“As you are aware, it has now been decided that we will ‘run’ with Kier on H5 and we have agreed the ‘technical solution’ for constructing the building. There are still a number of commercial/technical issues to resolve over the course of the next week, but we must be in a position by the 7th November 20003 where we can place a Letter of Intent with them in order to enable them to make as early a start on site as possible. Alan [Talabani] will be leading the negotiations on resolving this in terms of a fixed price, however could you all please assist him in doing this by issuing information ASAP where possible.”
“We would wish to agree that L and AD’s do not exceed 1% of Contract price.”
“Level of LAD’s to remain as ER’s [Employer’s Requirements]. This issue is not negotiable.”
“Have been thinking about Ampleforth … I don’t think the replacement PM is up to the job!!! Have not decided how to play this with Jim Fletcher as yet because I do not want to prolong my involvement with the project—I’ll let you know how it goes.”
“As Kier are not yet in a position to confirm fixed costs for all of the VE items, we [are] not yet in a position to conclude the formal contract documents for H5. We therefore need to issue a revised Letter of Intent as the previous one expired today.”
“FURTHER LETTER OF INTENT REQUIRED IMMEDIATELY.”
“Please respond to these items at your earliest convenience so that the outputs can be incorporated in the Contract documents. If not, they will not form post contract variations as the execution of the Contract Documents should not be delayed further. A draft copy of the Contract documents will be dropped off at your offices this evening. Please forward any comments you may have on these to Alan Talabani at the above address.”
“Thanks for the contract docs which have been the subject of discussions S Phillips/yourself. Their checking, the receipt of warranties and finalising consultants appointments incl the issue of the extra fees they seek for VE work, will all take more time and it is to be noted that the current Letter of intent expired Friday 27th Feb. I will have for you in short timescale a request for further cover to take us to 26th March, the date by which realistically we should have all these outstanding matters resolved. I have again to record disappointment that despite conversations with Allied Irish, with Peter Bryan including letters, and direct contact from our Regional Financial director, no letter in the reqd form has been received re Loan facility being in place for Ampleforth and the building works which relate to the subject Contract. I am having serious problems in appeasing our masters in HQ that our position is secure bearing in mind that various unfulfilled promises via P Bryan and the bank direct, have been given.”
“We are still aiming for signed and executed contracts in place by the end of March. This should then enable AIB to issue formal confirmation of funding.”
“Please can we get all these bits and pieces sorted? It would be especially nice to have a contract.”
“The outstanding contractual issues include:- 1. Warranties in approved wordings not received. 2. Consultant appointment issues not yet resolved. 3. Consultant fee supplements not yet agreed. We regret that we cannot park these matters to post contract signing stage. … Following W Kay’s [a Kier director] meeting with Peter Bryan yesterday, it appears a letter from AI is closer, so progress is being made. Can you arrange to let us have the revised letter of intent by return.”
“Apologies for not getting back to you earlier. I respond to your notes below as follows: 1. Warranties—Agreed, these have not been forwarded to yourselves yet. I have been waiting for a response from AIB which has not come yet. I will issue all warranties during next week (except for the funder one—which requires AIB comments). 2. Consultant appointment /. Fee supplements—I must say that I am a little disappointed that these have not been resolved yet. The consultant appointment details were included in the tender documents that were issued to you back in August last year, and have not really changed since then. Around December last year you told me that some of the designers were not playing ball and asked T&T to have a word with them, which we did, and my understanding was that it had then been resolved. Consultant appointments aside, I was under the impression that Kier were happy that the contract could be executed with the warranties inserted retrospectively. That appears to not be the case now. Whilst it is obviously preferable to have everything in place prior, it is not unheard of to insert warranties at a later date and therefore I do not see this as a reason to hold up the executing of the contract. What is clear is that at the moment, the letter of intent which you are working to has expired and the contracts are not in place. We will therefore issue a revised letter of intent to you early next week. I know I said this last time, but can we please make sure this really is the last one that we have to issue. If there is anything else you need from us to make this happen, please let me know. My understanding re the AIB letter following the meeting between Peter / William is that the Abbey had given the AIB authority to discuss the matter directly with Kier and that you would contact them directly to seek confirmation of funding, assurances etc.”
