“20(1) Where this section applies to any qualifying works or qualifying long term agreement, the relevant contributions of tenants are limited in accordance with subsection (6) or (7) (or both) unless consultation requirements have been either – (a) complied with in relation to the works or agreement, or (b) dispensed with in relation to the works or agreement by (or on appeal from) a leasehold valuation tribunal.”
“Where an application is made to [the appropriate tribunal] for a determination to dispense with all or any of the consultation requirements in relation to any qualifying works … the tribunal may make the determination if satisfied that it is reasonable to dispense with the requirements.”
“17.1 Any failure to comply with the consultation requirements was caused by an administrative error; technical difficulties and/or the introduction of a new working process for the creation of s20 Notices. 17.2 Notice was served at the property of the leaseholder of Flat 5 in respect of the intended works. 17.3 Despite the respondents being on notice of the works since at least21 September 2018 (when the costs of the works with demanded by way of invoice) they have not at any time: (a) identified any relevant prejudice caused by result of any purported failure to be consulted; (b) identified anything they would have said, if they had been given the opportunity; and/or (c) identified any relevant prejudice they would suffer if an unconditional dispensation were to be granted.”
“…. I would certainly have responded within three days to ask why it would cost so much, how many quotes were obtained and the reason for choosing this contractor… I would also have increased my monthly payments to my account to spread the costs. I do not have savings available to take large lump sums to meet bills. I have to budget.”
“10. The Tribunal noted in its previous decision that, by letter dated25 June 2021 , Judge Vance had directed that “if the applicant wishes to pursue a s.20ZA dispensation application it must complete the relevant application form and pay the required tribunal fee.”
“13. The applicant asserted that the Third Respondent has failed to establish that she suffered any prejudice by their failure to consult her and that this is sufficient for the application for dispensation to be granted. The tribunal rejects this assertion for a number of reasons: (a) As the Supreme Court was itself at pains to point out, it is not just a simple equation of no prejudice equals dispensation. If that were the case, landlords could, as a matter of standard practice, get away with avoiding any consultation whenever they can predict the prejudice is unlikely, thus driving a coach and horses through the legislation. (b) The tribunal accepts the Third Respondent’s submission that she suffered prejudice in the form of being unable to budget for the expense of the works. A section 20 notice provides a lessee not only with the opportunity to participate in a consultation process but also with an estimate of the likely cost. The particular form in which the applicant failed to comply with the requirements in this case means that the Third Respondent was unaware of the potential charge until she received the bill. (c) Perhaps most significant is that the process outlined by the Supreme Court only works if the lessee is given a genuine opportunity to make a case that there has been prejudice. That opportunity depends on having access to the necessary information. If a lessee did not know the relevant facts, it would be impossible for them to demonstrate any prejudice arising from them. In this case, the Third Respondent initiated email correspondence with the applicant in 2018 asking for the relevant information. Two years later, in October 2021, the applicant provided a schedule of the relevant works on the basis of which they asserted that the Third Respondent had everything that she needed. However, the applicant has overlooks a vital aspect, namely why the works were initiated. The only information on this is in the section 20 notice which simply states, “responsive repair works required.”
“45. Thus, in a case where it was common ground that the extent, quality and cost of the works were in no way affected by the landlord’s failure to comply with the Requirement, I find it hard to see why the dispensation should not be granted (at least in the absence of some very good reason): in such a case the tenants would be in precisely the position that the legislation intended them to be – ie as if the Requirements had been complied with”
“It is axiomatic that each case must be decided on its own particular facts. Moreover, the FTT should be guided, but not led, by the principles laid down in Daejan. I note what is said by Lord Neuberger at [41] ‘…the very fact that section 20ZA(1) is expressed as it is means that it would be inappropriate to interpret it as imposing any fetter on the [FTT’s] exercise of the jurisdiction beyond what can be gathered from the 1985 Act itself, and any other relevant admissible material. Further the circumstances in which a section 20ZA application is made could be almost infinitely various so any principles that can be derived should not be regarded as representing rigid rules.’”
“although the [FTT] decision referred to me being unable to budget for the cost … I did not put great importance on this so I do not agree with this point in the decision.”
“Perhaps most significant is that the process outlined by the Supreme Court only works if the lessee is given a genuine opportunity to make a case that there has been prejudice. That opportunity depends on having access to the necessary information. If a lessee did not know the relevant facts, it would be impossible for them to demonstrate any prejudice arising from them. In this case, the Third Respondent initiated email correspondence with the Applicant in 2018 asking for the relevant information. Two years later, in October 2021, the Applicant provided a schedule of the relevant works, on the basis of which they asserted that the Third Respondent had everything she needed. However, the Applicant has overlooked a vital aspect, namely why the works were initiated. The only information on this is in the section 20 notice which simply states, “Responsive repair works required.”
“(a) describe, in general terms, the works proposed to be carried out or specify the place and hours at which a description of the proposed works may be inspected; (b) state the landlord’s reasons for considering it necessary to carry out the proposed works; (c) contain a statement of the total amount of the expenditure estimated by the landlord as likely to be incurred by him on and in connection with the proposed works;”
“Further, such information needs to provided within a reasonable time frame. The older any works are, the more difficult it will be for any expert to comment usefully on them. What information the Applicant did provide came a long time after the event.”
“The Applicant appears to have misunderstood the relevance of the delay in providing information to the Third Respondent. The delay was part of what denied the Third Respondent a genuine opportunity to make a case that there had been prejudice.”