on the value of the company at that period of time, both sides are in a position to obtain evidence of matters which affect the value and to obtain experts reports upon it and to make their own calculations. To try to plead to each of those details in a formal pleading appears to me not a helpful way forward; on the contrary it seems to me that the better way is that which the claimants have chosen, and the procedure from this point may indeed be one which can dispense with further pleadings.”
“9. ….. To the extent that a claim is made that the mere fact of the appointments caused loss to the Claimants, it is accepted that Penningtons are likely to be liable to indemnify the Receivers in respect of such liability to the Claimants. ….. 10. So for example, if …. it were held that the mere fact of the appointments caused the destruction of the entire business which had value as claimed of£4,610,000 and drove the Claimants into liquidation, with a net deficiency of£5,373,900 , and that absent such appointment the Claimants would have continued to trade and avoided liquidation, then it is accepted that Penningtons are liable to indemnify the Receivers in relation to such claims, because they arise out of the mere fact of the appointments. 11. However to the extent that a claim is made that the Receivers failed to obtain proper value for the assets over which they took control, or failed to act as they should have done, the position is different. It was a matter for the Receivers to decide they would conduct themselves, and if they failed to obtain proper value for particular assets then the cause of such loss is not Penningtons’ advice. To put it another way if the Receivers failed to obtain proper value for assets then this was a break in the chain of causation between Penningtons’ advice on appointment and the loss in question. 12. ….. the Statement of Case dated31st May 2002 was understood until very recently to be a claim that all of the pleaded losses had been caused by the mere fact of appointment. ….. After analysis of the Statement of Case it appeared that there was common ground between the Receivers and Penningtons in that the entire losses claimed were said to have arisen as a result of the mere fact of appointment. Accordingly there would be no great issue of causation of loss between those parties. There is no suggestion that the Receivers did anything wrong apart from take their appointments. 13. It now appears that it is conceded by the Claimants that their Statement of Case is incomplete and that they wish a further round of pleadings and evidence. ….”
“15. ….. The wrongful acts are pleaded in paragraph 2 in terms of their assumption of control of the businesses on the9th June 1992 , without any suggestion that they acted unreasonably.”
“The Claimants do not and will not seek to allege that the receivers were in breach of the duties which they would have owed the companies and/or their appointor had they been validly appointed.”
“ …. our position is that our case is a case of valuation and we will make that commitment in absolute terms and the point, and …. we are happy to add that on to it “and the Claimants confirm that their case is one of pure valuation”
“Upon the Claimant stating that the Claimants’ case is one of valuation and not that the receivers were in breach of the duties which they would have owed to the companies or others had they been validly appointed as receivers”
“9.1 If the court concludes that liquidation was inevitable, the Claimants accept that the losses that result from the liquidation per se cannot be recovered. The correct approach then is to identify how the hypothetical liquidation of the Claimants would have proceeded without the intervention of the Defendants and then to compare that to the actual result of the liquidation to date. ….. 9.4 However, the suggestion that the hypothetical liquidation would have proceeded in the same way as the Defendants’ tortious conduct actually did is plainly unsustainable for the same reasons as set out in paragraph 8.3 above. …..”