“Heat soaked thermally toughened soda lime silicate safety glass has a safer breakage behaviour when compared with annealed glass. It also has a known level of residual risk of spontaneous breakage arising from the possible presence of critical nickel sulphide (NiS) inclusions in the thermally toughened soda lime silicate glass. Note 1 This case deals with extremely large quantities of glass. These quantities are dealt with on a statistical basis. Therefore it is impossible to select a quantity of heat soaked thermally toughened soda lime silicate safety glass, for a building, and claim that “no break” by NiS inclusion can occur. The breakage of heat soaked thermally toughened soda lime silicate safety glass caused by other influences is excluded.”
“risk of spontaneous breakage of heat soaked thermally toughened soda lime silicate safety glass, on a statistical basis, due to the presence of critical nickel sulphide inclusions, is no more than one breakage per 400 tonnes of heat soaked thermally toughened soda lime silicate safety glass.”
“By specifying a requirement for failure rates for the process for large volumes of heat-soaked toughened glass, an onus is put on the heat-soaker to know the performance of the oven and to have the equipment duly calibrated. Thus a specifier may indicate a requirement for the heat-soaking regime to be designed with an objective of achieving a residual risk of 1 failure per 100 tonnes or 400 tonnes of glass as a statistical average over large volumes of hear-soaking. However, higher or lower rates of failure may still occur on smaller batches associated with individual projects.”; ii) In 2010, in a draft of a report to advise the Claimants on the breakages they were experiencing, Dr Wolmuth wrote: “In practice, in my experience, most projects that use toughened glass have no nickel sulphide breakages reported despite the project’s glass volumes suggesting that some might be expected. However, a few projects have more failures proven than might be expected. I attribute this experience to the small amount of contamination required to create a large number of Inclusions. This results in average projects being rare. I consider the statistic of 1 in 400 tonnes as being similar to the typical family being quoted as having 2.4 children. The varying incident of nickel sulphide Inclusion breakages on different projects may be explained to some extent by statistical analysis if a Poisson distribution is assumed to predict the probability of a given number of failures.”; And, later in the same report: “When using toughened glass, the risk of nickel sulphide inclusion related failure can not be eliminated despite diligent heat soaking. The risk can also not be quantified on project specific glass volumes - far higher or lower rates of NIS induced failure are likely to occur than large glass volume production statistics suggest.”; And, later in the same report: iii) To similar effect, in December 2010 when advising the Claimants on remedial works, Wintech Ltd wrote: “All toughened glass is susceptible to spontaneous breakage due to nickel sulphide inclusions. All toughened glass is to be heat soaked to reduce the risk of such breakage. The heat soaking regime is to comply with the specified requirements and the associated equipment calibrated and procedures vetted technically prior to the glass for the project being processed. The objective of heat soaking is to limit the residual statistical risk on large glass volumes to 1 in 400 tonnes. However, the residual risk of such breakages on individual projects may be much higher or lower. Thus, a small but real risk remains of a number of breakages after installation despite diligent heat soaking. The incidences of any such breakage are likely to peak in the first five years or so but breakages may occur many years later.”
“No, but this is something that happens a lot. It doesn’t happen to the same extent that it has happened here, perhaps, or in quite the same upfront buildings, but there are quite a lot of buildings where it takes place.”
“If you are talking about glass which has been heat soaked, there aren’t that many that are really bad, to be quite honest. There are some that go over the top a little, but not many, in the UK.”
“Miracle escape for City workers as giant plate glass window falls from 17th floor into busy street City workers had a narrow escape yesterday when a giant plate glass window fell 17 storeys, shattering on the street below. The 15ft high pane just missed office workers enjoying an early lunch and a group of people standing at a bus stop on Threadneedle Street in the heart of London’s financial district. … The building is co-owned by Hammerson Plc, the Bank of Ireland and GE Real Estate, however it is not yet known who is in the frame for the accident.”
