“Subsequent to further (non-intrusive) inspections carried out in 2019, the following further defects were detected and/or are reasonably suspected as being included in the construction of the Buildings of the Development. These amounted to defects and/or further breaches of the said requirements of theBuilding Regulations 2000 . The Schedule of Defects provides a full list of these defects, their location, the statutory requirements that apply and particulars of the alleged breaches thereof, as well as the proposed remediation works and estimated cost of remediation (including the rain screen cladding which is item 1) … ”
“(1) Additional remedial works costs outside NHBC cover: the Buildmark Policy only covers “necessary repairs”
“… the Claimants now… claim damages of approximately£5.8m to reflect the supposed costs of re-doing all of the Replacement Works to all of the blocks in which they have flats. This claim is brought on the basis of a concern that the new cladding might not comply with Building Regulations. The claim is not legitimate because: (1) They do not positively assert a single example whereby the Replacement Works do not or will not comply with Building Regulations. (2) In the event that the Replacement Works were to contravene Building Regulations the costs of re-doing the Replacement Works would be met by insurers. The NHBC confirmed to residents in January 2020 that they should be contacted in the event an issue arose with the completed works. (3) There is no legal basis on which any group of tenants, let alone the small minority of the tenants that form the Claimants in these proceedings, are entitled to such relief.”
“The court may strike out a statement of case if it appears to the court: … (a) that the statement of case discloses no reasonable grounds for bringing or defending the claim; (b) that the statement of case is an abuse of the court’s process or is otherwise likely to obstruct the just disposal of the proceedings …”
“Panels & Insulation … The documents that have been disclosed do not demonstrate that, at the time of design or construction, the combustible ACM rain screen or Cedar rain screen cladding that were installed over combustible K15 insulation match the classification criteria or BR135 using test data from BS8414.” ii) At paragraph 73 of the Particulars of Claim the alleged breach in respect of the Backing Wall & Window Support is pleaded as follows: “Behind the ACM and Kingspan K15 insulation, the backing wall to the rain screen system is a sheathing board that contains a content of wood chip that is likely to render the sheathing board Class B at best when classified in accordance with BS EN 13501 and pressure treated timber supports to windows that are believed to be Class C when classified in accordance with BS EN 13501. On this basis, (and in the absence of a BR 135 classification using test data from BS8414 and intrusive inspection) the curtain walling and windows did not comply with requirement B4(1) and paragraph 12.7 of Approved Document B.” iii) At paragraph 75 the pleaded allegation in respect of Cavity Barriers is: “The documents disclosed for the proposed remedial Building Work do not demonstrate the test or certification evidence upon which the specification of the new open state cavity barriers has been based such that it would be ensured that the cavity barrier will close the cavity against articulated surfaces of the cladding system such as returns in the panel trays.”
“The opaque and spandrel panels within the curtain wall and windows are assumed to have contained combustible materials and insulation …” ii) Likewise, item 4 is pleaded at paragraph 77 as: “It is assumed that fire stopping should have been installed between the curtain wall and the compartment floor slab. Fire stopping on compartment floor lines between slab edges and internal faces of curtain walling is likely to be defective or missing in places …”
“[37] In my judgment … the key question must always be whether or not, at the time of issuing a Writ, the claimant was in a position properly to identify the essence of the tort or breach of contract complained of and if given appropriate time to marshal what it knew, to formulate Particulars of Claim. If the claimant was not in a position to do so, then the claimant could have no present intention of prosecuting proceedings, since it had no known basis for doing so. Whilst therefore the absence of present intention to prosecute proceedings is not enough to constitute an abuse of process, without the additional absence of known valid grounds for a claim, the latter carries with it, as a matter of necessity, the former. If a claimant cannot do that which is necessary to prosecute the claim by setting out the basis of it, even in a rudimentary way, a claimant has no business to issue a Claim Form at all "in the hope that something may turn up". The effect of issuing a Writ or Claim Form in such circumstances is, so the plaintiff/claimant hopes, to stop the limitation period running and thus deprive the defendant of a potential limitation defence. The plaintiff/claimant thus, unilaterally, by its own action, seeks to achieve for itself an extension of the time allowed by statute for the commencement of an action, even though it is in no position properly to formulate a claim against the relevant defendant. That must, in my judgment, be an abuse of process and one for which there can be no remedy save that of striking out the proceedings so as to deprive the claimant of its putative advantage. The illegitimate benefit hopefully achieved can only be nullified by this means. Whatever powers may be available to the court for other abuses, if this is an abuse, there is only one suitable sanction. … [40] Although defectively endorsed Writs could be cured by subsequent statements of claim in the ordinary way, such cure depended upon the plaintiff having a known genuine cause of action at the time of the issue of the Writ and the irregularity merely being the failure properly to set it out. As appears from the decisions discussed earlier, that principle is of no application where the plaintiff had no known basis for making the claim at the time when the Writ was issued.”
“[232] … if there is a defect in the roof above a penthouse apartment caused by [the contractor’s] poor workmanship so that the apartment is unfit for habitation, the loss sustained by the owner of the apartment is, in my opinion, the lack of, and need for, a sound roof. Ordinarily, the compensation for that loss would be the sum of money representing the cost of the necessary repairs. If it is the case that the carrying out of those repairs will necessarily benefit other leaseholders who are not claimants, I do not see how that can affect the particular claimant's right to compensation. [233] … In my judgment the owner of an apartment which has been rendered unfit for habitation because of a defect in the common parts is entitled to the cost of repairing that defect, or at least to the cost of carrying out those repairs necessary to make his flat fit for habitation. [234] So, staying with my example, the owner of a penthouse apartment on the top floor which was rendered unfit for habitation because of the state of the roof is in my view entitled to recover the cost of the work to the roof that is necessary to render his apartment fit for habitation. Nothing less will restore him to the position that he would have been in if the breach had not occurred. If that owner is awarded only his share of the service charge, he will then be dependent on all the remaining leaseholders agreeing to fund the balance of the cost of repairing the roof. But if they or some of them refuse, then the work may never be done.”