“I am sorry you appear to have been under the impression that we could fully sign up without warranties seen and agreed. Our rule book prevents this Alan and I cannot think how an alternative resolve could have got into your mind, or who could have put it there. That said therefore we need to agree on these before the contract is concluded—let’s hope that can be before the expiry of the next LoI commitment. Whilst W Kay was given to expect a letter from AI in the sentiment discussed that is not with us yet. The agreement of Appointments with Consultants has been a protracted one and correspondence exchange continues between us. AA and Shires have still some issues to resolve with us, Halcrows too but less so.”
“You will by now have received Jonathan Holt’s letter commenting on a number of issues emerging from the warranty wordings previously received from you. This will require to be agreed. The good news is that the above now remains the only issue to resolve, matters of payment security, dealing with consultants’ applic[ations] for additional fees etc now resolved. A further letter of intent to formalise the current position will therefore be required, and JH is currently working on a revised value. I shall contact you as soon as this figure is known.” 54. On 7th May Mr Talabani gave a response to Kier’s proposed amendments to the warranties, agreeing to some of the proposed amendments but not to others, and wrote to Mr McNeil by email: “As we are nearly there now, can I suggest we just execute the Contract Docs asap rather than re-issue a letter of intent. As we are so close, I would really rather not have to go back to Peter [Bryan] to issue yet another letter.”
“We are exposed at this time [i.e. because the latest letter of intent had expired]. I have asked Jonathan [Holt] to elicit a very quick response to your counter-views on warranties. I agree that executing the docs is desirable, but that would depend on speed of resolution on warranty wordings.”
“Until this matter is resolved we cannot formalise the appointment.”
“The trail remains hot Alan. No imminent sign of this contract being signed so I have to ask again for an extension to the letter of intent to the value advised w/c 03/05. Can you pl advise as quickly as poss.”
“They’re blaming this issue on not sorting the cont docs. [In context, this sentence must mean: They are using this as a reason why they cannot execute the contract documents.] Not on really as I have told them go proceed without and if it has to be paid post contract, we’ll raise as a variation.”
“If the contract docs are within spitting distance, I’d rather push to get them executed rather than issue revised l of i’s etc.”
“Given that the L of I is limited not only by value but also date this does need to be revised. We would given the current level of cost exposure accept an amended L of I extending the date to the end of July 04. Is there any reason now why a L of I for the full contract value (unlimited by time) cannot be issued.”
“I agree to the extended Letter of Intent, but we must endeavour to resolve the outstanding issues below with some urgency.”
“Ampleforth H5—Craig—Meeting with Craig to sort variation costs, then we’ll all get together after I’m back to mop up. Rev’d let of intent issued so don’t worry about cont docs.”
“The only thing holding up executing the contract docs is Shires appointment. What is the point of giving them£5k if they have already told Rob that they want all of it and will not settle for a substantially smaller amount? Have you spoken to them after Rob did last week? In the light of the above, I suggest we issue a letter of intent for the whole value up to the end of the job. Then Shires can go fuck themselves.”
“Watch out for Talabani, he get[s] on with Peter [Bryan] as well but is liable to taking the mickey where i [he] can and deliver a slackish service because he thinks he’s well in—I gave him a few stern words and he was ok—just need to keep an eye on him…”
“Please note that despite this T&T and Kier will endeavour to progress execution of the contract as soon as possible … I’m just keen that we don’t allow Shires to hold us all to ransom.”
“Irrespective of any other matters which have yet to be formalised, we cannot execute the Contract Documents until the Shire issue is resolved. I note that Shires have written to TTPM (copied to Peter Bryan) on 13 September 04 expressing their continued concern that the matter is preventing execution of the Appointment Docs. Please discuss with TTPM/Abbey and confirm their intentions in this regard.”
“I am prepared to pay the goodwill gesture but no more.”
“Whilst we have a draft set of Contract Documents, there are a number of issues yet to be resolved by the Abbey prior to the signing/exchange of Contracts[,] for example additional fees claimed by Shire Consulting and AA for Landscaping Works. Alan Talabani is aware of these and other issues and should be able to brief you further.”
