“I would only assume we are talking about the vibration and the structure because if we are talking about production, well, it shows from what we produced and also it will show that if it is great, why are we here?”
“…my client contacted your agent but [s]he faced many technical and legal troubles such as: delay in provision and supplement of spare parts for 42 days which caused dropout in my client production line which resulted in financial losses amounted to million$2,560,000 ; your agent has sent to my client 30 nets and after operating [s]he found them of poor type in violation of specifications stated in the contract as they don’t last more than 10 days while they (sic) life span exceed one month, noting that they didn’t send a technician as previously made.”
“The work scope will be to spend 3 days maximum on the plant to start up, make sure they get the required product quality, achieve the rate, define the spare mesh specs and get them to sign off on the remaining 10% they owe.”
“The other thing on the loading seems high on the middle deck and the blinding on the middle deck, the middle deck isn’t doing anything but unloading. It is very academic at this point. If the loading was high on the top deck, I would be much more concerned. If the loading was high on the bottom deck, I would be much more concerned.”
“Please confirm that I should base the preliminary sizing on product C, 106 to 500 micron duty. If you are only producing this fraction, say, 10% of the time it may be worth basing the sizing on your most frequently required product and accepting a slightly lower rate for 10% of the time.”
“I have also noticed that you are currently using inclined vibratory technology. For your information we would expect to offer a greater product yield for the equivalent area with a sharper separation as we would be able to fit meshes closer to your required cut point. For my information, could you please provide an overview of your current set up and yields. I would like to test your sand in our factory to demonstrate the efficiencies we could provide while at the same time confirm machine sizing and model selection. We would need about 50kg of your feedstock to do this. Following receipt of this information I will work on a provisional offer.”
“As a test will be conducted and to size aggressively a rate of 4 TPH/m² will be used”
“I have discussed this with Mike [Birt] and he thinks 3 x 4240-2 would be a better option from a mesh life point of view but we concluded that our combined experience with the minerals separator and deck loading benefits was not sufficient to make a final decision at this time.”
“Mesh blinded due to heavy burden and insufficient ball action. Would increase ball action on the production unit. Product out of spec. Retest at slightly faster rate, i.e approx 50m² requirement.”
“Increased to 2 balls per pocket. Just in Spec. Will combine this fraction with overs and run additional tests.”
“When I saw this and the particle size distribution I saw it [as] a scalping and fines removal operation and I thought we would be able to get a higher rate on this machine.”
“…what we have done over time is we go and, after machines in the field are run, we check back to the lab tests and make sure the machines in the fields are operating at that. And we typically are either running at a 5% or a 10% safety factor.”
“Maybe not with the safety factor when you are looking at that.”
“We refer to your recent inquiry in relation to your requirements for screening Silica Sand. For this application we are offering three (3) x Model MM3180-3 minerals machines. The MM3180-3 is a three (3) deck unit offering a screen area of 16.7M² per separation. We can confirm following test that the total screen area required to do the 200 TPH duty is 50.1M² (per separation level) therefore 3 units are required. Please find proposal, outline drawing and laboratory report attached to my e-mail. We feel three decks offer you greater flexibility. For example, if you run with the 600, 500 and 106 micron decks fitted you could make two products, the 500/106 and, if you reblend the 500/600 fraction back in, you can make the 600/106 product. In addition, and due to the machine being a parallel bank of screens where the feed is evenly distributed to two sides, you could even make the 500/106 product on one side of the machine and the 850/106 product on the other for instance. Alternatively you could fit the machine with an 850, 600 or 500 top deck and a 106 bottom deck with a load relieving mesh fitted to the middle deck increase mesh life on longer production runs.”
“Other screen manufacturers will be able to offer either good product quality or high screening efficiency but not both like Rotex gyratory equipment. As you have a high specification, other manufacturers will concentrate on producing this but please pay attention to the product recovery efficiency. Even for a relatively small 2% efficiency improvement the payback is worth noting. For Example. Through test we have established that we can offer equipment to provide the 98% on size requirement with a high product recovery efficiency of 94.4% (please refer to lab report). Being conservative, let’s say the inclined vibratory models such as the ones installed at your plant currently can offer the same product grade but they are 2% less efficient at removing saleable product from the feed. The tables below outline exactly what that means to your plant… As you can see from the above, the difference will be made up within a year of production dependent on how many production hours your plant works per year and that does not include the installation cost difference or the fact that we are offering an extra deck and greater flexibility. This is for 2% greater efficiency only, please check your other lab reports and calculate for yourself.”
