“(4) Not later than 9 days before the dates for payment set out in the Schedule of Due Dates referred to in the Numbered Documents or in the Sub-Contract Particulars (as the case may be) (in each case the "Application Date"), the Sub-Contractor shall submit applications for payment to ISG's financial manager/surveyor… (6) The due date for payment of any interim payment shall be the relevant date set out in the Schedule of Due Dates referred to in the Numbered Documents or in the Sub-Contract Particulars (as the case may be) or, if the relevant application for payment issued by the Sub-Contractor is submitted after the date required for its submission by clause 2(4), the relevant due date shall be postponed by the number of days by which the application is late. Provided always that the last due date for payment of any interim payment shall not fall after the expiry of a 3 month period following practical completion of the Works, and the Sub-Contractor shall not be entitled to submit any application for payment in respect of any interim payment after expiry of that period… (8) ISG shall notify the Sub-Contractor in writing within 5 days of the relevant due date for any interim or final payment of the amount ISG considers to be, or to have been, due at the due date and the basis on which such amount is calculated. The payee shall submit a tax invoice to the payer for payment of the notified amount. Subject to any Pay Less Notice issued in accordance with clause 2(10), the payer shall pay the payee the amount so notified on or before the final date for payment… (10) The payer shall, if it intends to pay less than the sum stated as due from it in the relevant payment notice issued by it in accordance with clause 2(8), issue notice of that intention (a "Pay Less Notice") not later than 2 days before the final date for payment of the relevant notification of the amount specifying both the amount the payer considers to be due to the payee at the date the notice is given and the basis on which that amount has been calculated. Where a Pay Less Notice is given, the payment to be made on or before the relevant final date for payment shall be not less than the amount stated as due in that notice… (17) The Sub-Contractor and where applicable ISG shall submit any application for payment or invoice in accordance with clause 31. In relation to the requirements for giving notices under clauses 2(4), 2(8) or 2(10) it is immaterial that the amount then considered to be due may be zero. Payments shall be made by ISG to the Sub-Contractor if the relevant notice states that the amount is due to the Sub-Contractor, and by the Sub-Contractor to ISG if the relevant notice states that the amount is due to ISG.”
“(1) This section applies in a case where, in relation to any payment provided for by a construction contract— (a) the contract requires the payer or a specified person to give the payee a notice complying with section 110A(2) not later than five days after the payment due date, but (b) notice is not given as so required. (2) Subject to subsection (4), the payee may give to the payer a notice complying with section 110A(3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the contract to be given. (3) Where pursuant to subsection (2) the payee gives a notice complying with section 110A (3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given. (4) If— (a) the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person of— (i) the sum that the payee considers will become due on the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated, and (b) the payee gives such notification in accordance with the contract, that notification is to be regarded as a notice complying with section 110A (3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection),”
“(3) A notice complies with this subsection if it specifies— (a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and (b) the basis on which that sum is calculated.” (a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and (b) the basis on which that sum is calculated.”
“The due date for payment of any interim payment shall be the relevant date set out in the Schedule of Due Dates referred to in the Numbered Documents or in the Sub-Contract Particulars (as the case may be) or, if the relevant application for payment issued by the Sub-Contractor is submitted after the date required for its submission by clause 2(4), the relevant due date shall be postponed by the number of days by which the application is late…”
“ISG shall notify the Sub-Contractor in writing within 5 days of the relevant due date for any interim or final payment of the amount ISG considers to be, or to have been, due at the due date and the basis on which such amount is calculated. The payee shall submit a tax invoice to the payer of payment of the notified amount. Subject to any pay less notice issued in accordance with clause 2(10), the payer shall pay the payee the amount so notified on or before the final date for payment.”
“The payee shall submit a tax invoice to the payer for a payment of the notified amount.”