“23. If an adjudicator has it in mind to determine a point wholly or partly on the basis of material that has not been put before him by the parties, he must give them an opportunity to make submissions on it. For example, he should not arrive at a rate for particular work using a pricing guide to which no reference had been made during the course of the referral without giving the parties an opportunity to comment on it. 24. By contrast, there is no rule that a judge, arbitrator or adjudicator must decide a case only by accepting the submissions of one party or the other. An adjudicator can reach a decision on a point of importance on the material before him on a basis for which neither party has contended, provided that the parties were aware of the relevant material and that the issues to which it gave rise had been fairly canvassed before the adjudicator. It is not unknown for a party to avoid raising an argument on one aspect of its case if that would involve making an assertion or a concession that could be very damaging to another aspect of its case.”
“[85] The objective which underlies the 1996 Act and the statutory scheme requires the courts to respect and enforce the adjudicator's decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the decision of an adjudicator. The courts should give no encouragement to the approach… which… may, indeed, aptly be described as “simply scrabbling around to find some argument, however tenuous, to resist payment”. [86] It is only too easy in a complex case for a party who is dissatisfied with the decision of an adjudicator to comb through the adjudicator's reasons and identify points upon which to present a challenge under the labels “excess of jurisdiction” or “breach of natural justice”
“it is necessary, in my judgment, that a natural justice challenge shows that the relevant failing by the adjudicator “went to the heart of the dispute”: see Pilon Limited v Breyer Group PLC[2010] EWHC 837 para 43. Even if an adjudicator has gone on a “frolic” or has failed, deliberately, to consider a defence that is of no moment unless such failure pertains to a critical part of the decision ultimately reached.”
“48. A number of authorities have referred to the question of natural justice in the context of adjudications. I respectfully adopt and endorse the judgment of Coulson J in Pilon Limited v Breyer Group Ltd[2010] EWHC 837 where he reviewed relevant authorities from [17] and provided a summary of the relevant principles at 22. For present purposes it is sufficient to set out his summary, which was: 22 As a matter of principle, therefore, it seems to me that the law on this topic can be summarised as follows. 22.1 The adjudicator must attempt to answer the question referred to him. The question may consist of a number of separate sub-issues. If the adjudicator has endeavoured generally to address those issues in order to answer the question then, whether right or wrong, his decision is enforceable: …. 22.2 If the adjudicator fails to address the question referred to him because he has taken an erroneously restrictive view of his jurisdiction (and has, for example, failed even to consider the defence to the claim or some fundamental element of it), then that may make his decision unenforceable, either on grounds of jurisdiction or natural justice: …. 22.3 However, for that result to obtain, the adjudicator's failure must be deliberate. If there has simply been an inadvertent failure to consider one of a number of issues embraced by the single dispute that the adjudicator has to decide, then such a failure will not ordinarily render the decision unenforceable: …. 22.4 It goes without saying that any such failure must also be material: …. In other words, the error must be shown to have had a potentially significant effect on the overall result of the adjudication: …. 22.5 A factor which may be relevant to the court's consideration of this topic in any given case is whether or not the claiming party has brought about the adjudicator's error by a misguided attempt to seek a tactical advantage. … .” 49. It will be noted that an inadvertent failure to consider one of a number of issues will “ordinarily” not render the decision unenforceable. This qualification admits the possibility that an inadvertent failure may in an extraordinary case bring the principle into play. No clear guidance is available about when an inadvertent failure will render the decision unenforceable. Since the essence of the adjudication process is that the real dispute between the parties should be resolved, it seems to me that the touchstone should be whether the inadvertent failure means that the adjudicator has not effectively addressed the major issues raised on either side. Clearly, as [22.4] of Pilon makes clear, the failure must be material in the sense of having had a potentially significant effect on the overall result of the adjudication.”
“111. Based on the Parties’ submissions I am not persuaded by the Contractor that the air conditioning design was out with the specification in the Sub-Contract. The Contractor’s submissions do not take me to a clear requirement for close control or a clear breach of a performance specification. Page 27 of 34 Adjudicator’s Decision – POL v VMA (DRS-00016554) – September 2025 210 112. The Contractor places reliance upon a report drafted by its replacement subcontractor (360 Heating) which, amongst other things, says there is no problem with the studio apartments, units 7 and 9 (RefExhibit 17 item 10 also referenced SurExhibit 4a-2 from a previous adjudication). An email from 360 Heating dated28 October 2024 informs me that some of the fan coil units can be repurposed within its design. 113. The Contractor also places reliance on an email from Mr Whitehurst in which he says the existing fan coil units (presumably the Viridis fan coil units) can be utilised in the 1 bed units. 114. It is clear from the evidence provided by the Contractor that the valuation of air conditioning within AFP 8 cannot be £nil. I have no other assessment to consider and so I decide the value as claimed by the Subcontractor, subject to adjustment to reflect the possibility of defects in the pipework, consistent with the water services. 115. My valuation is£23,703.66 (£47,407.33 x 50% =£23,703.66 ) (see RefExhibit 3, tab Contract Works, columns H & J, attached to this Decision).”
“Based on the evidence provided, it is clear to me that some pipework was likely defective (i.e. valves etc and hot/cold connections) and so I decide the value is 50% of the amount claimed, i.e.£16,953.88 (£33,907.76 X 50% =£16,953.88 ) (see RefExhibit 3, tab Contract Works, columns H & J, attached to this Decision).”