“Thank you for your inquiry. We are pleased to quote for acceptance within 30 days. APPLICATION DATA: 118. Material: Silica Sand Separations: 500 & 600 Micron Bulk 1600 KG/M 3 Specification: 98% 500 to 106 Micron 119. Density: Feed Rate: 200 T/HR Temperature: Ambient °C PROPOSAL SUMMARY: (3). Rotex Minerals Separator Model MM 3180-3 High Capacity Screener Eighteen (18) deck unit with nominal screen area of 16.7M² per deck. Motor: 15 HP, 1200 RPM, 3 Phase, 60 Hz, 450 Volt , TEFC motor. Dimensions: As shown in Rotex preliminary outline drawing #183754 Installation: Machine installed by hanger support shaft suspension. … 121. Screen Clothing •. 0.5mm Aperture, 0.16mm diameter, 304/SS wire screen cloth, 48” x 90”, made up with edging and grommets and applied to the top deck screen frames on the above machine (6 Req’d.) •. 0.25mm Aperture, 0.09mm diameter, 304/SS wire screen cloth, 48” x 90”, made up with edging and grommets and applied to the middle deck screen frames on the above machine (6 Req’d). (For example only, other mesh could be selected to make other separations and provide flexibility, D50 of sample was 244 Micron so 250 micron mesh selected for quotation purposes only. In the event of an order this could be discussed and finalized). •. 0.118mm Aperture, 0.056mm diameter, 304/SS wire screen cloth, 48” x 90”, made up with edging and grommets and applied to the bottom deck screen frames on the above machine (6 Req’d).”
“Great job Neil. Let me know if I missed anything. As soon as you get the official PO get the data to Colin so we can start to coordinate production. Andrew has already alerted Cincinnati.”
“following your official acceptance and my return to the UK . . . we will commence with the primary engineering phase where we will provide you with design drawings and layout drawings for your acceptance.”
“14. In Hardwick Game Farm v SSAPA[1969] 2 AC 31 there was a series of oral contracts between SSAPA and its supplier, Grimsdale, for meal to be fed to game birds. Each contract was followed by a Contract (or Sold) Note sent by the sellers which contained on the back what were described as “Conditions of Sale”
“... I consider that reasonable notice of the terms was given by the plaintiffs. Putting it another way, I consider that the defendant’s conduct in continuing the course of business after at least 11 notices of the terms and omitting to request a sight of them would have led and did lead the plaintiffs reasonably to believe the defendants accepted their terms. In those circumstances it is irrelevant that in fact [the managing director] did not read the notices.” 18. Bingham LJ (as he then was) said, at page 435, that the only possible answer to the question “Has reasonable notice of the terms been given?” was that it had. 19. Again, this appears to have been a case where the course of dealing consisted of a number of transactions carried out in precisely the same way. 20. The facts of Balmoral Group v Borealis (UK)[2006] EWHC 1900 (Comm) were a little more complicated. Between 1994 and mid-2002 Balmoral made nearly 400 purchases of polyethylene from one or more companies in the Borealis group. By a fax dated18 January 1995 Borealis made it plain that its prices were quoted “… subject to normal terms and to current conditions of sale”, and these terms were put on the back, or as one of the pages, of the invoices submitted by Borealis to Balmoral. These invoices were seen and initialled by Balmoral’s managing director: he realised that there were terms on the back of the invoices but he did not study them. 21. From December 1995 Balmoral’s purchase orders referred to Balmoral’s terms, albeit in rather poor typescript at the bottom of the purchase orders, but these were never otherwise referred to or provided to Borealis. Christopher Clarke J (as he then was) found that there were no customary terms in the polymer trade in the UK in the sense of terms which are so “… certain, notorious and reasonable …” that anyone purchasing polymer must be taken to have contracted on those terms, unless expressly excluded or otherwise agreed. But he did find that suppliers of polymer in the UK habitually seek to sell on their standard terms and conditions. 