“The project is currently 28 days in delay and liquidated damages inserted in Appendix 1, Clause 24.2.1 of the contract was£50,000 per week. As such the total amount of liquidated damages recoverable amounts to£200,000 .”
“The above mentioned Works are being undertaken pursuant to a letter of instruction (current version H) dated14 September 2004 . The sum of£164,516.80 as set out in your Project Manager Turner & Townsend’s letter dated7 January 2005 … remains outstanding. You have no right to withhold the sum outstanding, or any part of it. In such circumstances, the ‘Construction Act’ gives us the right to suspend performance of the Works if your failure to pay continues for a period of 7 days from this notice. We therefore look forward to receipt of the outstanding payment by return.”
“Are the Contract clauses applicable?”
“Damages are accruing at a rate of£50k per week. It is understood that the estimate of damages is valid and TTCM do not consider this to be an issue.”
“My firm view is that relations between Kier and the Trust are governed by the letters of intent. The Trust has no entitlement to deduct liquidated and ascertained damages. Kier has no entitlement to seek payment in excess of the cap [in the letter of intent].”
“[W]here you get a situation which involves the use of some special skill or competence, then the test as to whether there has been negligence or not is … the standard of the ordinary skilled man exercising and professing to have that special skill. A man need not possess the highest expert skill; it is well established law that it is sufficient if he exercises the ordinary skill of an ordinary competent man exercising that particular art. … I myself would prefer to put it this way, that he is not guilty of negligence if he has acted in accordance with a practice accepted as proper by a responsible body of medical men skilled in that particular art. … Putting it the other way round, a man is not negligent, if he is acting in accordance with such a practice, merely because there is a body of opinion who would take a contrary view.”
“[I]n my view, the court is not bound to hold that a defendant doctor escapes liability for negligent treatment or diagnosis just because he leads evidence from a number of medical experts who are genuinely of opinion that the defendant’s treatment or diagnosis accorded with sound medical practice. In the Bolam case itself, McNair J. [1957] 1 W.L.R. 583, 587, stated that the defendant had to have acted in accordance with the practice accepted as proper by a ‘responsible body of medical men.’ Later, at p. 588, he referred to ‘a standard of practice recognised as proper by a competent reasonable body of opinion.’ Again, in the passage which I have cited from Maynard's case [Maynard v West Midlands Regional Health Authority [1984] 1 W.L.R. 634], Lord Scarman refers to a ‘respectable’ body of professional opinion. The use of these adjectives—responsible, reasonable and respectable—all show that the court has to be satisfied that the exponents of the body of opinion relied upon can demonstrate that such opinion has a logical basis. In particular in cases involving, as they so often do, the weighing of risks against benefits, the judge before accepting a body of opinion as being responsible, reasonable or respectable, will need to be satisfied that, in forming their views, the experts have directed their minds to the question of comparative risks and benefits and have reached a defensible conclusion on the matter.” “[I]n cases of diagnosis and treatment there are cases where, despite a body of professional opinion sanctioning the defendant’s conduct, the defendant can properly be held liable for negligence … In my judgment that is because, in some cases, it cannot be demonstrated to the judge’s satisfaction that the body of opinion relied upon is reasonable or responsible. In the vast majority of cases the fact that distinguished experts in the field are of a particular opinion will demonstrate the reasonableness of that opinion. In particular, where there are questions of assessment of the relative risks and benefits of adopting a particular medical practice, a reasonable view necessarily presupposes that the relative risks and benefits have been weighed by the experts in forming their opinions. But if, in a rare case, it can be demonstrated that the professional opinion is not capable of withstanding logical analysis, the judge is entitled to hold that the body of opinion is not reasonable or responsible. “I emphasise that in my view it will very seldom be right for a judge to reach the conclusion that views genuinely held by a competent medical expert are unreasonable. The assessment of medical risks and benefits is a matter of clinical judgment which a judge would not normally be able to make without expert evidence. … [I]t would be wrong to allow such assessment to deteriorate into seeking to persuade the judge to prefer one of two views both of which are capable of being logically supported. It is only where a judge can be satisfied that the body of expert opinion cannot be logically supported at all that such opinion will not provide the bench mark by reference to which the defendant’s conduct falls to be assessed.”
