“It is common ground that there was a valid assignment of the Sub-Contract by MW to EWHL. The dispute concerns the effect of such assignment, namely, whether it transferred all benefits, including accrued benefits, or merely future rights under the Sub-Contract; if it transferred all benefits, whether it also transferred all obligations so as to amount to a novation.”
“In summary, there was an effective assignment of MW’s accrued and future rights under the Sub-Contract by the notices in writing given to EWHL and Outotec.”
“The assignment of the Sub-Contact by MW to EWHL did not transfer the benefit and burden so as to take effect as a novation ...”
“Even where M+W has no claim for contribution under the 1978 Act by reason of the lack of notification under clause 37 of the subcontract, it may nevertheless rely on the defence of abatement in reduction of its liability under the subcontract for milestone payments.”
“Four days before this judgment was handed down, EWH and M+W reached terms of settlement. Nevertheless, both parties still filed their list of editorial corrections by the deadline that day and neither asked me not to hand down this judgment. In any event, the third-party proceedings have not been settled and many of the findings are important to those ongoing proceedings.”
“It is for M+W to prove its defence of abatement and I cannot, without evidence on the point, determine on the balance of probabilities that the task is impossible and that, as a matter of generality, the difference in value of the defective subcontract plant is necessarily greater than the claimed remedial costs.”
“This concept is addressed in Chitty [on Contracts] at 19-079 &19-080: “The principle that the burden of a contract cannot be transferred so as to discharge the original contractor without the consent of the other party means that, as a general rule, the assignee of the benefit of a contract involving mutual rights and obligations does not acquire the assignor’s contractual obligations… … However, where contractual rights are assigned, the extent of those rights will be defined by the original contract… The conditional benefit principle arises where the right assigned is conditional or qualified, the condition being that certain restrictions shall be observed or certain burdens assumed. The restrictions or qualifications are an intrinsic part of the right which the assignee has to take as it stands. The question whether a contract creates a conditional benefit is one of construction.”
“… where a right under a contract was conditional upon, or qualified by, performance of some obligation in return for which the right has been granted, an assignee of the benefit of such right will only be entitled to exercise the right subject to performance of the burden: Tito v Waddell (No.2)[1977] Ch 106 , 290, per Megarry V-C; Rhone v Stephens[1994] 2 AC 310 , 322, per Lord Templeman; Davies v Jones [2010] 2 All ER (Comm) 755, para 27, per Sir Andrew Morritt C. That principle is referred to in the authorities as “the conditional benefit principle”.”
“The Guarantor [Metso] hereby guarantees the due and proper performance by the Subcontractor [Outotec] of the Subcontractor's duties and obligations arising under or in connection with the Subcontract so that if the Subcontractor shall in any respect fail to perform any of its duties or obligations arising under or in connection with the Subcontract or shall commit any breach of any provision, or fail to fulfil any warranty or indemnity, set out in the Subcontract, then, upon the Contractor's [MW’s] written demand, the Guarantor shall forthwith perform and fulfil in the place of the Subcontractor each and every duty, obligation, provision, warranty or indemnity in respect of which the Subcontractor has committed a breach or which the Subcontractor has otherwise failed to fulfil.”
“If the Subcontractor in any respect fails to observe or perform any of its duties or obligations to the Contractor under or in connection with the Subcontract, or if the Subcontractor fails to pay any direct debt, losses, damages, expenses, charges, interest or costs due from the Subcontractor to the Contractor under or in connection with the Subcontract, or if the employment of the Subcontractor under the Subcontract shall determine by operation of or notice given under Clause 44 of the Subcontract, then the Guarantor shall indemnify the Contractor against all direct losses, damages, costs and expenses incurred by the Contractor by reason of such failure or non-payment or termination (including costs and expenses incurred by the Contractor in connection with the enforcement of or preservation of its rights under this Agreement) provided that the Contractor shall take all reasonable measures to mitigate any loss or damage which it has suffered or incurred or may suffer or incur pursuant to this Clause 3 and the Guarantor shall upon first written demand itself pay to the Contractor without any deduction or set-off the amount of such direct debt, losses, damages, expenses, charges, interest or costs as the case shall require. Such amounts to be paid by the Guarantor to the Contractor within 30 days of receipt of such demand. However, subject to the other provisions of this Guarantee, this shall not be construed as imposing greater obligations or liabilities on the Guarantor than are imposed on the Subcontractor under the Subcontract.”