22. The procedure was that when an order was received someone at Borealis, after checking that the price on the order was the same as that on the price list, would check with the supplying plant that delivery could be made. If it could, someone at Borealis would confirm the order (probably by telephone) to someone at Balmoral. Delivery would then take place and, a couple of days thereafter, an invoice would be sent to Balmoral with Borealis’s terms on the back. 23. Having considered the Circle Freight and Hardwick Game Farm cases, together with other authorities, Christopher Clarke J said, at [348]: “Whether or not one party’s standard terms are incorporated depends on whether that which each party says and does is such as to lead a reasonable person in their position to believe that those terms were to govern their legal relations. The Court has to determine what each party was reasonably entitled to conclude from the acts and words of the other ... The question is one of fact to which prior authority may form an uncertain guide.” 24. Christopher Clarke J concluded that, since Balmoral had purchased material at the quoted prices and had paid the invoices submitted by Borealis with the knowledge of Borealis’s conditions and without ever suggesting that they were not applicable, Borealis was reasonably entitled to assume that Balmoral accepted that its conditions applied. 25. In Sterling Hydraulics Ltd v Dichtomatik Ltd[2007] 1 Lloyd’s Rep 8 His Honour Judge Havelock-Allan QC had to consider a “battle of the forms” case. The claimant, SHL, always placed its orders with the defendant, DL, using its standard form of purchase order. This said: “Please supply the following subject to the terms and conditions as set out below and overleaf.”
“Delivery based on our General Terms of Sale”
“This appeal raises the question whether in what is sometimes called ‘the battle of forms’, there can be circumstances in which a traditional offer and acceptance analysis can be displaced by reference to the conduct of the parties over a long-term relationship. An offer to buy containing the purchaser’s terms which is followed by an acknowledgement of purchase containing the seller’s terms which is followed by delivery will (other things being equal) result in a contract on the seller’s terms. If, however, it is clear that the neither party ever intended the seller’s terms to apply and always intended the purchaser’s terms to apply, it is conceptually possible to arrive at the conclusion that the purchaser’s terms are to apply. It will be a rare case where that happens. Do the facts of this appeal amount to that rare case?” 30. He went on to describe the course of dealing in the following terms, at [7]: “The judge found that Amphenol acknowledged the purchase orders by sending an acknowledgment to Tekdata. In law it could only be at that date at earliest that a contract for the purchase and sale of the specified connectors came into existence. The acknowledgment, however, stated that Amphenol’s terms and conditions were to apply and the traditional view would be that, if no further documentation passed between the parties and if Tekdata took delivery of the connectors, the contract would be on the terms of Amphenol’s acknowledgement. The judge, however, held that it was never intended that Amphenol’s terms should apply because the parties had always intended that Tekdata’s terms were to apply. He seems to have concluded, although he did not expressly say so, that the clause (at the bottom right hand corner of the acknowledgement) about the application of Amphenol’s terms was to be ignored and that the contract came into existence when the acknowledgment was returned to Tekdata.” 31. Dyson LJ said this, at [25]: “... it is not possible to lay down a general rule that will apply in all cases where there is a battle of the forms. It always depends on an assessment of what the parties must objectively be taken to have intended. But where the facts are no more complicated than that A makes an offer on its conditions and B accepts that offer on its conditions and, without more, performance follows, it seems to me that the correct analysis is what Longmore LJ has described as the ‘traditional offer and acceptance analysis’, ie that there is a contract on B’s conditions.””
