“C. Findings of fact C1. The repairs which were to be carried out while [the claimant] was in temporary accommodation C1. The repairs which were to be carried out while [the claimant] was in temporary accommodation 13. I concluded the works of repair which required [the claimant] to temporarily move out of [property 1] in October 2012 were set out in the undated document headed “[property 1] - Scope of Works” (page 204). I reached this conclusion for the following reasons: a) The Local Government Ombudsman report dated26 April 2012 included a recommendation that the internal works of repair listed at paragraph 40 of the LGO report be carried out. b) The document headed “[property 1] - Scope of Works” replicates paragraph 40, except that it also includes several additional items of work. In light of these additional items of work, I concluded it was a more recent version of the list at paragraph 40 of the LGO report. 14. On 20 April, Mr Keith Kiernan, the Legal Disrepair Manager at [the LA], wrote to [the claimant]. In this letter Mr Kiernan made clear that it was the internal works and not the external works which required [the claimant] to move out temporarily. 15. Although [the claimant] was required to move out because of the internal works to [property 1], the20 April 2012 letter explained that external works to [property 1] and 30B would also be carried out while [the claimant] was in temporary accommodation. 16. I concluded the external works were set out in a “Snagging report” dated17 August 2011 (pages 197 to 198). I reached this conclusion for the following reasons: a) The Local Government Ombudsman report dated26 April 2012 included a recommendation that [the LA] also carry out the external works of repair set out at Appendix A of the LGO report. b) I was not provided with Appendix A and both representatives told me they did not have this document. However, in light of paragraphs 36 and 40 of the LGO report, it is clear Appendix A consisted of a list of external works produced by [the LA] at some point between July 2011 and19 October 2011 . c) the fact the17 August 2011 document is described as a “Snagging report” is consistent with the background information within the LGO report which refers to earlier refurbishment works by one of [the LA’s] contractors. d) In her oral evidence, [the claimant] confirmed pages 197 to 198 set out the external works of repair which were to be carried out while she moved temporarily into (property 2]. C2. The completion of these repair works 17. I concluded the internal works of repair in the “[property 1] Scope of Works” document had been completed by22 February 2013 . 18. I reached this conclusion because on22 February 2013 [the claimant] and Ms Mulholland conducted a joint inspection of [property 1]. The purpose of this inspection was to check on the works which had been carried out to [property 1] while [the claimant] had been in temporary accommodation. The results of this inspection were set out in an undated “Snagging report” (pages 207 to 212). The contents of this snagging report indicate that all the internal works set out in the “[property 1] - Scope of Works” document had been carried out. 19. Although the internal works of repair had been completed by22 February 2013 , during the inspection on22 February 2013 [the claimant] raised various concerns about the way the internal works had been completed. As result, the snagging report at pages 207 to 211 set out a list of [the claimant’s] concerns and the action [the LA] and their contractor agreed to take to address these concerns. I reached the following conclusions about these concerns and about the action that was to be taken to address them: a) In light of the description of [the claimant’s] concerns in the second snagging report (i.e. the report which records the outcome of the22 February 2013 inspection), I concluded that all of the issues raised by [the claimant] on 22 February were minor problems. b) In light of the description of the proposed action in the second snagging report, I concluded it was unnecessary for [the claimant] to remain in temporary accommodation while these issues were addressed. c) I concluded that adequate steps had been taken to address all of these issues by6 February 2015 . I reached this conclusion for the following reasons: i. On10 December 2013 Mr Kiernan emailed the Housing Benefit department about [property 1] and said: “…the property is immaculate now.” (page 43) ii. On6 October 2014 [the claimant’s] sister emailed Mr Kiernan. Her email raised a number of concerns about [property 1]. However, her email did not suggest that any of the items in the second snagging report were unresolved. iii. On6 February 2015 Mr Kiernan wrote to [the claimant] once again confirming that there were no outstanding issues in relation to the internal works. iv. [The claimant] accepts she visited [property 1] twice in around early May 2015. At paragraph 7 of her first witness statement, [the claimant] says she “cannot remember what condition the interior of the property was in during these visits” (page 95). However, [the claimant] and her sister have been methodical in identifying and raising with [the LA] their concerns about [property 1]. In light of this, I conclude it is significant that the documents before me do not suggest [the claimant] or her sister raised with [the LA] any concerns about a failure to take the action set out in the second snagging report following these visits. v. In so far as it is possible to tell from the photographic evidence before me, it appears the actions in the second snagging report were carried out. For example, photograph 5 to Ms Cheshire’s witness statement shows an isolation switch with a label referring to a Vent Axia HR25 fan. The installation of Vent Axia HR25 fans in place of the fans initially installed by the contractors was agreed at points 1.01 and 2.01 of the second snagging report. vi. [The claimant] and her representatives have not in this appeal identified any actions within the second snagging report which were not carried out. This is in circumstances where [the claimant] and her solicitor visited [property 1] on12 December 2019 and methodically documented [the claimant’s] concerns about the internal condition of [property 1] at that point. 