“In a number of the authorities which I have cited above the point has been made that each case must turn on its own facts. Whilst I respectfully agree with that, it does seem to me that there are a number of clear principles which should always govern the exercise of the court's discretion when it is considering a stay of execution in adjudication enforcement proceedings. Those principles can be set out as follows: a) Adjudication (whether pursuant to the 1996 Act or the consequential amendments to the standard forms of building and engineering contracts) is designed to be a quick and inexpensive method of arriving at a temporary result in a construction dispute. b) In consequence, adjudicators' decisions are intended to be enforced summarily and the claimant (being the successful party in the adjudication) should not generally be kept out of its money. c) In an application to stay the execution of summary judgment arising out of an Adjudicator's decision, the Court must exercise its discretion under Order 47 with considerations a) and b) firmly in mind (see AWG). d) The probable inability of the claimant to repay the judgment sum (awarded by the Adjudicator and enforced by way of summary judgment) at the end of the substantive trial, or arbitration hearing, may constitute special circumstances within the meaning of Order 47 rule 1(1)(a) rendering it appropriate to grant a stay (see Herschell). e) If the claimant is in insolvent liquidation, or there is no dispute on the evidence that the claimant is insolvent, then a stay of execution will usually be granted (see Bouygues and Rainford House). f) Even if the evidence of the claimant's present financial position suggested that it is probable that it would be unable to repay the judgment sum when it fell due, that would not usually justify the grant of a stay if: (i) the claimant's financial position is the same or similar to its financial position at the time that the relevant contract was made (see Herschell); or (ii) the claimant's financial position is due, either wholly, or in significant part, to the defendant's failure to pay those sums which were awarded by the adjudicator (see Absolute Rentals).”
“g) If the evidence demonstrates that there is a real risk that any judgment would go unsatisfied by reason of the claimant organising its financial affairs with the purpose of dissipating or disposing of the adjudication sum so that it would not be available to be repaid, then this would also justify the grant of a stay”
“Without derogating from that statement of principle a decision to enforce or not is an exercise of the court's discretion, which must balance the well known interest in enforcing valid adjudication decisions — for reasons that have been repeated frequently elsewhere and do not need further repetition now — against the perceived or actual risk of future injustice if the party subsequently becomes unable to reciprocate in the payment of what it owes under the same contract”
“In AWG Construction Services Ltd v Rockingham Motor Speedway Ltd, HHJ Toulmin CMG QC observed that, whilst it was not possible to say how far an applicant had to go in putting evidence before a court in support of a stay, it should be noted that the court should not grant a stay unless, consistent with the overriding objective in the CPR, the justice of the case demanded it. In addition, the judge indicated that one matter that the court might consider is the diligence with which the defendant pursued its cross-claim or challenge to the adjudicator’s original decision. If the claimant was to be kept out of its money at all, it should be for the shortest reasonable time, so that the right approach might well be to grant a stay for a limited time originally, with extensions depending on the conduct of the parties. By contrast, a failure by the defendant to pursue its cross-claim or challenge with diligence may itself be a bar to a successful application for a stay of execution.”
“No litigation by PAML against BLL to obtain a finaldetermination “33. In many of the cases in which a defendant to adjudication enforcement proceedings has sought a stay of execution, that party has commenced litigation or arbitration to try to obtain a final determination that the sum awarded by the adjudicator is not due (or a lower sum is due). “34. That is because such litigation or arbitration is assumed to be underway by principle (d) in Wimbledon (by the words “at the end of the substantive trial”). “35. In this regard, see Coulson, at paragraph 17.30. See also ALE Heavylift v MSD (Darlington) Ltd[2006] EWHC 2080 (TCC) [2006] EWHC 2080 (TCC) , HHJ Toulmin CMG QC, at paragraph 100: “I must also take into account the fact that MSD has not commenced any form of proceedings to recover sums to which it claims to be entitled although it could have done so. It is therefore impossible to predict the date on which, if MSD is successful in those proceedings, ALE would be liable to repay the money and the financial circumstances in which it will be placed at that date.” “36. BLL’s Contract with PAML provides – in the JCT Agreement completed on behalf of PAML – for litigation, by way of an English court jurisdiction agreement (JCT Agreement, Article 9 [1/7/61]; the Contract Particulars stated that Article 8 (Arbitration) did not apply [1/7/61]). “37. PAML has taken no steps to litigate against BLL. “38. Thus, as in ALE, it is impossible to predict the date on which PAML might be successful in obtaining a final determination that the sum awarded by the adjudicator is not due (or a lower sum is due). “PAML chose to take other steps to try to avoid paying BLLwhich were inconsistent with it litigating against BLL to obtaina final determination “39. At the start of Adjudication 3, on16 October 2019 , PAML (through its then solicitors, Costigan King) sought to persuade the Adjudicator to resign on the basis that PAML was not BLL’s Employer under the Contract, and in fact there was no contract at all [1/7/320]. “40. It was also suggested in Costigan King’s letter of16 October 2019 that Adjudications 1 and 2 had not been conducted on behalf of PAML [1/7/320]. “41. Costigan King’s letter of16 October 2019 [1/7/320] created obvious concerns for BLL who, for example, sought to engage with Gateley [1/7/344] to confirm who – if not PAML – Gateley had been acting for in Adjudication 1 and Adjudication 2 – the latter having been started by the “Trust” against BLL. “42. After Costigan King’s letter of16 October 2019 did not succeed in obtaining the Adjudicator’s resignation, on1 November 2019 PAML switched to arguing that Decision 2 (which it now implicitly accepted along with the Contract) somehow meant that the sum ordered due in Decision 1 should not be paid [1/7/373, #78(b)]. “43. While Adjudication 3 progressed (with Costigan King sending and receiving submissions for PAML), PAML nevertheless refused to give Costigan King authority to accept service of these proceedings. The upshot of this was that BLL would have to seek to serve PAML in North Cyprus, unless the Court ordered service by alternative means (upon Costigan King). BLL duly applied to this Court for such an order, which was granted. “44. None of the above tactics would have been open to PAML if PAML had commenced litigation against BLL to obtain a final determination, so that it might now try to rely upon principle (d) in Wimbledon. “45. It is submitted that given all the circumstances, it does not fall to PAML to now ask this court to exercise its discretion in favour of a stay of execution.” “I must also take into account the fact that MSD has not commenced any form of proceedings to recover sums to which it claims to be entitled although it could have done so. It is therefore impossible to predict the date on which, if MSD is successful in those proceedings, ALE would be liable to repay the money and the financial circumstances in which it will be placed at that date.”
“(2) Such a feature is only likely to arise in a very small number of cases, and in exceptional factual circumstances. This addition to the principles is not intended to re-open the whole issue of the basis upon which stays of execution will be ordered in adjudication enforcement cases, or to define a specific, exhaustive and closed set of circumstances that can constitute “special circumstances” in the terms ofCPR Part 83.7 (4). In the vast majority of cases, the existing principles in Wimbledon v Vago will suffice and recourse to principle (g) will be extremely rare. “(3) A high test will be applied as to whether the evidence does indeed reach the standard necessary for this principle to apply. I consider that in order to fall into this category the standard is broadly the same as that necessary to justify the grant of a freezing order (what used to be called Mareva relief). “(4) The addition of this further principle is not designed to prevent a claimant from dealing with the adjudication sum in the ordinary course of business, or make evidence of what a claimant may be intending to do in the future, in the ordinary course of business, relevant or admissible under this head. The whole purpose of adjudications being summarily enforceable would be frustrated if all a winning party could do with any payment was to place it in an account, and not use it, to avoid the risk of a stay of execution being ordered.