“i) Where A makes an offer on its conditions and B accepts that offer on its conditions and, without more, performance follows, the correct analysis, assuming that each party's conditions have been reasonably drawn to the attention of the other, is that there is a contract on B's conditions: see Tekdata. ii) … iii) The course of dealing by the party contending that its terms and conditions are incorporated has to be consistent and unequivocal: see Sterling Hydraulics. iv) … v) A party's standard terms and conditions will not be incorporated unless that party has given the other party reasonable notice of those terms and conditions: see Circle Freight. vi) It is not always necessary for a party's terms and conditions to be included or referred to in the documents forming the contract; it may be sufficient if they are clearly contained in or referred to in invoices sent subsequently: see Balmoral at [352], [356]. vii) …”
“I would offer a further variant, which may be easier for commercial men to apply. Would the parties have agreed that a particular term formed part of the contract if they were reasonable men looking at the matter objectively in the knowledge that no adverse consequences could flow from the answer. I add this latter qualification because even the most reasonable commercial man will become a little less than objective when told that the answer could cost him US$ 3 million . The term will only be contractual if the parties’ answer would have been a definite “Yes”. “Possibly” will not do.”
“First production of our plant”
“To be honest with you, I was not aware that the incorrect mesh was fitted at this point. I was not aware it was fitted until earlier this year, to be honest with you, until Mr Lieberwirth’s report. But it answers a lot of questions on the early stages. …The blinding, looking back, was the incorrect mesh specification fitted” …The blinding, looking back, was the incorrect mesh specification fitted”
“Dear Neil, about the statues [sic] of our minerals separator, is there any update? can you please send us a mesh slightly bigger than our current mesh “size 120”? we would like to test that to see if the blinding will be the same. also, in meanwhile what the things [sic] we can do to solve the problem? please tell me anything you found it useful . . . and we [sic] you can come to our site for solving this matters?”
“Hamed Aldrees and Partners accept the yields may change as a consequence of the revised specification and the varying feed particle size distribution.”
“I want to inform you that our customers are changing their [standards] for the new year. The [standards] vary from one customer and another, but generally the allowed fine materials in the product (below the 105 µm) shouldn’t exceed 0.8%.”
“The application was for silica sand with 200 T/Hr and separation of: 500 & 106 Micron, and specification of: 98% 500 to 106 Micron. According to your laboratory report (Num: 2269) based on a sample of our raw materials, the fines percentage in the final product was 1.65%. The first time the (sic) machines ran with materials was at6/6/2013 During the commissioning visit by Mr Neil Smith, and from then until now, the machines were unable to deliver sand with quality and the specification mentioned above. We are having a problem with the fines in the final product, the fines are reaching high levels, due to the blockage “blinding” of the meshes. There were a follow-up and communication with your company in the UK and allot (sic) of experiments and actions done on this (sic) machines to solve this matter, also another visit from Mr. Neil on: 4/Dec/2013 But until now, the problem still unsolved. We are hoping that you appreciate our situation that we are not able to produce silica sand by this (sic) machines because the quality level of the final product is not meeting with our customers requirements.”
“The fines level is not exceeding 0.5% on 37 TPH, tomorrow I will increase it to 45 TPH and check what happens.”
“Everything is good now, the fines level is not exceeding 0.5%, I’m increasing the feeding every 2 or 3 days, we have reached 37 TPH on both #4 and #5.”
“Rotex’s advice to change the bottom mesh meant that we were losing a significant amount of product between 0.118 mm and 0.145 mm, then 0.165 mm and eventually 0.170 mm. Consequently, Aldrees also decided to change the top mesh specification from 0.500 mm to 0.438 mm. This was so that we were able to sell a finer grade of silica sand (i.e between 0.150/155 mm - 0.420 mm) and so hopefully achieve a higher price. It was directly as a result of the product lost because of Rotex’s advice to change the bottom mesh specification that we did this.”
“Yes, of course” (Day 4/40). But a few minutes later, when it was put to him that the figure of 40 tonnes per hour mentioned in the minutes was in respect of the output, Mr Turk said (at Day 4/42): “It says the ratio of 40 TPH. I cannot say for sure if it is the output or the feed.”
“Shakers No. 4 and No. 5 are functioning properly by the ratio of 40 tonnes per hour and the screens for the remaining shakers are ordered.”
“Shakers No 2, No 3, No 4 and No 5 are functioning great - preparing to work on shaker No 1.”
