“Save to the extent that the Purchaser has not complied with Clause 3 and such failure has affected the ability of the Contractor to comply with its obligations under the Contract, the Contractor shall, with due diligence, carry out and complete the Engineering Works in accordance with the Contract and the Regulations and to the reasonable satisfaction of the Project Director and provide all labour, materials, equipment, Contractor’s equipment, transport to and from and in and about the Site and all other things, whether of a temporary or permanent nature, required for the performance of the Engineering Works insofar as the necessity for providing the same is specified in or is reasonably to be inferred from the Contract.”
“despite previous warning by the Purchaser in writing the Contractor is failing to proceed with the Engineering Works with due diligence or is otherwise persistently in material breach of its obligations under the Contract;”
“what is due diligence and expedition depends, of course, on the object which is sought to be achieved. If one is obliged to achieve a certain object within twelve weeks, it may be necessary to exercise much more speed than if your only obligation is to produce it in twenty-four weeks or indeed in four years. The same applies to diligence. You cannot have diligence in the abstract. It must be related to the objective.”
“My approach to the proper construction and application of the clause would be this. Although the contractor must proceed both regularly and diligently with the works, and although each word imports into that obligation certain discrete concepts which would not otherwise inform it, there is a measure of overlap between them and it is thus unhelpful to seek to define two quite separate and distinct obligations. What particularly is supplied by the word 'regularly' is not least a requirement to attend for work on a regular daily basis with sufficient in the way of men, materials and plant to have the physical capacity to progress the works substantially in accordance with the contractual obligations. What in particular the word 'diligently' contributes to the concept is the need to apply that physical capacity industriously and efficiently towards that same end. Taken together the obligation upon the contractor is essentially to proceed continuously, industriously and efficiently with appropriate physical resources so as to progress the works steadily towards completion substantially in accordance with the contractual requirements as to time, sequence and quality of work. Beyond that I think it impossible to give useful guidance. These are after all plain English words and in reality the failure of which clause 25(1)(b) speaks is, like the elephant, far easier to recognise than to describe.”
“The employer impliedly agrees to do all that is necessary on his part to bring about completion of the contract. For example, he must give possession of the site within a reasonable time. He may be obliged to obtain planning permission or building regulation consent in sufficient time to enable the contractor to proceed without delay … .”
“Where there is a comprehensive written contract such as the Standard Form of Building Contract there may be very little room for the implication of any terms, for if the parties have dealt expressly with a matter in the contract, no term dealing with the same matter can be implied.”
“Before you lay people off from our Project, please talk to us.”
“Sabic discussions and negotiations with Cape since June have created a situation where Cape refuses to work with Simon Carves to complete the project. P. Booth appears to understand the magnitude of the problem Sabic has created with Cape and to a degree all of [SCL’s] site subcontractors with unauthorised communication. He also appreciates the fact Cape has been disingenuous in their description of contractual disputes they have with SC. Recommended Path Forward 1. SC will send Cape a detailed analysis of all disputed amounts. 2. Letter should be sent Cape advising their communications and taking action at direction from Sabic on the scope of work under contract to SC places them in breach of contract. 3. Use this mistake by Sabic as a key component in recovery strategy.”
“the only credible option for recovery of the£4.7 million is Sabic. Any attempts to manufacture claims against subcontractors or withhold payments for questionable deductions will result in contractors demanning.”
““[SCL] will be aware that under terms of the contact, [SCL] agreed to secure an [EID] of5th December 2008 in accordance with the Completions Plan, which was appended to the Supplemental Settlement and Schedule Agreement dated2nd July 2008 (“SSA2”). [SCL] will also be aware that under clause 2.1.1 of the Contract [SCL] shall, with due diligence, carry out and complete the Engineering Works in accordance with the Contract. SABIC are concerned at [SCL’s] lack of due diligence in completing the Engineering Works. Examples of the activities causing the delay include the following: i) Hydrotesting In evidence, Mr Teague accepted that the hydrotesting was virtually complete. SABIC no longer relies upon it as an activity that was causing delay by3 October 2008 . It is therefore not necessary to consider it in any further detail. … ii) Loop Testing – these were programmed to be completed by [SCL] on3rd October 2008 , and as of the date of this letter Circa 900 This was in fact an overestimate, the actual number being in the region of 848. Loop tests remain to be done. Again the majority of the Loop tests were finished later than the dates required in the completion plan. iii) Insulation – the insulation works were to be completed by [SCL] on10th October 2008 , as of the date this letter Circa 14,000 linear metres remains to be installed. iv) Systems at MC1– based on the early finish dates in the Completions Plan, 122 Systems should have been achieved MC1, as of the date of this letter only fifteen systems have achieved MC1. v) System