“2.29.2 A notice from the Employer under clause 2.29.1 shall state that for the period between the Completion Date and the date of practical completion of the Works (or the relevant Section) by the Contractor, or the date of termination of the Contractor's employment under this Contract (whichever is earlier): 2.29.2.1 he requires the Contractor to pay liquidated damages at the rate stated in the Contract Particulars, or lesser rate stated in the notice, in which event the Employer may recover the same as a debt; and/or 2.29.2.2 that he will withhold or deduct liquidated damages at the rate stated in the Contract Particulars, or at such lesser stated rate, from sums due to the Contractor.”
“13.1.1. The LAD Claim is invalid and does not allow the Responding Party to claim liquidated damages as so claimed; 13.1.2. The Responding Party is not entitled to claim liquidated damages as specified in its LAD Claim in respect of 141 days of delay; 13.1.3. The Referring Party is entitled to an extension of time of 141 days to the Completion Date, or some other period as the Adjudicator finds appropriate.” to claim liquidated damages as so claimed; 13.1.2. The Responding Party is not entitled to claim liquidated damages as specified in its LAD Claim in respect of 141 days of delay; 13.1.3. The Referring Party is entitled to an extension of time of 141 days to the Completion Date, or some other period as the Adjudicator finds appropriate.”
“It is correct that the parties dispute which version of the JCT Design & Build 2016 applies and governs the parties’ relationship. BDP repeats its position set out in the Referral that the version is that sent by Cygnet to BDP on or around13 March 2024 , accompanied with a covering letter, and was accepted by BDP by way of undertaking the works.”
“6. BDP and CBH disagree; (i) the Contract Completion Date said to be26th April 2024 by BDP and29th February 2024 by CBH and (ii) the Liquidated and Ascertained Damages said to be£14,500.00 per week by BDP and£1,000,00 per calender [sic] day by CBH…. … 11. It is plainly clear to me that the dispute referred to me surrounds; (i) liability or otherwise of BDP to pay liquidated damages together with the costs associated with correcting defective works, (ii) repayment or otherwise of retention, (iii) BDP extension of time entitlement and (iv) the cost claimed by CBH relating to a Health and Safety file. … 18. From the submissions I have received the following issues fall to be determined: (i) Contract Date for Completion of Works? (ii) Contract Rate for Liquidated Damages?...” (i) Contract Date for Completion of Works? (ii) Contract Rate for Liquidated Damages?...”
“26. It seems to me that both BDP and CBH share common ground that an agreed contract has not been executed. I accept what BDP advance in that a contract agreement does not need to be executed for the intended contract agreement to apply. Having said that in such circumstances there must be clear and unequivocable evidence as to what forms the intended contract agreement. It is plainly clear to me that the positions of BDP and CBH are totally polarised and as such there is no agreement at all as to what forms the intended contract agreement.”
“28. In consideration of para. 27 above together with all the sub-paras. neither BDP or CBH has persuaded me that BDP and CBH have agreed to include in the Contract liquidated damages at the rate of£14,500.00 per week (BDP) or£1,000.00 per calender [sic] day (CBH). 29. I Decide that BDP or CBH have not evidenced the rate for liquidated damages agreed by BDP and CBH or intended to be included in the Contract.”
“In consideration of paras. 24 to 29 above and that CBH has not adjusted the Contract Completion Date for any delay I find that CBH is not entitled to claim the liquidated damages claimed or any other amount of liquidated damages. I Decide that CBH is not entitled to claim liquidated damages at the rate and amount claimed or any other amount.”
“Had they been afforded such an opportunity, they would plainly have confirmed that the Adjudicator was not required to address whether or not there was an LADs mechanism in the contract, as the parties had already agreed there was such a mechanism (with the dispute around the validity of notices and the amount of applicable LADs). It follows that the Adjudicator’s breach of natural justice has had a material impact on the outcome of the Decision.”