“A claimant may use the Part 8 procedure where – a) he seeks the court’s decision on a question which is unlikely to involve a substantial dispute of fact.”
“…calculation in the Molloy Decision is contrary to that required by the Contract and/or VOP3 in the respects set out…..above and, as a consequence of the final determination of these matters of contractual interpretation, the Molloy Decision should not be enforced”. a) he seeks the court’s decision on a question which is unlikely to involve a substantial dispute of fact.”
“The Secondary Options Clauses included in this Contract are:….Option N:Price Adjustment for inflation, clauses N1.1, N2.1, N3.3, N3.1 and N4.1, as adjusted by Schedule 6.”
“1. The assessment interval is monthly. 2. The period within which payment is made is four weeks. 3. The proportions used to calculate the Price Adjustment Factor are as defined in Schedule 6.”
“4.3 The Contract data required for option N is as follows: • Until such time as the Parties agree a mechanism to adjust prices in line with actual cost fluctuation via. open book accounting, the proportions used to calculate the Price Adjustment Factor are: For the Highway Service as defined in Schedule 2: the following indices prepared by the Department of Trade and Industry and published as the Monthly Bulletin of Construction Indices (Civil Engineering Works) 1990, namely: a) the Index of the Cost of Labour in Civil Engineering Construction b) the Index of the Cost of Providing and Maintaining Construction Plant and Equipment. c) The Indices of Construction Materials Prices. Shall be used in the proportions listed in the table below Construction Indices Proportion Labour Plant Aggregates Cements Coated Macadam and Bituminous Products DERV Fuel 0.35 0.18 0.12 0.1 0.1 0.15 1.00 For all Works other than the Highway Service, the Retail Prices Index (RPI) prepared by the Office for National Statistics shall apply. • The base date for indices is March 2003 with the date of assessment being1st April 2004 and every anniversary thereof.”
“An annual uplift in rates is applied on the 1st April annually as detailed in paragraph 43 of Schedule 6 of the Service Delivery Agreement. Para.3 of Schedule 5 of the contract specifically applies NEC Option N: Price adjustment for inflation. It was agreed that the NEC – Option N – Para.N4.1, does apply to this contract and it was therefore agreed that each year an average monthly ‘Baxter’ index for the previous 12 months would be added to the January Baxter index for the forthcoming year for Highways works and similarly an RPI average on the remainder.”
“…each year an average monthly ‘Baxter’ index for the previous 12 months would be added to the January Baxter index for the forthcoming year for Highways works and similarly an RPI average on the remainder”
“Amey has brought this claim to challenge the enforceability of the Molloy Decision.”
“…a sum due to Amey of£37,794.624 (including interest). If the effect of the erroneous compounding of the VOP3 calculation is removed, then Amey’s calculation would be£2,828,860 including interest.”
“My decisions on the remedies sought: 1. Remedy a – I decide that the 2005 Joint Statement is a legally binding contractual agreement to vary the terms of the 2003 Service Delivery Agreement, that all parts of the 2005 Joint Statement are binding on both parties and that VOP 3 amended in writing the terms of NEC Option N which formed part of the 2003 Service Delivery Agreement. 2. Remedy b – I decide that [HDC] is not entitled to disregard VOP3. ….. 7. Remedy g – I decide that [HDC] is not entitled to deduct, withhold or counterclaim any sums against Amey as regards any matter decided herein.”
“Amey contends that no such sums should be deducted, withheld or counterclaimed from Amey as [HDC] is not entitled to disregard VOP3, which applies to every uplift for the full ten year duration of the 2003 Service Delivery Agreement.”
“72. ..... For now, I find that the Joint Statement substituted VOP 3 for paragraph N4.1 in the SDA. ….. 75. I am of the view, and find, that what was intended was that at the start of each year (which I interpret to mean each calendar year, since there is no explanation of the expression “each year” in VOP 3 or elsewhere in the Joint Statement) an average Baxter increase would be calculated for the previous twelve month period and the amount of the average increase would be added to the Baxter index for the January” 76. Thus, by applying that new index, an adjustment would be calculable as applicable for the Highway services work for the forthcoming year. At the end of that year, a similar calculation would be made of the average Baxter increase during that year and a new index applied, reflecting that increase, from the next January for that forthcoming year. 77. A similar calculation would be made for the RPI increase and that would be applied to all non-highway works. I find that this was the meaning to be given to VOP3.”
“I have been given to understand the financial significance of the issues that I am required to address, although consideration and determination of financial matters is not within my jurisdiction. As a result of that understanding, I have come to the conclusion that it is appropriate to give full details of the analyses I have made and detailed explanations of the conclusions I have arrived at.”
“His decision shall be enforceable and binding upon the Parties as a matter of contractual obligation unless and until finally determined by the Courts in accordance with paragraph 5 or by agreement of the Parties.”
“…the parties have failed to reach agreement on how to calculate the VOP3 Index which should apply to the sums due under the Contract in accordance with [the Entwistle Decision]. Therefore the Parties now refer this dispute back to adjudication so that the quantum of the sums owed to Amey on account of the VOP 3 Index, as interpreted in [the Entwistle Decision] can be determined”
“The dispute concerns how price inflation should be calculated using the VOP3 index”
“Having considered the jurisdictional points raised, I concluded that I did have jurisdiction. I advised the parties of this in my e mail timed at 12:40hrs on2nd February 2015 :…..my view is that such a dispute regarding how the VOP3 Index should be calculated is something which can be referred to adjudication…..it appears to me that what I am asked to decide is [Amey’s] financial entitlement based on its interpretation of how the VOP3 Index should be calculated and which it says is in accordance with Mr Entwistle’s Decision. My view is that that is something which I have jurisdiction to decide.”
“…findings in relation to the issues which were identified were to be decided by [Mr Entwistle] and, subject to them forming the basis of his award (in line with Hyder) they would be binding on the parties.”
“More than one adjudication is permissible, provided a second adjudicator is not asked to decide again that which the first adjudicator has already decided.”