“9. Although some may find rather distasteful the prospect of a successful litigant’s pursuing proceedings for contempt against a witness who gave evidence against him, that is not a matter that can properly influence the court’s decision…Nonetheless, because the proceedings are of a public nature “the court from which permission is sought will be concerned to see that the case is one in which the public interest requires the committal proceedings to be brought” (per Sir Richard Scott V.-C.) in Malgar Ltd v R.E. Leach (Engineering) Ltd[2000] FSR 393 at page 396. … 12. In Malgar, Sir Richard Scott declined to give permission for proceedings to be instituted against the alleged contemnors because the falsity of the statements in question could not be clearly established without trespassing on the issues in the trial and because in any event the statements themselves had not been persisted in to the point at which they were likely to affect the outcome of the proceedings. … 16. Whenever the court is asked by a private litigant for permission to bring proceedings for contempt based on false statements allegedly made in a witness statement it should remind itself that the proceedings are public in nature and that ultimately the only question is whether it is in the public interest for such proceedings to be brought. However, when answering that question there are many factors that the court will need to consider. Among the foremost are the strength of the evidence tending to show not only that the statement in question was false but that it was known at the time to be false, the circumstances in which it was made, its significance having regard to the nature of the proceedings in which it was made, such evidence as there may be of the maker’s state of mind, including his understanding of the likely effect of the statement and the use to which it was actually put in the proceedings. Factors such as these are likely to indicate whether the alleged contempt, if proved, is of sufficient gravity for there to be a public interest in taking proceedings in relation to it. In addition, the court will also wish to have regard to whether the proceedings would be likely to justify the resources that would have to be devoted to them. … 19. In some cases, of which this is an example, it may be possible to deal with an application of this kind at a much earlier stage, especially if the alleged contempt relates to a statement made for a limited purpose which has passed and has no continuing relevance to the proceedings. Although we did not hear argument on this point, I think that in general a party who considers that a witness may have committed a contempt of this kind should warn him of that fact at the earliest opportunity (as the appellant did in this case) and that a failure to do so is a matter that the court may take into account if and when it is asked to give permission for proceedings to be brought. However, it is important not to impose any improper pressure on a witness who may later be called to give oral evidence. In particular, if the alleged contemnor is to be called as a witness, an application under rule 32.24 should not be made, and if made should not be entertained by the court, until he has finished giving his evidence. 20. A court dealing with an application of this kind must, of course, give reasons for its decision, but I need hardly emphasise that if the judge decides that permission should be granted he should be careful when doing so to avoid prejudicing the outcome of the substantive proceedings. At the stage of the application for permission the court is not concerned with the substance of the complaint; it is concerned only to satisfy itself that, if established, it is one that the public interest requires should be pursued. If, as in the present case, some aspects of the complaint have been admitted, the judge is free to refer to them, but it will usually be wise to refrain from saying more about the merits of the complaint than is necessary. … 23 The judge’s conclusion that proceedings for contempt in this case would be unlikely to promote the integrity of the legal process or respect for it in the future is one which I find difficult to accept. It is true that only prominent examples of the kind that are widely reported in the press can be expected to make an impression on the public at large, but that is to ignore the fact that the pursuit of contempt proceedings in ordinary cases may have a significant effect by drawing the attention of the legal profession, and through it that of potential witnesses, to the dangers of making false statements. If the courts are seen to treat serious examples of false evidence as of little importance, they run the risk of encouraging witnesses to regard the statement of truth as a mere formality. That is not a matter which the judge appears to have taken into consideration. In my view the prosecution of proceedings for contempt in the present case would be likely to have a salutary effect in bringing home to those who are involved in claims of this kind, of which there are many, the importance of honesty in making witness statements and the significance of the statement of truth.”
“79 The critical question, in this and every case, is whether or not it is in the public interest that an application to commit should be made. That is not an issue of fact but a question of judgment. The discretion to permit an application to commit should be approached with considerable caution. It is not in the public interest that applications to commit should become a regular feature in cases where at or shortly before trial it appears that statements of fact in pleadings supported by statements of truth may have been untrue. Whether an application for committal is in the public interest will depend on a number of considerations many of which have been considered in the authorities including the significance of the statement in the context of the case, the clarity of its meaning, the strength of the contention that the maker of it knew it to be untrue, the status of the maker, the seriousness of the consequences of it having been made, the length of time over which, and the circumstances in which, it was maintained, and any explanation as to why it was made.”