“There are qualifications to it as follows. 1. One such qualification is provided by Bolitho as quoted above, namely: ‘But if, in a rare case, it can be demonstrated that the professional opinion is not capable of withstanding logical analysis, the judge is entitled to hold that the body of opinion is not reasonable or responsible.’ 2. Another is referred to in Nye Saunders [Nye Saunders and Partners v Alan E. Bristow (1987) 37 B.L.R. 92] where Stephen Brown L.J. held: ‘[The judge] was entitled to take the view that the evidence of [the architect's experts] did not constitute evidence of a responsible body of architects accepting as a proper practice that no warning of inflation need be given when providing an estimate of the cost of proposed works. It seems to me that the learned judge had ample evidence before him which entitled him to find that there was a failure on the part of Mr Nye to draw the attention of the client to the fact that inflation was a factor which should be taken into account when considering the ultimate cost and that the failure constituted a breach of the Hedley Byrne type duty to the defendant.’ 3. The third qualification is expressed by Lloyd L.J. in Gold v. Haringey Health Authority [1988] 1 Q.B. 481, 490: ‘If the giving of contraceptive advice required no special skill, then I could see an argument that the Bolam test should not apply.’” ‘But if, in a rare case, it can be demonstrated that the professional opinion is not capable of withstanding logical analysis, the judge is entitled to hold that the body of opinion is not reasonable or responsible.’ ‘[The judge] was entitled to take the view that the evidence of [the architect's experts] did not constitute evidence of a responsible body of architects accepting as a proper practice that no warning of inflation need be given when providing an estimate of the cost of proposed works. It seems to me that the learned judge had ample evidence before him which entitled him to find that there was a failure on the part of Mr Nye to draw the attention of the client to the fact that inflation was a factor which should be taken into account when considering the ultimate cost and that the failure constituted a breach of the Hedley Byrne type duty to the defendant.’ ‘If the giving of contraceptive advice required no special skill, then I could see an argument that the Bolam test should not apply.’”
“If a project manager does not have the expertise to advise his client as to the adequacy of the insurance arrangements proposed by the contractor, he has a choice. He may obtain expert advice from an insurance broker or lawyer. Questions may arise as to who has to pay for this. Alternatively, he may inform the client that expert advice is required, and seek to persuade the client to obtain it. What he cannot do is simply act as a ‘post-box’ and send the evidence of the proposed arrangements to the client without comment.”
“The only thing holding up executing the contract docs is Shires appointment. … I suggest we issue a letter of intent for the whole value up to the end of the job. Then Shires can go fuck themselves.”
“In these circumstances, where the plaintiffs’ loss depends upon the actions of an independent third party, it is necessary to consider as a matter of law what it is necessary to establish as a matter of causation, and where causation ends and quantification of damage begins. (1) What has to be proved to establish a causal link between the negligence of the defendants and the loss sustained by the plaintiffs depends in the first instance on whether the negligence consists of some positive act or misfeasance, or an omission or non-feasance. In the former case, the question of causation is one of historical fact. The court has to determine on the balance of probability whether the defendant’s act, for example the careless driving, caused the plaintiff's loss consisting of his broken leg. Once established on balance of probability, that fact is taken as true and the plaintiff recovers his damage in full. There is no discount because the judge considers that the balance is only just tipped in favour of the plaintiff; and the plaintiff gets nothing if he fails to establish that it is more likely than not that the accident resulted in the injury. Questions of quantification of the plaintiff’s loss, however, may depend upon future uncertain events. … It is trite law that these questions are not decided on a balance of probability, but rather on the court’s assessment, often expressed in percentage terms, of the risk eventuating or the prospect of promotion, which it should be noted depends in part at least on the hypothetical acts of a third party ... (2) If the defendant’s negligence consists of an omission, … causation depends, not upon a question of historical fact, but on the answer to the hypothetical question, what would the plaintiff have done if [the defendant had done what it omitted to do]? This can only be a matter of inference to be determined from all the circumstances. … Although the question is a hypothetical one, it is well established that the plaintiff must prove on balance of probability that he would have taken action to obtain the benefit or avoid the risk. But again, if he does establish that, there is no discount because the balance is only just tipped in his favour. … (3) In many cases the plaintiff’s loss depends on the hypothetical action of a third party, either in addition to action by the plaintiff, as in this case, or independently of it. In such a case, does the plaintiff have to prove on balance of probability, as Mr. Jackson submits, that the third party would have acted so as to confer the benefit or avoid the risk to the plaintiff, or can the plaintiff succeed provided he shows that he had a substantial chance rather than a speculative one, the evaluation of the substantial chance being a question of quantification of damages? Although there is not a great deal of authority, and none in the Court of Appeal, relating to solicitors failing to give advice which is directly in point, I have no doubt that Mr. Jackson’s submission is wrong and the second alternative is correct.”