“The Guarantor agrees that its obligations under this Agreement shall be those of a primary and independent obligor and that the Contractor shall not be required to pursue any remedy against the Subcontractor before proceeding against the Guarantor under this Agreement.”
“The Contractor shall be entitled to recover no more under this Agreement in respect of any matter than the Contractor would be entitled to recover from the Subcontractor in respect of that matter, and, without prejudice to the foregoing, as between the Guarantor and the Contractor, all the limitations and defences available to the Subcontractor in respect of its obligations and liabilities under the Subcontract or otherwise available to the Subcontractor at law shall be available to the Guarantor in respect of its liabilities under this Agreement. The Contractor shall not be entitled to commence proceedings against the Guarantor under this Agreement in respect of any claim once any proceedings against the Subcontractor in respect of such claim would be statute-barred.”
“The Guarantor's obligations and liability under this Agreement will remain in full force and effect and shall not be discharged, released, reduced, impaired or affected by reason of any of the following: 8.2.1. any provision of the Subcontract being or becoming illegal, invalid, void, voidable or unenforceable for any reason whatsoever; …. 8.2.8. any other fact, circumstance, act, event, omission or provision of statute or law or otherwise which, but for this clause, might operate to discharge, impair or otherwise affect any of the obligations of the Surety under this Agreement or any of the rights, powers or remedies conferred on the Contractor by this Agreement or by law.”
“… A guarantee is merely a particular type of contract. The relevant question – in this as in every case – is 'what is the nature of the guarantee obligation that the guarantor has assumed?' That is the question that Phillips J, in the Mystery of Mercers case, recognised as the critical one. It is the question that in St Microelectronics NV v. Condor Insurance Ltd[2006] EWHC 977 (Comm) ; [2006] Lloyd's Law Reports Vol 2 525, at paragraph 36, Christopher Clarke J said underlies all cases such as this; and it is the question that the judge also asked himself in paragraph 92 of his judgment in this case. The answer to the question turns on the interpretation of the guarantee, as to which there are no special rules. A guarantor is likely in most cases to know the nature of the business relationship between the principal and the creditor. So is the creditor. But proof of such knowledge by either or both parties to the guarantee does not, by itself, tell you anything conclusive about the nature, terms or intended effect of the guarantee. That depends upon the true interpretation of its language, an inquiry involving 'the ascertainment of the meaning which the document would convey to a reasonable person having all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract' (Investors Compensation Scheme Ltd v. West Bromwich Building Society[1998] 1 WLR 896 , at 912, per Lord Hoffmann). In engaging in such an inquiry, it may well be appropriate to have regard to the commercial arrangements which were at the time in place between the principal and the creditor, which will form part of the background against which the guarantee is given. But the proposition that the interpretation of the guarantee is conclusively dictated by knowledge that the guarantor may alone have had is inconsistent with the now well-settled approach to the construction of written instruments, including guarantees, and is wrong.”
“Elmer's claims in misrepresentation and negligent mis-statement are founded upon the allegedly tortious conduct of Ashville said to have induced Elmer to sign and execute the contract. Had the statements complained of become terms of the contract, Elmer's claims for breach would, it would seem, have fallen under head (b). It is not said that the statements became terms of the contract, but that does not mean that the claims arising from them are not connected with the contract. In my view Elmer's claims in misrepresentation and negligent mis-statement relate to statements made in connection with the contract in the very real sense that they are said to have induced the making of it. Any other conclusion would in my view introduce an unwelcome element of artificiality into a very ordinary commercial transaction.”
“The underlying public interest is the same: that there should be finality in litigation and that a party should not be twice vexed in the same matter. This public interest is reinforced by the current emphasis on efficiency and economy in the conduct of litigation, in the interests of the parties and the public as a whole. The bringing of a claim or the raising of a defence in later proceedings may, without more, amount to abuse if the court is satisfied (the onus being on the party alleging abuse) that the claim or defence should have been raised in the earlier proceedings if it was to be raised at all. I would not accept that it is necessary, before abuse may be found, to identify any additional element such as a collateral attack on a previous decision or some dishonesty, but where those elements are present the later proceedings will be much more obviously abusive, and there will rarely be a finding of abuse unless the later proceeding involves what the court regards as unjust harassment of a party. It is, however, wrong to hold that because a matter could have been raised in earlier proceedings it should have been, so as to render the raising of it in later proceedings necessarily abusive. That is to adopt too dogmatic an approach to what should in my opinion be a broad, merits-based judgment which takes account of the public and private interests involved and also takes account of all the facts of the case, focusing attention on the crucial question whether, in all circumstances, a party is misusing or abusing the process of the court in seeking to raise before it the issue which could have been raised before. […] While the result may often be the same, it is in my view preferable to ask whether in all the circumstances a party’s conduct is an abuse than to ask whether the conduct is an abuse and then, if it is, to ask whether the abuse is excused or justified by special circumstances. Properly applied, and whatever the legitimacy of its descent, the rule has in my view a valuable part to play in protecting the interests of justice.”