“One Rotex shaker can produce a quantity of about 30 to 40 tons”
“Daily productivity of Rotex shakers = 30 tons * 5 shakers * 10 working hours = 1500 tons”
“Washing plant is currently working with a production capacity estimated of 60% of its capacity. Increasing the percentage will be gradually over 21 days as controlling the performance of the plant is conducted accurately. The washed product current measurement is 100-500. Daily production of washed sand: 455 tons Monthly productivity of the washed sand including the calculation of suspensions resulting from modifications and maintenance: 455 tons x 26 days x 77.3 = 9144 tons.”
“But this is estimating. Excuse me. This is estimation.”
“The main issue you have for reduced production level is due to the 0%> 500 micron requirement and the fact you are screening at 438 micron to achieve this, in addition to blinding but [sic] I believe you may be overfeeding the units slightly but your recent modifications to the sieve frames are providing good results. … Top mesh Evaluation: Screening at 438 micron, you are losing all the product sized material between 415 micron and 500 micron and this is affecting your plant output significantly. Please see feed PSD you provided during my visit for 23.04.2015 600 Mic – 9.550% 500 Mic – 10.227% 425 Mic – 27.972% 212 Mic – 19.065% 180 Mic – 13.071% 150 Mic – 8.331% 125 Mic – 6.265% Pan - 5.520% To be clear. Screening at 500 and 100 micron during the test, we discharged 83% of the entire fee as product which included on size with up to 2% overs and fines. If we recovered an 83% yield with 12.1% being removed as oversize with the rest discharged as fines. Screening at 438 micron, the oversize yield, based on the feed above increases to 47.749% (9.55 + 10.227% + 27.972%) from 12.1% with lots of product contained in the waste fraction. 47.749% oversize, equates to about 95.5 TPH at a feed rate of 200 TPH to 4 machines so nearly half the feed is discharged as waste at the moment. In addition, the available on size material is reduced from 87% 0.1 mm to 0.5 mm to 46.7% between 0.125 and 0.45 mm. That equates to 93.4 TPH (was 166 TPH in the test) if the 4 machines are fed at 50 TPH each. Divide that by 4 and we would expect each unit to discharge 23.4 TPH (ignoring product finds retention from the bottom deck now). . . . Lower Deck: The mesh fitted to the lower deck is 172 micron and synthetic. This mesh was selected due to blinding. The blinding is now more controllable with the modified ball pockets but screening at 172 micron, we would expect you to lose a little product sized material below 180 micron as you would expect. Because you are cutting at 172 micron, we would expect the product fraction to retain allot [sic] of the 150 micron to 180 micron product and about 50% of the <150 micron to 106 micron which is indicated in the final product specs. That means the product class at the lower end is low and output may further is [sic] reduced due to overfeeding and blinding. With this in mind we should wait until we have done the tests according to your new requirements before ordering 1200 meshes.”
“At start-up (2013, 3 years after supplying the units) we faced some blinding issue. This was made worse because the machines were fitted with the old style MS sieve frames where the ball pockets are 12” x 12”
“All we were doing by replacing the top deck mesh to 0.500 mm was to go back to the mesh specification that we were using from commissioning in 2013 which resulted in blinding and a low feed rate…”
“Also, based on either a 0.475 mm or a 0.500 mm top deck mesh we were still losing the product between 0.170 mm and 0.118 mm because of Rotex’s recommendation that the bottom deck mesh be changed to try and control the blinding on the bottom deck (and therefore undersize material in the product). I later changed the order to increase the number of 0.500 mm meshes to 200 (from 120) and decrease the 475 micron meshes to 280 (from 360). I suggested that we might mix the top deck meshes to try and increase output but keep the oversize material in the product to an acceptable level.”
“We did change the top deck mesh to 0.438 mm in May 2014, but we changed back to 0.478 and 0.500 mm top deck meshes in September 2015 when the replacement meshes had arrived and following Neil Smith’s recommendation that we do so. As can be seen from the production reports, this has not resulted in an increase in production.”
