“F. In circumstances in which the issues of clean up and remediation of the Bodo Creek (as defined in accordance with paragraph 1 below) are the subject of an independent mediation led by the former Dutch Ambassador to Nigeria, the Claimants’ Clean Up Claims as defined in paragraph 16 below shall be stayed and shall be struck out if not restored in accordance with paragraph 16. G. The parties enter into and will implement this Agreement in a spirit of cooperation and good faith in the expectation that it will reduce the work that is required for the trial set down for May 2015 (the “trial”) and, if possible, facilitate an early resolution of those Claims. This Agreement shall be interpreted and enforced so as to ensure that the Parties abide by the intentions and objectives, set out herein, upon which this Agreement is based.”
“Claim for injunctive relief or damages in lieu of clean up and remediation 16. The Claimants shall not pursue their claims in relation to clean up and remediation of the Bodo Creek and in particular their claims for injunctive relief or damages in lieu of the same (the “Clean Up Claims”) and the Clean Up Claims shall be stayed until further order and shall be struck out automatically at 4:00pm on the date two calendar years from the date of this Agreement (the “Strike Out Date”). This Agreement is subject to the Claimants being at liberty to apply to the Court to restore the Clean Up Claims for trial by 4:00pm on the date seven days prior to the Strike Out Date. 17. Save for paragraph 16 above and this paragraph 17 the Clean Up Claims shall not be subject to this Agreement.”
“That part of the New Bodo Community Claim relating to clean up and remediation (namely paragraphs 34 to 39 and 65 to 67 of the re-amended Particulars of Claim dated10 July 2014 and paragraphs 21 to 27 and the first three lines of paragraph 65(1) of the Schedule of Loss dated14 February 2014 in the New Bodo Community Claim) will be stayed until further order and shall be struck out automatically at 4:00pm on the date two calendar years from the date of the Narrowing Agreement (the “Strike Out Date”); the Claimants being at liberty to apply to the Court to restore for trial those parts of the New Bodo Community Claim that are pleaded in those paragraphs, any such an application to be issued and served by 4:00pm on the date seven days prior to the Strike Out Date.” (Emphasis supplied)
“1. BMP comprising of Working Groups (including a technical Working Committee) a Steering Committee and a Plenary (general assembly/overall decision making body), will continue to cover all relevant aspects and activities related to the mediation. The Plenary reviews and endorses the proposals by the Working Groups, the overall work plan and approves the Project Director for the clean-up, remediation and restoration works. 2. The clean-up, remediation and restoration of the Identified Areas in BODO will be carried out in accordance with Nigerian law, by reputable contractors with proven international track record and experience with large scale clean-up, remediation and restoration works in a complex environment approved by the BMP Plenary… 4. SPDC will be responsible for the cost of clean-up, remediation and restoration of the Identified Areas under consideration, including the related bidding and contracting processes which shall be in accordance with the Joint Operating Agreement of SPDC, based on the recommendations of the Technical Working Committee and taking into account the applicable approval procedures of the relevant Nigerian authorities, including the National Petroleum Investment Management Services (NAPIMS). 5. In order to ensure that the clean-up, remediation and restoration of the Identified Areas is achieved, Bodo will grant and maintain unfettered access to SPDC, the Project Director, the Contractors and all persons performing or related to the performance of the clean-up, remediation and restoration works of the Identified Areas. 6. The day-to-day implementation of the clean-up, remediation and restoration work plan for the Identified Areas in BODO will be guided and supervised by the Project Director…”
“As I explained to you in December when I told you about the settlement proposal, the clean-up part of your claim has been ‘stayed’ in the High Court in London. What this means is that this part of the claim has not been concluded but instead has been put on hold for a period of 2 years from October 2014. That should mean that if clean-up does not commence before October 2016, your community could instruct us to take the matter back before the British Judge. When the Dutch Ambassador to Nigeria began lobbying Shell on your behalf we felt that it would be a good idea to give that initiative an opportunity to succeed as it has a good chance of working. We understand that international contractors have been appointed. It is therefore important that the process is given a chance to succeed before we consider intervening. If we find that the clean-up is not being done to a sufficient standard we will speak with you and if the Community instructs us to we will return to court to try to force Shell to clean-up to an international standard. However, until we allow that clean-up to start we cannot assess it to see whether it is being done to an international standard so it is extremely important that the clean-up is allowed to start. I would also like to stress that there is no pot of money available for clean-up that could be shared instead of being used for clean-up. If the clean-up of the Bodo creek is prevented from going ahead then Shell can simply walk away, the British courts would very likely decide not to get involved and the Bodo creek will not be cleaned. There is no alternative to clean-up. It is therefore imperative that the clean-up is allowed to go ahead as the Bodo creeks are your and your families’ future livelihood. The option to return to court is a last resort and this option will not be available to you if you do not allow the clean-up to start. I appeal to you to allow the clean-up to commence and then we can assess the situation after it has started early next year.” (Emphasis supplied)
“It is important to put on record that Leigh Day & Co has no mandate or any new brief to act or represent Bodo community in any capacity, as such should not be copied to any letter concerning Bodo people as we are still asking the law firm to give account of all its actions and inactions to Bodo people as regard all funds collected on our behalf.”
“It is no longer the role of the court simply to provide a level playing-field and to referee whatever game the parties choose to play upon it. The court is concerned to ensure that judicial and court resources are appropriately and proportionately used in accordance with the requirements of justice.”
“Are there really genuine issues which require to be resolved or is it the case, on the other hand, that this litigation when viewed as a whole, and in its proper context, is such as to bring the administration of justice into disrepute? Is there really any legitimate or tangible advantage to be gained? …I have an obligation to ensure that the court's process is being used compatibly with the overriding objective. The court is today required to be more proactive in such matters, especially when dealing with a number of people who cannot afford legal advice to protect their best interests.”