“The Feasibility Study Agreement was varied by written agreement between the parties in respect of additional services to be provided by the Claimant to the Defendant the consequential increase in the costs to the Defendant of the Claimant performing its duties under the feasibility Study Agreement. Agreed ‘Variation Orders’ included those dated5 May 2010 ;25 march 2011 ;15 April 2011 ;10 July 2011 ;29 September 2011 ;11 November 2011 ;2 December 2011 ;17 January 2012 ;12 March 2012 ;12 May 2012 ;15 May 2012 ;26 May 2012 ;8 July 2012 ;31 July 2012 ;15 October 2012 ;30 October 2012 ; and18 July 2013 .”
“(b) Save as aforesaid, the defendant has no record of any ‘Variation Orders’ as alleged and in the premises no admissions are made. Through its letters to the claimant of27 September 2013 ,23 October 2013 and the letter of Farrer & Co to the claimant’s solicitor dated28 January 2014 , the defendant has requested copies of any such ‘Variation Orders’ but the claimant has failed to provide them.”
“(a) Either • Provide a copy of the email or letter under cover of which your client claims that the purported VO was originally sent to our client; or • If the purported VO was not sent under cover of an email or letter, please set out in full circumstances in which it was first delivered to our client, including whom when and by whom it was delivered; (b) Provide copies of any contemporaneous documents which were sent at or around the same time as the purported VO by way of explanation of the need for the proposed variation; (c) Either • Provide by return a copy of the email or letter by which each purported VO apparently signed by Mr Laing was returned to your client; or • If the signed copy of the purported VO was not sent under cover of an email or letter, please set out in full the circumstances in which it was delivered to your client, including how, when and by whom it was delivered; (d) Confirm that you client has preserved in their original condition the original hard and electronic copies of the purported VO’s together with any [of] the originals of any covering correspondence; and (e) Confirm that your client will make available for inspection and forensic analysis both hard and electronic copies of the purported “Variation Orders”, all associated contemporaneous correspondence and all associated metadata. In the meantime, our client does not admit the authenticity of the purported of the Variation Orders and reserves the right to require your client to prove that at any hearing before an expert or at trial…”
“Since receipt of the letter we have had the opportunity to speak to Glenn Laing who confirms that: (1) He agreed to each of the 17 Variation Orders at various points between January 2010 and December 2012; and (2) He signed each of the 17 Variation Orders.”
“4…As is set out above, premise A of the Amending Deed recorded that the FSA had been amended by Variation Orders V001 to V017; the defendant has therefore accepted that Variation Orders V001 to V017 were agreed between the parties. It is averred that its non-admission at paragraph 4 of the defence and counterclaim on this point should be struck out and/or subject to summary judgment in the claimant’s favour.” (d) At paragraph 9(a) GBMMEC aver that the original figure of£1,924,023 excluded any provision for contingencies. “The parties agreed under the Variation Orders that the overall cost of the work being undertaken and organised by the claimant increased from this initial estimate.” (e) At paragraph 9(b) there is this important assertion: “(b) By the time the 17th Variation Order was signed on behalf of the defendant on31 October 2012 , the agreed contract price, as recorded in the 17th Variation Order, had increased to£10,811,352 . The three Variation Orders dated18 July 2013 , for which the claimant does not have copies signed on behalf of the defendant, took the total contract price to£11,154,627 .”
“The original signed contract was job 0391 for£1,924,023 but there was no contingency. The first variation was to add some contingency and other variations followed, so that the contract (£1,924,023 ) plus variations (£5,908,482 ) adds up to£7,832,505 . However the cost of 0391 was£667,600 and my forecast for 0412 is£6,875,969 =£7,552,505 so it could be said that there was too much contingency (about£280,000 ) in the original estimates. Similarly, I have overestimated the costs of 0432, 045 and 0460, however an adjustment downwards (and that is unusual) may be made to the completion of the work. There is a large amount of money of contingency still enclosed within the variations as ‘requested’, about£1,600,000 which was not used out of£1,843,500 which was included in the estimate. Contingency must appear in any quotation, and I have done so but it makes my ‘forecasting’ look good.”
“I do not think I attached any particular significance to the date of signature since the Variation Orders did not reflect the quantitative and qualitative changes in the scope of the claimant’s work.”