“[I]n my judgment, the plaintiff must prove as a matter of causation that he has a real or substantial chance as opposed to a speculative one. If he succeeds in doing so, the evaluation of the chance is part of the assessment of the quantum of damage, the range lying somewhere between something that just qualifies as real or substantial on the one hand and near certainty on the other. I do not think that it is helpful to seek to lay down in percentage terms what the lower and upper ends of the bracket should be.”
“Q. You’ve got the Trust’s and the school’s best interests, obviously, at the forefront of your mind. If Turner & Townsend had said to you, ‘We’re feeling lucky, let's call their bluff’, and you’d said, ‘What might happen?’, and they’d said, ‘Kier might leave’, you would have said, I assume, ‘I’m not prepared to run that risk’. Is that fair? A. Yes, that’s fair. Q. Because it would, we agree, be taking an irresponsible commercial risk, wouldn’t it? A. Quite so.”
“[H]ad a commercially astute contractor such as Kier been in a position to execute the contract [it] would not have done so on the basis of the terms currently on the table. I consider that, had Kier entered into a single stage design and build contract, at any time from late May 2004 onwards, it would have been, as a minimum, on the basis of an additional payment for 12 weeks prolongation costs plus relief from 12 weeks LADs. By mid September … there were major delays with sub-contractors on the main block on cladding and curtain walling, M&E, plasterwork, joinery and decorations. By this time the factors for and against signing the contract were only tipped further against Kier being willing to sign. I consider the detriment to Kier far outweighed any discernible benefit.”
“I’m afraid I would—I go back to what I said earlier. I think Simon—and I know Simon—is sitting on the fence. If I had been there, I would have looked at this and said, ‘This doesn’t stack up to me. You are not reflecting the true level of risk here,’ because the flags are already there before this report. They’re already saying we are getting into delays and he’s not factoring that. He’s just—he’s excluding that from his report to give himself probably—to enable himself to sit on the fence, is my view of this.”
