"Lidl’s entitlement to liquidated and ascertained damages ("
"[RGC] seeks the appointment of an Adjudicator to confirm that Lidl is not entitled to partial LADs in respect of Sections 1 and 2 of the Works whether as claimed in their letter of12 July 2012 , or otherwise."
"However, it is in fact disputed by [RGC] that full LADs (as described in paragraphs 11.1 and 11.2 above) are payable due, principally, to [RGC's] entitlement to an extension of time, which is the subject of a separate dispute falling outside the scope of this adjudication. Accordingly, the claim for LADs as described in paragraphs 11.1 and 11.2 above is also outside the scope of this adjudication."
"The issue for determination in this Adjudication concerns Lidl’s claim to be entitled to partial and pro-rata liquidated and ascertained damages ("
"A declaration that Lidl is not entitled to pro-rata LADs in respect of Sections 1 and 2 of the Works as claimed in their letter of12 July 2012 , or at all"
"Therefore this reference is limited to a dispute regarding the liquidated damages for the period after a partial possession of Section 1 and Section 2 had taken place."
"The purpose of this Adjudication is to determine whether or not Lidl is entitled to levy the pro-rata damages as claimed (or at all). [RGC] say they are not. In the event that the Adjudicator finds against [RGC], [RGC] would commence a separate adjudication to determine the quantum of such LADs."
"I FIND THAT in the first instance [Lidl] is entitled to recover the sum of£125,000 in respect of LADs in connection with Sections 1 and 2 made up as follows . . ."
"I FIND THAT [Lidl] is entitled to claim a "lesser rate" in respect of LADs under Clause 29.2.1 as on the face of it [Lidl] has complied with the procedure set out under the clause. "
"As regards the declarations sought by RGC I have found as follows: 45.1 Declaration 1 LADs - [Lidl] is entitled to deduct the LADs all as set out in its letter dated12 July 2012 ." 45.2 . . .” In this context, it is to be noted that, at paragraph 27 of the Decision, the adjudicator had stated that Lidl had claimed LADs “totally (sic)£469,850 in respect of sections 1 and 2 all as set out in its letter dated12 July 2012 which was issued following publication of my Decision in the first adjudication involving the parties."
"Although it is important for the referring party to ensure that the referral notice is as clear and detailed as possible, it is important to ensure that, unless there is express agreement otherwise, the referral notice does not seek to enlarge the dispute that was the subject of the notice of adjudication."
". . . where an adjudicator, in court terms, offers an obiter opinion on a point or topic which is not part of the dispute for which he does have jurisdiction, that opinion is not jurisdictionally part of his decision."
“On the severability issue, I conclude, albeit obiter in the result, as follows: (a) The first step must be to ascertain what dispute or disputes has or have been referred to adjudication. One needs to see whether in fact or in effect there is in substance only one dispute or two and what any such dispute comprises. (b) It is open to a party to an adjudication agreement as here to seek to refer more than one dispute or difference to an adjudicator. If there is no objection to that by the other party or if the contract permits it, the adjudicator will have to resolve all referred disputes and differences. If there is objection, the adjudicator can only proceed with resolving more than one dispute or difference if the contract permits him to do so. (c) If the decision properly addresses more than one dispute or difference, a successful jurisdictional challenge on that part of the decision which deals with one such dispute or difference will not undermine the validity and enforceability of that part of the decision which deals with the other(s). (d) The same in logic must apply to the case where there is a non-compliance with the rules of natural justice which only affects the disposal of one dispute or difference. (e) There is a proviso to (c) and (d) above which is that, if the decision as drafted is simply not severable in practice, for instance on the wording, or if the breach of the rules of natural justice is so severe or all pervading that the remainder of the decision is tainted, the decision will not be enforced. (f) In all cases where there is a decision on one dispute or difference, and the adjudicator acts, materially, in excess of jurisdiction or in breach of the rules of natural justice, the decision will not be enforced by the Court.”
"I see no good reason why the substance of the adjudicator's decision should not be enforced albeit that the amended decision relating to the sum of£250,860 plus VAT should be reduced by£21,149 plus VAT which would produce a net sum of£229,711 plus VAT which remains as the figure due at14 January 2012 . Since he did not have jurisdiction to reject or accept items 11 and 12, he had no jurisdiction to produce a decision which adjudicated upon them. It follows that in principle Greencoat was entitled to put forward as at14 January 2012 set-offs in respect of items 11 and 12. Effectively, what the adjudicator did was, doubtless with good intentions, to decide upon to further disputes (items 11 and 12) which were not within his jurisdiction. The court is therefore enforcing the large bulk of the adjudicator's decision; to do so is consistent with the authorities set out in Cantillon Ltd v Urvasco Ltd (2008) 117 Con LR 1."
"These two items were not part of or within the confines of the dispute as it had crystallised as they had not been mentioned before they emerged 22 days into the adjudication process."
"I FIND THAT [Lidl] is entitled to claim a "lesser rate" in respect of LADs under Clause 29.2.1 as on the face of it [Lidl] has complied with the procedure set out under the clause. "
"The purpose of this Adjudication is to determine whether or not Lidl is entitled to levy pro rata damages as claimed (or at all). [RGC] say that they are not. In the event that the Adjudicator finds against [RGC], [RGC] would commence a separate adjudication to determine the quantum of such LADs."
"on the true construction of the Contract, LADs do not accrue following Part Practical Completion of the Works or a Section thereof."