Cleaning and Blowing – based on the Completions Plan in SSA2 by25th September 2008 [SCL] should have cleaned and/or blown 29 Systems, however only two systems had been completed. The above list is not exhaustive, and bulk work in the reactor bay, outstanding civil and structural work, the absence of QA documentation a lack of design support, and [SCL’s] ongoing inability to properly manage key subcontractors are all contributing to the ongoing delays for which SABIC hold [SCL] responsible. The resultant effect of the delays being incurred, from the latest estimate that is available, estimates that Ethylene-in will not be achieved until early March 2009, twelve weeks late, in a programme that was anticipated to last 23 weeks. In addition, SABIC has received no assurances from [SCL] that Ethylene-in will be achieved by5th December 2008 or any other date. Clearly, this is a situation which SABIC finds unacceptable and cannot be prepared to tolerate. SABIC must therefore consider the options open to it so as to protect its interests against the failure on the part of [SCL] to comply with its obligations under the contract. There is no doubt that should it wish to do so, SABIC could terminate the Contract immediately in accordance with Clause 27.2.5. This would be on the basis that the financial position of [SCL] has deteriorated to such an extent that the capability of [SCL] adequately to fulfil its obligations under the contract has been placed in jeopardy. This is demonstrated by [SCL’s] inability to resource the works to ensure that Ethylene–in is achieved by5th December 2008 . Notwithstanding the fact that SABIC would be entitled to terminate the contract, its preference would be for [SCL] to remedy its breaches by completing the engineering works with due diligence. Please treat this letter as a warning under clause 27.2.10 of the Contract that SABIC considers that [SCL] are failing to proceed with the Engineering Works with due diligence or is otherwise persistently in material breach of its obligations under the Contract. The delays set out above confirm that [SCL] are failing to proceed with the engineering works with due diligence. In addition, by reference to the delays indentified above, [SCL] is in persistent material breach in not complying with its obligations to, with due diligence, carry out and complete the Engineering Works in accordance with clause 2.1.1 of the contract. [SCL] is therefore given a further seven (7) days from the date of this letter to rectify their failure to proceed with the Engineering Works with due diligence. SABIC also makes it clear that it reserves its rights to enforce the Parent Company Guarantee (PCG) dated13 June 2008 , which it has in place with Punj Lloyd Limited in any manner it considers appropriate. In this connection SABIC would advise you that it has today contacted Punj Lloyd Limited advising them of the contents of this letter. Please also be aware that SABIC’s rights under the Advance Payment Guarantee issued by HSBC bank plc dated24th June 2008 and the Performance Guarantee issued by standard chartered bank on21st July 2008 are reserved in all respects. ”
“Following termination, Ethylene in was not achieved on5 December 2008 . Ethylene was first introduced into the Process Plant for the purposes of commissioning on22 June 2009 , 28.3 weeks after the date agreed in SSA2. … Our client has incurred significant losses as a result of the delay in introducing ethylene into the Process Plant. Following ethylene in, it is accepted that our client had to undertake commissioning works prior to Polyethylene being produced. While SSA2 provided a commissioning period of 3 weeks, our client is prepared to accept that the commissioning period would have taken up to 6 weeks. In calculating its losses, our client will allow a 6 week period for commissioning following ethylene in. … If ethylene in had therefore been achieved on5 December 2008 , it is reasonable to expect that our client would have completed commissioning to have allowed Polyethylene to have been produced by16 January 2009 . Based upon the actual ethylene in date of22 June 2009 commissioning should therefore have been completed to have allowed Polyethylene to have been produced by3 August 2009 . Our client would therefore be able to claim its losses for the period between16 January 2009 (the date when commissioning should have been completed so that Polyethylene should have been produced following ethylene in on5 December 2008 ) and3 August 2009 (the date when commissioning should have been completed and Polyethylene produced following actual ethylene in on22 June 2009 ). This is a period of 28.3 weeks. However, following ethylene in, further defects were discovered which delayed the commissioning of the Process Plant. Commissioning was not completed so that Polyethylene was produced, until16 October 2009 . Based upon the expectation that commissioning should have taken 6 weeks from ethylene in, this is an additional 10.4 week period from3 August 2009 . The extended commissioning period was due to the discovery and rectification of defects in the Engineering Works undertaken by you. However, our client does not seek to recover damages for the full 10.4 weeks. Our client reserves the right to claim additional damages for the full 10.4 week period if it considers it appropriate to do so. Our client does seek to recover damages for the period of delay attributable to the rectification of one major defect during the commissiong period. This was the rectification of the defect to the EVS Structure. Unless or until this defect was rectified, no further commissioning work could be undertaken. The rectification of the defect to the EVS Structure took 6 weeks to complete. If the EVS Structure had no defect, then the commissioning could have been completed and Polyethylene produced 6 weeks earlier than16 October 2009 (on4 September 2009 ). Our client would therefore be able to claim its losses for this additional 6 week period.”