“In The Aramis[1989] 1 Lloyd’s Law Reports 213 at page 224 Bingham LJ cited with approval the following passage from the judgment of May LJ in The Elli[1985] 1 Lloyd’s Law Reports 107 at 115 to the effect that:- ‘No such contract should be implied on the facts of any given case unless it is necessary to do so: necessary, that is to say, to give business reality to a transaction and to create enforceable obligations between parties who are dealing with one another in circumstances in which one would expect [that] business reality and those enforceable obligations to exist.’ Those principles were also endorsed and applied by the Court of Appeal in Baird Textile Holdings Limited v Marks & Spencer plc[2001] EWCA Civ 274 . Mance LJ observed at paragraph 62 that that the test of any such implication is necessity is clear both on authority and also as a matter of consistency. It could not, he observed, be right to adopt a test of necessity when implying terms into a contract and a more relaxed test when implying a contract, which must itself have terms.” (2) The fact that parties have been dealing on a “subject to contract” basis—I refer again to the express statement in the letters of intent that neither party would be bound by the intended contract unless and until the contract was signed—does not of itself exclude the possibility that the time will come when the necessary implication of their conduct is that they have waived the requirement of a formal written contract. This has been put beyond doubt by the decision of the Supreme Court in RTS Flexible Systems Ltd v Molkerei Alois Müller Gmbh & Co KG (UK Production)[2010] UKSC 14 , [2010] 1 W.L.R. 753. Although that was a decision on a case that raised issues close to that under consideration here, I do not think that counsel referred me to it in argument. In RTS Flexible Systems the Supreme Court was at pains to make clear that whether or not a contract had come into existence would depend on the particular facts of each case. The decision post-dates the dispute between the Trust and Kier; it does not, I think, make new law, but it does perhaps serve to shine a brighter light on the argument under consideration than did the previous authorities. (3) The Trust’s argument that there was an implied contract incorporating the liquidated damages provision had some plausibility. In February 2005 BW had felt that it was more likely than not to succeed, and in October 2005 very experienced construction counsel, Mr Justin Fenwick QC, expressed the view that, although the contractual issues were tricky, the Trust’s was probably the better argument. (It should be emphasised that the view was expressed informally, after only a quick look at limited papers. The relevant point is simply that, having received such a reaction from such experienced counsel, the argument cannot be dismissed as unworthy of consideration.) However, by May 2005 BW had come to the view that, regarding incorporation of the liquidated damages provision, the Trust “[did] not have much of a case” (attendance note of4th May 2005 ). Further, in a careful written Opinion given on25 October 2005 experienced junior counsel, Mr Ben Patten, (now Ben Patten QC), advised that it was “clear beyond any real doubt that the parties contracted on the basis of the letters of intent only” and that an entitlement to recover liquidated damages under the letters of intent was “extremely improbable”
“The essence of a penalty is a payment of money stipulated as in terrorem of the offending party; the essence of liquidated damages is a genuine covenanted pre-estimate of damage. … The question whether a sum stipulated is a penalty or liquidated damages is a question of construction to be decided upon the terms and inherent circumstances of each particular contract, judged as at the time of the making of the contract, not as at the time of breach. ... To assist this task of construction various tests have been suggested, which if applicable to the case under consideration may prove helpful, or even conclusive. … It will be held to be a penalty if the sum stipulated for is extravagant and unconscionable in amount in comparison with the greatest loss that could conceivably be proved to have followed from the breach.”
“… whether a provision is to be treated as a penalty is a matter of construction to be resolved by asking whether at the time the contract was entered into the predominant contractual function of the provision was to deter a party from breaking the contract or to compensate the innocent party for breach. That the contractual function is deterrent rather than compensatory can be deduced by comparing the amount that would be payable on breach with the loss that might be sustained if breach occurred.”
“It is no obstacle to the sum stipulated being a genuine pre-estimate of damage, that the consequences of the breach are such as to make precise pre-estimation almost an impossibility. On the contrary, that is just the situation when it is probable that pre-estimated damage was the true bargain between the parties.”