“[79] It is not unknown for construction contracts to require the contractor (a) to comply with particular specification and standards and (b) to achieve a particular result. Such a contract, if worded with sufficient clarity, may impose a double obligation upon the contractor. He must as a minimum comply with the relevant specifications and standards. He must also take such further steps as are necessary to ensure that he achieves the specified result. In other words, he must ensure that the finished structure conforms with that which he has warranted. …. [80] The question which I must address is whether the agreement negotiated between [the parties] is a contract of that character.”
“[106] Let me now come to a conclusion. TR paras 3.2.2.2. (2) and 3b.5.1 [which appeared to impose an absolute obligation] are inconsistent with the remainder of the TR and 1101. They are too slender a thread upon which to hang a finding that MTH gave a warranty of 20 years life for the foundations.”
“(1) For C to be liable to A in respect of A’s liability to B which was the subject of a settlement it is not necessary for A to prove on the balance of probabilities that A was or would have been liable to B or that A was or would have been liable for the amount of the settlement. (2) For C to be liable to A in respect of the settlement, A must show that the specified eventuality (in the case of an indemnity given by C to A) or the breach of contract (in the case of a breach of contract between C and A) has caused the loss incurred in satisfying the settlement in the manner set out in the indemnity or as required for causation of damages and that the loss was within the loss covered by the indemnity or the damages were not too remote. (3) Unless the claim is of sufficient strength reasonably to justify a settlement and the amount paid in settlement is reasonable having regard to the strength of the claim, it cannot be shown that the loss has been caused by the relevant eventuality or breach of contract. In assessing the strength of the claim, unless the claim is so weak that no reasonable party would take it sufficiently seriously to negotiate any settlement involving payment, it cannot be said that the loss attributable to a reasonable settlement was not caused by the eventuality or the breach. (4) In general if, when a party is in breach of contract, a claim by a third party is in the reasonable contemplation of the parties as a probable result of the breach, then it will generally also be in the reasonable contemplation of the parties that there might be a reasonable settlement of any such claim by the other party. (5) The test of whether the amount paid in settlement was reasonable is whether the settlement was, in all the circumstances, within the range of settlements which reasonable people in the position of the settling party might have made. Such circumstances will generally include: (a) The strength of the claim; (b) Whether the settlement was the result of legal advice; (c) The uncertainties and expenses of litigation; (d) The benefits of settling the case rather than disputing it. (6) The question of whether a settlement was reasonable is to be assessed at the date of the settlement when necessarily the issues between A and B remained unresolved.” (a) The strength of the claim; (b) Whether the settlement was the result of legal advice; (d) The benefits of settling the case rather than disputing it. (6) The question of whether a settlement was reasonable is to be assessed at the date of the settlement when necessarily the issues between A and B remained unresolved.”
“The lease envisages that the scaffold will cause some disruption to business and that is permitted. So showing disruption is not sufficient – the disruption has to be “material”
“In summary, those cases state that a type or kind of loss is not too remote a consequence of a breach of contract if, at the time of contracting (and on the assumption that the parties actually foresaw the breach in question), it was within the parties’ reasonable contemplation as a not unlikely result of that breach.”
“1. Whether loss is recoverable is determined by reference to the type or kind of loss, and not by its scale or its foreseeability. If a type of loss falls within the principles of Hadley v Baxendale, that type of loss will be recoverable irrespective of scale. On the other hand, even foreseeably large losses are not recoverable if the type of kind of loss was not one for which the Defendant assumed responsibility (paragraph 21). 2. Assumption of responsibility is determined by more than what at the time of contract is reasonably foreseeable (paragraph 31). 3. The critical question is whether the parties can be assumed to have contracted with each other on the basis that the Defendants were assuming responsibility for the type of loss (paragraph 30). The consequences for which the contracting party will be liable are those which the law regards as best giving effect to the express obligations assumed and not extending them so as to impose on the contracting party a liability greater than he could reasonably have thought he was undertaking (paragraph 16).”