“Cooling Water Pump stopped during flushing of Cooling Water Supply and Return Header. Delivery NRV shut as designed, but resulting pipe work movement damaged a support on the Cooling Water Pipe work system. Commissioning activities suspended. Area made safe and technical team called to investigate. Pump stopped due to concerns about delivery pipe work 363. bellows distortion. Pump ran well for 20 mins.”
“A renunciation of a contract occurs when one party by words or conduct evinces an intention not to perform, or expressly declares that he is or will be unable to perform, his obligations under the contract in some essential respect. The renunciation may occur before or at the time fixed for performance. An absolute refusal by one party to perform his side of the contract will entitle the other party to treat himself as discharged, as will also a clear and unambiguous assertion by one party that he will be unable to perform when the time for performance should arrive. Short of such an express refusal or declaration, however, the test is to ascertain whether the action or actions of the party in default are such as to lead a reasonable person to conclude that he no longer intends to be bound by its provisions. The renunciation is then evidenced by conduct. Also the party in default: “ … may intend in fact to fulfil (the contract) but may be determined to do so only in a manner substantially inconsistent with his obligations,” or may refuse to perform the contract unless the other party complies with certain conditions not required by its terms. In such a case, there is little difficulty in holding that the contract has been renounced. Nevertheless, not every intimation of an intention not to perform or of an inability to perform some part of a contract will amount to a renunciation. Even a deliberate breach, actual or threatened, will not necessarily entitle the innocent party to treat himself as discharged, since it may sometimes be that such a breach can appropriately be sanctioned in damages. If the contract is entire and indivisible, that is to say, if it is expressly or impliedly agreed that the obligation of one party is dependent or conditional upon complete performance by the other, then a refusal to perform or declaration of inability to perform any part of the agreement will normally entitle the party in default to treat himself as discharged from further liability. But in any other case: “It is not a mere refusal or omission of one of the contracting parties to do something which he ought to do, that will justify the other in repudiating the contract; but there must be an absolute refusal to perform his side of the contract.” ”
“We understand that you have entered into a contract dated9th February 2006 with [SCL]. … In accordance with the terms of the contract the contractor is required to issue to [SABIC] a performance guarantee for the sum of GBP13,500,000 … being 10 percentage of the contract price. We, Standard Chartered Bank … give our guarantee and irrevocably undertake to pay any amount or amounts not exceeding in total a maximum of GBP 13,500,000 to you on receipt by us of your first demand in writing under the original signature accompanied by your signed statement certifying that the contractor is in breach of its obligations in the underlying contract and that you have served the required notice pursuant to clause 36.4 of the contract.”
“[SABIC] has agreed to make to [SCL] an advance payment of£14,338,609 … being the payment due up to and including mechanical completion, upon the issue to [SABIC] of an irrevocable on-demand bond in the sum of GBP13,000,000 … being amount equivalent to the advance payment contemplated and subsequent repayments. We, HSBC Bank plc, give our guarantee and irrevocably undertake to pay any amount or amounts no exceeding in total a maximum of GBP 15,000,000 … to you on receipt by us of your first. Demand [sic] in writing accompanied by your written confirmation certifying that [SCL] is in breach of its obligations in the contract.”
“By the beginning of the 19th century it appears to have been taken for granted, without need for any citation of authority, that the contractual promise of a guarantor to guarantee the performance by a debtor of his obligations to a creditor arising out of contract gave rise to an obligation on the part of the guarantor to see to it that the debtor performed his own obligations to the creditor. Statements to this effect are to be found in Wright v. Simpson (1802) 6 Ves.Jun. 714 , 734, perLord Eldon and in In re Lockey (1845) 1 Ph. 509 , 511, perLord Lyndhurst. These are the two cases which are cited as authority for this proposition by Sir Sidney Rowlatt in his authoritative work on Principal and Surety. They can be supplemented by other similar statements, including one in your Lordships' House, which confirm that it was taken for granted that this was the legal nature of the guarantor's obligation arising out of a contract of guarantee: Mactaggart v. Watson (1835) 3 Cl. & F. 525 , 540, perLord Brougham. It is because the obligation of the guarantor is to see to it that the debtor performed his own obligations to the creditor that the guarantor is not entitled to notice from the creditor of the debtor's failure to perform an obligation which is the subject of the guarantee, and that the creditor's cause of action against the guarantor arises at the moment of the debtor's default and the limitation period then starts to run.”
“As a matter of general principle, therefore, in the light of the commercial purpose of such bonds, … I take the view that if there has been a call on a bond which turns out to exceed the true loss sustained, then the party who provided the bond is entitled to recover the overpayment.”
“If the seller defaults in making delivery, the buyer can operate the bond. He does not have to go to far away countries and sue for damages, or go through a long arbitration. He can get the damages at once which are due to him for breach of contract. The bond is given so that, on notice of default being given, the buyer can have his money in hand to meet his claim for damages for the seller’s non-performance of contract. If he receives too much, that can be rectified later at an arbitration.”