“A200 Objectives 201. The standard specifies general principles and guidelines for the structural design of offshore wind turbine structures. 202. The objectives of this standard are to: — provide an internationally acceptable level of safety by defining minimum requirements for structures and structural components (in combination with referenced standards, recommended practices, guidelines, etc.) 19. — serve as a guideline for designers, suppliers, purchasers and regulators 20. — specify procedures and requirements for offshore structures subject to DNV certification 21. — serve as a basis for verification of offshore wind turbine structures for which DNV is contracted to perform the verification.”
“The aim of a project certification of an offshore wind farm is to assure an acceptable quality of the wind farm project. This is achieved by measuring the wind farm project against agreed standards and project specifications and by verifying that the project complies with these standards and specifications. The project certification is carried out by a third-party certification body. The successful project certification results in the issue of a project certification, which allows owners, investors, insurance companies, authorities and other interested parties to place confidence in the project and trust that the project meets the agreed standards and specifications.”
“101 … —design by partial safety factor method with direct simulation of combined load effect of simultaneous load processes.”
“Characteristic load effect 301 The characteristic combined load effect Sk may be established directly from the distribution of the annual maximum combined load effect that results from a structural analysis, which is based on simultaneous application of the two or more load processes. In the case of ULS design, the characteristic combined load effect Sk shall be taken as the 98% quantile in the distribution of the annual maximum combined load effect, i.e. the combined load effect whose return period is 50 years.”
“The design fatigue life for structural components should be based on the specified service life of the structure. If a service life is not specified, 20 years should be used.”
“A grouted connection can be established with or without shear keys as shown in Fig.1. Guidance note: Shear keys can reduce the fatigue strength of the tubular members and of the grout due to the stress concentrations around the keys. If shear keys are used in a grouted connection subjected to bending, they should be placed at the mid level of the connection in order to minimise the influence on the fatigue damage, because the maximum grout stresses from bending will develop at the top and the bottom of the grout member.”
“Experimental verification If no sufficient documentation of the behaviour of a grouted connection is available, experimental verification of the behaviour must be carried out.”
“The Wind Farms are to be designed, constructed and operated to provide the lowest lifetime cost option capable of meeting the full requirements of this Specification. Maximum output with minimum maintenance and maximum availability to generate are the prime requirements of the scheme. … The Works, together with the interfaces detailed in Section 8, shall be designed to withstand the full range of operational and environmental conditions with minimal maintenance. The Works elements shall be designed for a minimum site specific 'design life' of twenty (20) years without major retrofits or refurbishments; all elements shall be designed to operate safely and reliably in the environmental conditions that exist on the site for at least this lifetime.”
“It is stressed that the requirements contained in this section and the environmental conditions given are the MINIMUM requirements of the Employer to be taken into account in the design. It shall be the responsibility of the Contractor to identify any areas where the works need to be designed to any additional or more rigorous requirements or parameters.”
“The design of the foundations shall ensure a lifetime of 20 years in every aspect without planned replacement. The choice of structure, materials, corrosion protection system operation and inspection programme shall be made accordingly.”
“The design of the structures addressed by this Design Basis shall ensure a lifetime of 20 years in every aspect without planned replacement. The choice of structure, materials, corrosion protection system operation and inspection programme shall be made accordingly.”
“All parts of the Works, except wear parts and consumables shall be designed for a minimum service life 20 years.”
“The Contractor shall appoint an accredited Certifying Authority (e.g. DNV – the Norwegian Veritas or GL – Germanischer Lloyd) to independently evaluate the adequacy of his foundation design.”
“The grouted joint between pile and transition piece has an effective length of 1.5*D, i.e. 6.45m. The thickness of the grout is 75 mm. This allows for some adjustment of the inclination of the transition piece if necessary. No shear keys are included as the connection easily can transfer the axial force through friction between steel and grout.”
“The Claimant’s design of the foundations and/or grouted connections: (i) in breach of clause 8.1(x), was not fit for purpose; and (ii) in breach of clauses 8.1 (viii) and 8.1 (xv), was not wholly in accordance with the requirements of the Contract in that the Claimant was in breach of Clause 3.2.2.2 of the Employer’s Requirements. 2. That the Problem (as referred to in the Grouted Connection Agreement) is therefore a defect and a Defect within the meaning of the Contact and a matter which has arisen as a consequence of a breach of contract by the Claimant. 3. That the slippage of the transition pieces due to a lack of axial strength is therefore a defect and a Defect within the meaning of the Contract and a matter which has arisen as a consequence of a breach of contract by the Claimant.”
“Sometimes, again, a contractor will expressly undertake to carry out work which will perform a certain duty or function in conformity with plans and specifications, and it turns out that the work constructed in accordance with the plans and specifications will not perform that duty or function. It would appear that generally the express obligation to construct a work capable of carrying out the duty in question overrides the obligation to comply with the plans and specifications, and the contractor will be liable for the failure of the work notwithstanding that it is carried out in accordance with the plans and specification.”
“The general rule is that defects caused by an owner’s specification are not the responsibility of the contractor, unless the contractor expressly guarantees that the construction would be fit for a specific purpose, or a warranty can be implied by the owner’s actual reliance on the contractor’s skill and judgment.”
“There is no dispute that the principles on which a contract (or any other instrument or utterance) should be interpreted are those summarised by the House of Lords in Investors Compensation Scheme Ltd v West Bromwich Building Society[1998] 1 WLR 896 , 912-913. They are well known and need not be repeated. It is agreed that the question is what a reasonable person having all the background knowledge which would have been available to the parties would have understood them to be using the language in the contract to mean. The House emphasised that “we do not easily accept that people have made linguistic mistakes, particularly in formal documents ...” but said that in some cases the context and background drove a court to the conclusion that “something must have gone wrong with the language”
“In complex documents of the kind in issue there are bound to be ambiguities, infelicities and inconsistencies. An over-literal interpretation of one provision without regard to the whole may distort or frustrate the commercial purpose.”
“those standards, practices, methods and procedures conforming to all Legal Requirements to be performed with the exercise of skill, diligence, prudence and foresight that can ordinarily and reasonably be expected from a fully skilled contractor who is engaged in a similar type of undertaking or task in similar circumstances in a manner consistent with recognised international standards.”