“3. Claims for an Extension of Time 3.1 Weather The majority of time claimed for the Extension of Time is due to inclement weather. This application was initially submitted by Kier in their letter of17th September 2004 . Turner & Townsend responded to this letter on1st October 2004 requesting additional Information. Kier subsequently issued a second letter on30th November 2004 which requested a nine week extension of time. The amount of time claimed did not appear realistic and of the seven week’s attributed to inclement weather a five week delay was rejected. An extension of time granting a two week extension was therefore issued on2nd December 2004 . 3.2 Value Engineering KN have requested an extension of time (letter of20th November 2004 ) due to the inclusion of works in the Value Engineering Register. The re-design of various elements due to VE opportunities brought about difficulties in construction on site which KN claim added to the programme. For example during value engineering it was proposed by Kier’s team that the Housemaster’s houses could be built without the need for a steel frame. However Kier’s implementation team which had not been party to their value engineered re-design did not feel this was feasible and therefore the programme and costs to Kier appeared to be increased. The roof voids had been proposed to be reduced in size however this appeared to create problems during the construction phase in the routing of the services which clashed with the steelwork. As these works were included in KN’s Contractor’s Proposals they are not a valid reason for an Extension of Time. 3.3 Variations The total variations on the project generated a reduction in the contract sum of£97,463 . The variations instructed are of a minor nature. Works such as the joinery fit-out of the Boot Room (£6k ) and the provision and installation of furniture (£152k ) have been omitted from the contract which should have reduced Kier’s programme overall. As such an extension of time due to variation is not considered valid. … 3.1 Weather The majority of time claimed for the Extension of Time is due to inclement weather. This application was initially submitted by Kier in their letter of17th September 2004 . Turner & Townsend responded to this letter on1st October 2004 requesting additional Information. Kier subsequently issued a second letter on30th November 2004 which requested a nine week extension of time. The amount of time claimed did not appear realistic and of the seven week’s attributed to inclement weather a five week delay was rejected. An extension of time granting a two week extension was therefore issued on2nd December 2004 . 3.2 Value Engineering KN have requested an extension of time (letter of20th November 2004 ) due to the inclusion of works in the Value Engineering Register. The re-design of various elements due to VE opportunities brought about difficulties in construction on site which KN claim added to the programme. For example during value engineering it was proposed by Kier’s team that the Housemaster’s houses could be built without the need for a steel frame. However Kier’s implementation team which had not been party to their value engineered re-design did not feel this was feasible and therefore the programme and costs to Kier appeared to be increased. The roof voids had been proposed to be reduced in size however this appeared to create problems during the construction phase in the routing of the services which clashed with the steelwork. As these works were included in KN’s Contractor’s Proposals they are not a valid reason for an Extension of Time. 3.3 Variations The total variations on the project generated a reduction in the contract sum of£97,463 . The variations instructed are of a minor nature. Works such as the joinery fit-out of the Boot Room (£6k ) and the provision and installation of furniture (£152k ) have been omitted from the contract which should have reduced Kier’s programme overall. As such an extension of time due to variation is not considered valid. … 5 Conclusion The issue of the contract being in place is central. Were the contract in place and the LAD sum not considered penal it appears that the Abbey have a strong case for pursuing their claim.” (3) The logic of TTPM’s primary case on causation at the trial—that Kier’s alleged unwillingness to sign the contract was due to the risk of liability for liquidated damages for delay—was entirely consistent with Mr Edge’s opinion regarding extension of time. The point is made neatly by Mr Hinchliffe (paragraph 102 of his supplemental report): “… from late May 2004, and probably earlier, I believe Kier was aware of programme slippage, for which it realised it would probably struggle to justify the award of an EOT [extension of time].” (4) Dr Aldridge has considered the causes of delay and Kier’s claim for an extension of time. It is unnecessary for the purposes of this judgment to rehearse that analysis in detail; it is consistent with Mr Edge’s opinion and the implication of Mr Hinchliffe’s remark set out above. Dr Aldridge’s conclusion is as follows (supplemental report, paragraph 1.3.17): “The only EOT claim that appears valid is the claim for exceptionally adverse weather. TTPM’s 2 week award for this Relevant Event appears generous …” (5) The claim for an extension of time cannot be discounted entirely, in circumstances where, as Mr Edge had anticipated in his Report, Kier was ostensibly keen “to vigorously defend [its] position”
“Liability for any negligent failure by Us [TTPM] to carry out Our duties under these Terms shall be limited to such liability as is covered by Our Professional Indemnity Insurance Policy terms. Liability is also limited to such a sum as it would be equitable for Us to pay having regard to the extent of Our responsibility for any loss or damage suffered by You on the basis that all other consultants, contractors and subcontractors who also have a liability shall be deemed to have provided contractual undertakings to You on terms no less onerous than these Terms and shall be deemed to have paid to You such sums as it would be just and equitable for them to pay having regard to the extent of their responsibility for any such loss or damage and in no event shall Our liability exceed the fees paid to Us or£1million whichever is the less.”
“We shall take out a policy of Professional Indemnity Insurance with a limit of indemnity of£10 million for any one occurrence or series of occurrences arising out of any one event … and maintain such insurance for a period of 6 years from the date of completion of the services providing such insurance remains available in the market on reasonable rates and terms.”