“The Employer is desirous of carrying out works in relation to (i) the demolition of the existing building known as the West or Market Building on the 60 Threadneedle Street site, generally down to the existing suspended ground floor slab level, (ii) the demolition of the existing building known as the East Building on the corner of 125 Old Broad Street and Throgmorton Street, down to the lowest ground bearing basement slab, and (iii) the design and construction of approximately 320,000 square feet (net internal area) of office space to Category A finish, comprising the existing tower, which will be reclad, and the design and construction of a new podium linked to the tower, and together also with approximately 6,400 square feet (net internal area) of retail space at ground level finished to shell and core and the provision of basement storage, plant and parking areas (together, the “Project”), for which the Employer has issued to the Contractor the Employer’s Requirements.”
“The Contractor hereby confirms that it is satisfied that: 10.3.1 the Contract Documents, including the Contractor’s Proposals, satisfy the Employer’s Requirements; 10.3.2 the Contractor’s Proposals make full allowance for all matters necessary to complete the specification and design details in accordance with the Employer’s Requirements; 10.3.3 after taking account of any and all design carried out or to be carried out by the Employer’s Design Team and/or the Contractor’s Design Team, and after integrating that design with its own, the Works shall comply with the Employer’s Requirements; 10.3.4 the Employer’s Requirements and the design carried out or to be carried out by the Contractor and/or the Employer’s Design Team and /or the Contractor’s Design Team have been prepared in sufficient detail to allow the Contractors to confirm the Contract Sum and the Contract period.”
“The Contractor shall upon and subject to the Conditions carry out and complete the Works referred to in the Employer's Requirements, the Contractor's Proposals (to which the Contract Sum Analysis is annexed), the Articles of Agreement, these Conditions and the Appendices in accordance with the aforementioned documents and for that purpose shall complete the design for the Works including the selection of any specifications for any kinds and standards of the materials and goods and workmanship to be used in the construction of the Works so far as not described or stated in the Employer's Requirements or Contractor's Proposals…”
“"2.5.1.1 The Contractor shall be fully responsible in all respects for the design of the Works, including all design work prepared before or after the date of this Contract, and shall Adopt any design contained in the Employer's Requirements. 2.5.1.2 The Contractor shall Adopt any design work in relation to Works which may be carried out or which may have been carried out by the Employer's Design Team, the Contractor's Design Team, Domestic Sub-Contractors or any other person employed by the Contractor at the request of the Employer. 2.5.1.3 For the avoidance of doubt, the Contractor shall remain responsible for any design work notwithstanding any comment made by the Professional Team in respect of any design reviewed by the Professional Team and (save as provided by clause 12) no such comment shall entitle the Contractor to an extension of time and/or loss and expense under clauses 25 and 26 of this Contract. Where in the Contractor's opinion the implementation of any annotation by any member of the Professional Team would require a Change to be instructed by the Employer, he shall forthwith notify the Employer prior to commencement of the relevant Works. 2.5.1.4 Without prejudice to the generality of clauses 2.5.1 to 2.5.3, the Contractor, acting as an independent architect, shall he fully responsible and liable to the Employer for all aspects of design and design development, the selection of goods and materials and the satisfaction of performance specifications or any requirement included or specifically referred to in the Contract Documents.”
“Any references to the design which the Contractor has prepared or shall prepare or issue for the Works shall include a reference to any design which the Contractor has caused or shall cause to be prepared or issued by others, and any design relating to or for the Works forming part of the Employer's Requirements. The Contractor shall have the same liability as that set out in clauses 2.5.1.1 to 2.5.1.4 inclusive in respect of any defect or insufficiency in any such design forming part of the Employer's Requirements.”
“8.1.1 All materials and goods shall be of good quality, appropriate for their purpose, to the reasonable satisfaction of the Employer and in accordance with the Contractor's Proposals and/or the Employer's Requirements and any performance specification. 8.1.2 All workmanship shall be carried out in a good, proper and workmanlike manner in accordance with good building practice and to standards, if any, described in the Contractor's Proposals and/or the Employer's Requirements and in any performance specification and in accordance with the Health and Safety Plan and, to the extent that no such standards are described, workmanship shall be of a standard appropriate to the Works and to the reasonable satisfaction of the Employer. 8.1.2A Without prejudice to clauses 8.1.1 and 8.1.2 above, the Works shall be carried out in accordance with all applicable Statutory Requirements and all applicable British and relevant European Standards and Codes of Practice.”