"49…: i) Where A has brought an action against B, a later action against B or C may be struck out where the second action is an abuse of process. ii) A later action against B is much more likely to be held to be an abuse of process than a later action against C. iii) The burden of establishing abuse of process is on B or C or as the case may be. iv) It is wrong to hold that because a matter could have been raised in earlier proceedings it should have been, so as to render the raising of it in later proceedings necessarily abusive. v) The question in every case is whether, applying a broad merits based approach, A's conduct is in all the circumstances an abuse of process. vi) The court will rarely find that the later action is an abuse of process unless the later action involves unjust harassment or oppression of B or C. 50. Proposition ii) above seems to me to be of importance because it is one thing to say that A should bring all his claims against B in one action, whereas it is quite another thing to say that he should bring all his claims against B and C (let alone against B, C, D, E, F and G) in one action. There may be many entirely legitimate reasons for a claimant deciding to bring an action against B first and, only later (and if necessary) against others. 51. Those reasons include, for example, the cost of proceeding against more than one defendant, especially where B is apparently solvent and the case against B seems stronger than against others. More defendants mean more lawyers, more time and more expense. This is especially so in large commercial disputes. It by no means follows that either the public interest in efficiency and economy in litigation or the interests of the parties, including in particular the interests of C, D and E, is or are best served by one action against them all. 52. It seems to me that the courts should be astute to ensure that it is only in a case where C can establish oppression or an abuse of process that a later action against C should be struck out. I could not help wondering whether the defendants in this case would have given their lawyers the same instructions on the question whether they should have been sued in the first action if they had been asked before that action began as they have given now that a later action has been begun. 53. It is clear from the speeches of both Lord Bingham and Lord Millett that all depends upon the circumstances of the particular case and that the court should adopt a broad merits based approach, but it is likely that the most important question in any case will be whether C, D, E or any other new defendant in a later action can persuade the court that the action against him is oppressive. It seems to me to be likely to be a rare case in which he will succeed in doing so."
“77. …as the Aldi Stores Ltd case again makes clear and as Sir Anthony Clarke MR stresses, a claimant who keeps a second claim against the same defendant up his sleeve while prosecuting the first is at high risk of being held to have abused the court's process. Moreover, putting his cards on the table does not simply mean warning the defendant that another action is or may be in the pipeline. It means making it possible for the court to manage the issues so as to be fair to both sides.”
“96. For my part, I do not think that parties should keep future claims secret merely because a second claim might involve other issues. The proper course is for parties to put their cards on the table so that no one is taken by surprise and the appropriate course in case management terms can be considered by the judge. In particular parties should not keep quiet in the hope of improving their position in respect of a claim arising out of similar facts or evidence in the future. Nor should they do so simply because a second claim may involve other complex issues. On the contrary they should come clean so that the court can decide whether one or more trials is required and when. The time for such a decision to be taken is before there is a trial of any of the issues. In this way the underlying approach of the CPR, namely that of co-operation between the parties, robust case management and disposing of cases, including particular issues, justly can be forwarded and not frustrated. 97. While these considerations have been highlighted in the Aldi Stores Ltd case[2008] 1 WLR 748 , they have been relevant considerations at least since the CPR came into force in 1999…”
“If M+W had brought its claim in misrepresentation against Outotec in the EWHL Proceedings, the entire litigation would have become completely unmanageable for all parties involved”
“We confirm that it is our intention to hold you fully liable under the subcontracts and we will seek remedy to the extent available under the subcontracts and at law or in tort for all losses and costs incurred”
“In 2022, Metso announced that it intended to divest itself of its EfW operations in the USA. Since then, the Outotec business has rapidly declined”
“Further, or alternatively, M+W will rely on the defects in the equipment supplied, as set out below at paragraphs 69 to 76, which collectively and/or severally demonstrate that Outotec did not have either proven plant or technology at the time the representations were made, at any other time prior to entry into the Subcontract.”