“A. …I would say around August - it was August 21. I cannot remember for sure which one - the exact date we fitted the 500 microns. Q. But you didn’t abandon the 0% oversize specification because that was still a requirement of your customers, wasn’t it? A. It is not actually requirement of our customers. Our customer doesn’t have this requirement. This is what I simply told Mr Neil Smith in my e-mail 2014. But it is not a customer – Q. Why would you tell him that? Why would you have told Mr Smith that if it wasn’t true? A. I would say that I don’t have - I didn’t want to explain a lot of data with him or share internal - the content. So I would just make my short, this is more suitable for our customers. Q. Mr Turk, I’m going to suggest to you that you did not abandon the 0% specification and you did not refer [sic] to 500 microns. Do you accept that? A. No. We did refer [sic] to 400/500 microns [overspeaking] back to 500 microns. Q. Mr Turk, even in your own witness statement you said you went back to 500 and 475 microns. Had you forgotten that? A. No. We - I refer to Mr Neil e-mail where he said that we can check the 500 micron and 475 to maintain a 0% specification, but after that we used up our 425 micron and we went straight to 500 microns completely.” 500 microns completely.”
“The input materials will be 0-3 mm silica sand, our desired output is 0-500 microns (with 0% above 500 µm) ….”
“…the feed isn’t stable but I believe that it will give an idea of the input.”
“…please notice the big changes of the input materials through the year.”
“2. That paragraph [4.4.8] is based on my 50 years’ experience of running a sand plant. The variations described in paragraph 4.4.8 of my report are in relation to the particle size distribution of mined sand. Variation of the mined sand is a result of the depth rather than moving across the mine. As you go down the mine you will encounter sections that contain more fine or more oversize material for example. Therefore, once the sand has been mined it is mixed together. 3. To assist the Court, I give the example of doing a particle size distribution analysis of this mixed mined sand on two days. 4. On Day 1 the analysis shows the coarse and mid-size material (for example on the 500 and 355 sieve) 10% material. If one day 2 that same analysis shows that the material on that sieve has reduced to 7% or increased from 10 to 13% on that sieve it would not be a surprise and not cause any concern. Anything more than that would cause concern and further investigation into the mine and where the sand was being taken from. 5. For fine material (for example the 106 sieve), I would only expect to see a variation of plus or -1% on a day 1 and day 2 of the mixed mine sand. 6. These are variations that I would expect to see in the mixed mine sand. As stated in the last two sentences of paragraph 4.4.8 of my Report of24 November 2017 , I would not expect these variations to reach the feed to the screeners on a typical sand processing plant by an experienced industrial sand producer. The processing of the sand from mixing it to feeding the screeners, as described in my report, is used to ensure what is being fed to the screeners is consistent (with any negligible variation in particle size distribution) which in turn allows for a consistent feed rate and output from the screening machines.”
“2.1.5.1. It is industry wide best practice to run mined sand through a washing plant before running it through dry sand screening machines. I would consider the use of a wash plant to not only be best practice but a necessity in order to achieve consistent feed and consistent performance from dry sand screening machines. I would expect a modern industrial sand producer or their consultant to understand that and not attempt to avoid this industrywide practice by not having a wash plant. 2.1.5.2 A washing plant helps to reduce fines, cleans clay, silt and colloid size particles from the sand, mitigates excess trace minerals (such as iron oxide), shapes sand grains by knocking off rough edges, ensures the product entering the screening machines is consistent, and, because it is used with a dryer, controls moisture. Over-all, a washing and drying plant are an essential part of the process for preparing and controlling quality and consistency of the sand to be screened. 2.1.5.3 In 50 years of working in the sand processing industry I have never heard of anyone going directly from the mine to the dry screens without utilising a wash plant and dryer to ensure a consistent screenable feed.”
“These are relatively narrow issues and I can see little prejudice to Rotex if they were to be taken into account. I will, of course, give Rotex an opportunity to make further submissions on these points following the circulation of this judgment in draft should it wish to do so.”
“Aldrees wanted the plant to run at full production as quickly as possible after wet commissioning and after the plant had been optimised for production (which would have been two or three months maximum, with 70-80% optimisation happening in the first month).”
“Last 10% upon satisfactory testing and commissioning.”
“At sight [sic] after testing and commissioning.”