“SERVICE LIFE OF COMPONENTS 1. The service life of components [i.e. actual period of time during which no excessive expenditure is required on operation, maintenance or repair of a component or construction] , as recorded in use — shall be no less than the following: (b) Curtain Walling/Cladding Elements [Work Section H11] Insulating Glass Units :30 years”
“MATERIAL PREFERENCES The Contractor shall be responsible for the final selection of materials, sizes, thicknesses, types, fixing details and associated work, all in accordance with specified standards. The Contractor shall guarantee that the materials, type of construction, dimension, size and thicknesses stated in the working drawings shall satisfy the design intent and performance requirements. Acceptance of the Contractor's proposals by the Architect... shall not relieve the Contractor from responsibility to provide suitable materials, components and assemblies fit for purpose intended by the manufacturer and in compliance with the Design.”
“SUBMITTED PROPOSALS: Following appointment, the Contractor shall be entirely responsible for achieving the completed installation, and any proposal submitted, for all components, and assemblies of the installation, shall achieve or surpass the design and performance criteria stated in this General Specification and the accompanying Trade Specification(s)/Work Section(s). Neither the acceptance of the design proposed by the Contractor, nor the successful testing of any prototype and/or sample and their acceptance by the Architect, shall relieve the Contractor of his responsibility for the adequacy of the work he carries out.”
“DEVELOP THE DESIGN: Use specialist skill and expertise to develop the design from the drawings and specification supplied, taking into account the: (a) Method of fabrication and installation of the products. (b) Selection of suitable materials for the purpose for which they are intended. (c) Design requirements of this General Specification and the Trade Specification(s)/Work Section(s). (d) Integration of the work(s) and/or products(s) with adjacent work by others. (e) Purpose and operation of the works.” (a) Method of fabrication and installation of the products. (b) Selection of suitable materials for the purpose for which they are intended. (c) Design requirements of this General Specification and the Trade Specification(s)/Work Section(s). (d) Integration of the work(s) and/or products(s) with adjacent work by others. (e) Purpose and operation of the works.”
“This specification should be read in conjunction with the Contract Conditions, Preliminaries and A70 specification [i.e. the General Specification]”
“Curtain walling system type: Unitised, structural silicone bonded via carrier frame, drained and vented via mullions Performance criteria to comply with Design/Performance Requirements and Testing subsections. …”
“DESIGN: Complete the detailed design of the curtain walling and associated features shown on the preliminary design drawings to meet the requirements of this specification. Coordinate detailed design with that for all related works.”
“DESIGN LIFE Refer to General Specification A70, clause 33G. The facade shall be designed such that it has a life expectancy of not less than 60 years for the primary elements, which shall include all framing members, 'lashings, copings and similar weathering elements, and seals which cannot be readily inspected without dismantling the facade. All other items, which may be replaced during the life of the building will be regarded as secondary elements. These items will include gaskets and mastic seals. Exposed finished to metal components. All of these items will have a design life of at least 30 years, with the exception of the internal blinds which shall have a design life of 15 years.”
“THERMALLY TOUGHENED GLASS: All thermally toughened, glass shall be heat soak tested to reduce the risk of failure due to nickel sulphide inclusions (NiS). The process known as "double toughening" will not be permitted. Heat soaking shall be carried out to meet the requirements as called for within DIN 18516 Pt.4 at a temperature of 290°C +/- 10°C for a minimum of 8 hours. (or equal approved method). The contractor shall provide the client with documentation to show that the glass has been heat soak tested and the frequency of failures during test. The glass shall conform to BSEN 12150 in the horizontal toughening process...”
“THERMALLY TOUGHENED GLASS Standard: To DIN 18516 Pt 4. Toughening process: horizontal to eliminate tong marks and minimize dimensional inaccuracies. Nickel sulfide inclusions: Heat soak toughened glass to minimise the incidence of failure in situ. Period of heating: 8 hours. Mean glass temperature: 290 +/- 10°C for not less than 8 hours.”
“GENERALLY: Fabricate and install curtain walling in accordance with this specification and the final detailed drawings ...”