“13.1 Unless otherwise set out in the Offer Letter, all intellectual property rights, including without prejudice to the generality of the foregoing, copyrights, patents, know how and any other intellectual property rights howsoever arising in all documents and drawings shall remain the property of Ridge. 13.2 Ridge grants a non-exclusive, royalty free licence to the Client to use or reproduce drawings, documents or data produced by Ridge in connection with the Services for all reasonable purposes in connection with the Project and/or Services. …. 13.5 Ridge shall provide copies of any drawings, documents or data required by the Client pursuant to clause 13.2 and shall be entitled to its reasonable copying and administrative costs of providing such copies.”
“The Recipient shall upon the request of the Bakery at any time and within 10 working days of such request, return or destroy (at the Bakery’s option) all Confidential Information of the Bakery and all documents, notes, memoranda, papers, records, disks and any other material relating thereto or which bears or incorporated any of that Confidential Information or any information derived from it …..” (iv)Clause 10: “The provisions of this Agreement shall continue to apply notwithstanding that the Bakery may or may not engage the recipient for the Purpose and notwithstanding the completion of the services or the termination of the Recipient’s engagement at any time.”
“With regards to your generic request for Project Documentation, Leicester Bakery have been issued all documentation produced by Ridge in the course of the project delivery so will be able to provide this information directly to the new Employer’s Agent. We would also confirm that the termination of our agreement includes the termination of all Clients rights under the agreement.”
“LB has a more pressing issue in requiring access to documentation. Mr Sandell alleged in an email of 19 March that all information had been handed over, patently that is not the case.”
“Your assertion that Leicester Bakery do not have all documentation on the project is incorrect. The documentation referred to in the adjudication notice are emails sent to Leicester Bakery and minutes of meetings at which Leicester Bakery attended. In addition, as directly instructed by Leicester Bakery, their Client Representative was acting on their behalf and was party to the correspondence and documentation referred to in the Adjudication.”
“It is apparent from the adjudication that took place in December 2018 relating to the staircase that drawings were not sent on to LB and that discussions were entered into and agreements made to which LB was not privy. Accordingly, drawings, reports, site visits and surveys need to be disclosed to ensure LB has everything because LB is constantly being surprised in adjudication proceedings and needs full disclosure to cover the gaps that are clearly present.”
“This clause is drafted very widely and covers all documents, drawings and other media associated with the Works. … This is a collateral contractual obligation to provide disclosure of all documentation and as it has not been provided will be presented to the Court as further evidence of your unreasonable behaviour in breach of two separate contracts.”
“Thank you for confirming that you intend to breach the disclosure obligations of both agreements without proper cause.”
“We again reiterate our request that you provide us with all the documents we required. We confirm that we will pay the reasonable costs of you providing those documents.”
“Following the making of the Demand [20 March 2019 ], the Defendant did deliver-up certain documents and stated to the Claimant that it had delivered up all such documents. However, the Claimant has subsequently discovered in the course of a dispute with a sub-contractor that certain documents had not been delivered up but had, wrongfully and in breach of contract and/or breach of fiduciary duty been provided to the sub-contractor to assist the sub-contractor in its claim against the Claimant.”
“The Claimant is currently unable to plead as to what (if any) losses have been suffered as a consequence of the Defendant’s breach of contract and/or breach of fiduciary duty and/or breach of bailment and/or conversion but reserves the right to plead further as to such losses following delivery-up of the Documents and/or disclosure in this action.”
“28. The prejudice of the Defendant’s refusal to comply with its obligation to deliver up documents and information as required by the Services Agreement and the Agreement has already been suffered by the Claimant in the first adjudication with the Contractor by virtue of the Claimant being bound by agreement with the Contractor which had been agreed by the Defendant. The Claimant conducted the adjudication without the relevant documents and in consequence sought to defend claims in circumstances where it would have compromised those claims if it had been aware of the existence of the documents that were provided by the Defendant to the Claimant. 29. As a consequence, the Claimant has incurred: (1) its own costs; and (2) costs that it will pay to its contractor that were caused by the Defendant’s breach of contract and/or fiduciary duty. Further, the Claimant lost the chance to settle the dispute on more favourable terms by being deprived of the documents that would have allowed it to take proper advice as to its legal position.”
“30. Paragraph 10.2 is noted. The dispute with GFT is irrelevant to the Claimant’s claim herein save that: (1) in the course of the said dispute it became apparent that the Defendant had not disclosed all of the “project documentation produced by Ridge” as stated by Mr Sandell; and (2) that the Claimant’s ability to conduct its case in that dispute was prejudiced by the Defendant’s failure to provide the Documents and/or certain individual documents that were relied on by GFT and of which the Claimant had no prior knowledge.”
“The defendant looks forward to receiving the claimant’s Initial Disclosure List of Documents and copies of the documents listed therein by the close of business today, including but not limited to any submissions and decision the adjudications between the claimant and its Contractor, GF Tomlinson & Sons.”
“At no time was the Listing Office informed that the parties had agreed to vacate the CMC. We had contacted the Court to express our view that a final hearing for the injunction would be a more appropriate listing than a CMC in this matter. This was to be investigated and it was agreed with the Court that if any changes to the listing occurred, we would inform you. We heard nothing further from the Court in this respect so it was assumed the CMC would be going ahead prior to the Court listing a final hearing. …. We remain of the view that a final hearing is the appropriate listing to deal with this matter effectively. A CMC is not necessary and has only arisen because the proceedings have been transferred, at your request. In any event, the CMC has now been vacated. It would be both beneficial and cost effective for the parties to co-operate in obtaining a listing from the Court for a final hearing to bring this matter to a close.”
“This was an application for an injunction to be made final at a subsequent hearing after the interim injunction was granted in our client’s favour and in respect of which your client has partially complied. The question is whether the injunction is made final or not; that’s it.”
“As a consequence of the failure to disclose documents properly or at all and in a timely fashion in response to the demands made by the Defendant, the Claimant was unable to prepare its evidence to respond to the claims made by the contractor in the March 2019 Adjudication.” (vi) Paragraph 16O then pleads that as a consequence of the absence of such evidence, the adjudicator gave the extensions of time that he did. (vii) From paragraph 16Q, the Claimant pleads its case as to loss and damage. The content of paragraphs 16O and 16Q is repeated. It is then said that as a consequence of the extensions of time, the Claimant lost the right to claim liquidated damages of£387,000 in relation to the Main Unit and£292,600 in relation to the Retail Units – a total of£679,600 . Further, it is said that the Contractor has submitted a further claim for£500,000 in relation to extended preliminaries “that would not have been necessary but for the Defendant’s unlawful acts”. (viii) At paragraph 16V, the Claimant claims damages or equitable compensation in a sum of not less than£1,170,600 (which is the total of the sums above). (ix) At paragraph 16W, the Claimant pleads further or in the alternative, a claim for damages or equitable compensation “for the loss of the chance to succeed in the March 2019 adjudication ….” (my emphasis). (x)Paragraph 16X the provides: “The Claimant is currently engaged in an arbitration with the contractor in an attempt to reduce its losses as more particularly set out above. The Claimant will plead further when the result of the arbitration is known.”
“(a) … An amendment is late if it could have been advanced earlier, or involves the duplication of cost and effort, or if it requires the resisting party to revisit any of the significant steps in the litigation (such as disclosure or the provision of witness statement and expert’s reports) which had been completed at the time of the amendment. … (c) The history of the amendment, together with an explanation for its lateness, is a matter for the amending party and is an important factor in the necessary balancing exercise. … In essence there must be a good reason for the delay.”