20. I concluded the external works of repair to [property 1] set out in the snagging report at pages 197 to 198 had been completed by6 February 2015 . I reached this conclusion for the following reasons: a) The second snagging report indicates that all but one of the external works of repair to [property 1] had been completed by22 February 2013 (pages 207 to 212). b) The item which was outstanding on22 February 2013 was the installation of a low level render plinth “to the rear elevation of the main building and rear right hand flank to rear addition” (point 7.01, page 211). It is clear from the report of Mr Ian Lovatt, the chartered surveyor instructed by [the claimant’s] solicitors and who inspected the premises on23 September 2020 , that this plinth was subsequently installed (see section 6.02(iii) and photographs 21 to 24). c) As to the date this render plinth was installed, the letter from Mr Kiernan dated10 December 2013 supports the conclusion that all the outstanding issues to the exterior of [property 1] had been dealt with by the end of 2013. This is reiterated by Mr Kiernan’s6 February 2015 letter. d) The second snagging report identified a number of minor snagging issues relating to the way the works to the exterior of [property 1] had been carried out (pages 211 to 212). In so far as it is possible to tell from the photographic evidence before me, these issues were subsequently addressed. For example, photograph 21 to Mr Lovatt’s report shows that a cage was subsequently fitted over the boiler flue (which addressed point 7.02 on page 211) and photographs 21 and 22 indicate that the making good to the lintels was subsequently carried out (points 7.03 and 7.04 on page 211). 3) The only external work of repair which Mr Lovatt’s report identified as being necessary was reconnecting a section of plastic guttering (Lovatt report, appendix A, item 7.01). I concluded this problem arose after the22 February 2013 inspection as the second snagging report does not refer to it. C3. Subsequent disrepair 21. In relation to the internal condition of [property 1] on19 March 2019 , I reached the following conclusions: a) The disrepair Mr Lovatt identified in his report arose after the completion of the works in the “[property 1] Scope of Works” document. This follows from the conclusions I have set out in section C2. In addition, I note Mr Lovatt’s statement within his report that he was unable to form a definitive opinion about the duration of the disrepair he identified (page 9 of the report). b) Given Mr Lovatt’s description of the defects and the works required to remedy them, I concluded the disrepair identified by Mr Lovatt was relatively minor. c) I concluded the works identified by Mr Lovatt could be carried out with a tenant in occupation. First, because the works required were relatively minor. Second, because at paragraph 6.03 of his report Mr Lovatt said: “In my opinion the majority of the works noted necessary at this property can be carried out with the tenant in occupation”
“D. Analysis 24. I accepted Mr Rutledge’s submission that the legal burden was on [the LA] to establish there were, on19 March 2019 , grounds to supersede the earlier decision to award Housing Benefit. 25. [The LA’s] position was that the relevant ground of supersession was that there had been a change of circumstances relevant to [the claimant’s] entitlement to Housing Benefit. In particular, [the LA’s] position was the repairs which had required [the claimant] to move into temporary accommodation in October 2012 had been completed and that this change impacted on [the claimant’s] entitlement to Housing Benefit because it meant she no longer fell within the terms of regulation 7(4). 26. I concluded [the LA] had discharged the legal burden on them to show that regulation 7(4) had ceased to apply for the following reasons: (a) [The claimant] had been required to move into temporary accommodation because of the need to carry out the internal repairs set out in the document headed [property 1 – Scope of Works] (page 204). [The LA’s] second snagging report establishes these works had been completed by22 February 2013 . (b) [The claimant] disputes this and says there were still problems with the internal condition of the premises on22 February 2013 . However, I concluded this did not assist [the claimant] for two reasons: i. In CH/393/2020 Commissioner Williams reached the following conclusion about regulation 5(7) of theHousing Benefit (General) Regulations 1987 – a regulation that was identical to regulation 7(4) of the current Housing Benefit regulations: i. In CH/393/2020 Commissioner Williams reached the following conclusion about regulation 5(7) of theHousing Benefit (General) Regulations 1987 – a regulation that was identical to regulation 7(4) of the current Housing Benefit regulations: 16. I agree with the view expressed in the commentary to regulation 5(4) of CPAG’s Housing Benefit Council Tax Benefit Legislation (2000-2001 edition p157) on the meaning of “essential”