“The tenants can always contend that they will suffer a disadvantage if a dispensation is accorded; however, as explained above, the only disadvantage of which they could legitimately complain is one which they would not have suffered if the [consultation requirements] had been fully complied with, but which they will suffer if an unconditional dispensation were granted.”
“… the Applicants argues that the case of Daejean Investments Ltd v. Benson[2013] UKSC 54 states that dispensation must be given unless there is evidence of actual prejudice being caused to the Respondents and no such prejudice had been asserted or proved in this case. The Tribunal agrees that the Respondents have not addressed prejudice, but lack of prejudice does not correct the lacunae in the Applicants arguments as discussed above. First, they have a potentially insuperable problem in attempting to obtain a dispensation for works carried out to a property which they did not at that time own and secondly, they have not satisfied the Tribunal that the works were so urgent and necessary that they could not wait two or three months before being started.”
“22. In the present case the works which were done have been described by the Applicants as both structural and urgent. However, insufficient evidence has been produced to support this assertion, and the evidence that has been produced by Mr Payne is conflicted as he has a direct interest in the property. This interest was not declared to the Tribunal, and only became apparent at the Hearing. In addition to the reports from an independent surveyor and structural engineer detailing the works to be carried out the Tribunal would have expected to see full estimates for the proposed works and a schedule of works. 23.All the works are said to have been completed but there is no documentary evidence of their satisfactory completion. 24. Having considered the submissions made by the Applicants the Tribunal is not satisfied that they have demonstrated the urgency of the works nor explained in detail the extent or costs of those works. 25. Neither can it consider giving a retrospective dispensation in relation to a property which the Applicants did not own at the time when the works were carried out. 26.This is not therefore a situation in which the Tribunal considers it appropriate or reasonable to exercise its discretion under s20ZA in favour of the Applicants and accordingly refuses the Applicants’ application.”
“16. Bys27(1) Land Registration Act 2002 title to registered land does not pass until registration which means that at the time when the Applicants carried out the work at the property, they were not the legal owners of the property. They owned only an equitable interest which would not entitle them to enter and do works on the property without the legal owner’s permission nor to serve a s20 notice or commence legal proceedings in their own name. There is no evidence that they had either sought or obtained the legal owner’s permission before carrying out the works. 17. The Tribunal is not impressed by the Applicant’s arguments that as equitable owners of the property the Applicants were entitled to do the works without consent of the registered proprietor. 18. It appears therefore that the Applicants had no locus standi either to do the works or to make a s20ZA application prior to their registration of title on07 January 2022 by which time the works had been completed It is noted that the Applicant’s application is dated31 January 2023 . They are therefore making an application retrospectively to dispense with consultation for works which they carried out to a property when they did not own it. The Tribunal cannot condone this action.”
“A person is entitled to exercise owner’s powers in relation to a registered estate or charge if he is- (a) the registered proprietor, or (b) entitled to be registered as the proprietor.” (a) the registered proprietor, or (b) entitled to be registered as the proprietor.”
“We need to see that these works were so urgent and immediate that they had to be done before you could, possibly, even send one letter to the respondents.”
“[In its grounds of appeal] the Appellant asserts that the lack of prejudice to the Respondents effectively precludes the Tribunal from denying the grant of the order to the Appellant. Lack of prejudice is an important factor which the Tribunal takes into account on exercising its discretion. It cannot however dominate in a situation where the basic right to an order has not been established. The Tribunal re-emphasises that grant of a dispensation order is not merely a rubber stamp available on payment of a small fee.”
“A report was prepared by Mr Payne of [RPA consultancy Limited], a company associated with the Applicant company, which recommended a series of works to be carried out some of which were said to be urgent or which should be commenced immediately. The Applicants rely on the findings of this report to justify the commencement of the works prior to issuing s20 documentation which they admit was in part non-compliant with the requirements of the section. The Tribunal is not satisfied that this report gives an independent and unbiased view of the proposed works because Mr Payne is also a Director of the Applicant company. He did not give evidence at the hearing.”
“[The appellant] insist that it was necessary to start the works immediately because the building was likely to collapse. Although the words ‘urgent’ ‘immediate’ and ‘necessary’ do appear in Mr Payne’s report (see above para 7) the Tribunal prefers the more moderate approach taken by Mr Partridge who agrees that some works are urgent but denies the fragility of the structure of the building. The Tribunal takes the view that none of the works undertaken by the Applicants could not have waited for the 2-3 months during which a proper s20 procedure could have been carried out. 13. Ms Meigh a Director of the Applicants, an established property company, gave evidence on their behalf. She conceded that Mr Payne had a conflict of interest caused by his Directorships of both the Applicant company and the company carrying out the survey of the property.”
“In the present case the works which were done have been described by the Applicants as both structural and urgent. However, insufficient evidence has been produced to support this assertion, and the evidence that has been produced by Mr Payne is conflicted as he has a direct interest in the property. This interest was not declared to the Tribunal, and only became apparent at the Hearing.”