“Water seeping into Sheer’s excavations. 2 Piles missing. 1 Pile having a gap at high level.”
"Berry contends that it is not responsible for any effects of the seepage of water because in its quotation of22 October 2010 it made Sheer responsible for any dewatering that may be required."
“4.066 However, Sheer does not detail the alleged effects on the programme. 4.067 At paragraph 4.1, 4.4, 4.5, 6.1.6 and 6.1.7 of the Response and in the Counterclaim at paragraphs 1, 2.2, and 3.1 Sheer makes further reference to delays to Sheer’s work caused by Berry. 4.068 There is some support of (sic) Sheer’s claims against Berry for delays at Documents 17 and 18 and at Tab 7 of the Response. 4.069 However, [Sheer] has failed to provide any proper analysis of the alleged delays to its works caused by Berry. 4.070 There is no information as to how Berry actually affected the Completion Date of Sheer’s work and not even the simplest attempt at any critical path analysis or even a simple narrative explaining how Berry actually critically affected Sheer’s progress. 4.071 Sheer has not addressed the issue raised by Berry at paragraph 3.4, page 5, that it was working below the water table level and that Berry stated that Secant piling would not prevent seepage and ingress of water and that the Contract made [Sheer] responsible for dewatering. 4.072 Berry has failed to prove to what extent, if any, Sheer caused critical delays to the completion of Sheer’s work. 4.073 Having watched the video with the Response of the flow of water through the piles I note that it was significant at one particular leak. There appears to be no reason why that water could not have been directed to a storage tank from which it could be pumped away without flooding the excavations or developing (sic) Sheer’s work. 4.074 Sheer has failed to proven (sic) that Berry caused any critical delays to the completion of Sheer’s work.”