“(1)(a) …the Contractor and the Sub-Contractor each has the right to refer any matter in dispute arising under or in connection with the Sub-Contract or the carrying out of the Sub-Contract Works to adjudication and either party may at any time give notice in writing (hereinafter called the Notice of Adjudication) to the other of his intention to do so. The adjudication shall be conducted under "The Institution of Civil Engineers’ Adjudication Procedure (1997)"… (b) Unless the adjudicator has already been appointed he is to be appointed by a timetable with the object of securing his appointment and referral of the dispute to him within 7 days of such notice.”
“…You kindly nominated Mr Klein of Warrington as adjudicator. However, our firm view is that Mr Klein is not an appropriate adjudicator in this matter, as we shall explain. Our Mr Fraser conducted a series of adjudications about one year ago, in which Mr Klein acted for the other party. The series was relatively acrimonious, and involved suggestions of forgery and profoundly contradicting credibility. At one stage, Mr Klein misunderstood our submission that a witness statement may have been signed by someone other than its author. This episode triggered his attached fax (redacted to anonymise the parties). We had not, in fact, suggested that Mr Klein had done so, and Mr Klein had misunderstood our submission. With the greatest respect to Mr Klein, whose professional probity we do not question whatsoever, this history may make it difficult to him to be seen to be impartial in this new adjudication. Accordingly, we do not propose to proceed with the adjudication notice in which you have appointed Mr Klein. We have served a fresh adjudication notice, which is attached. We also attach a further nomination application. We invite you to appoint an adjudicator other than Mr Klein (or, for that matter, Mr Dixon, whom you will recall was opposed by Lanes)…”
“I confirm that unless I resign for want of jurisdiction or a Court removes me then I am the duly nominated Adjudicator to adjudicate upon the dispute. I also point out that should Galliford serve the Referral Notice and documentation later than stipulated, I will remain the Adjudicator unless Lanes raise the jurisdictional challenge that the Referral has been served late and, therefore, I cannot have jurisdiction…”
“12. The law with regard to repudiation of an arbitration agreement was not seriously in dispute. It is clear that what BEA needs to show is a repudiation of the agreement to refer the BEA/Bellway dispute to Mr Peter Leaver QC, rather than simply the clause 11 agreement to arbitrate. The claim is made that, by pursuing claims against BEA in the Israeli proceedings, Bellway evinced an intention not to be bound by the agreement to refer those claims to the LCIA arbitration. 13. In order to show a repudiation of that agreement to refer, it was not disputed that BEA would have to show that Bellway evinced an intention no longer to be bound by that agreement and that Bellway's conduct would have to be such that a reasonable person, in BEA's shoes, would understand Bellway to be saying that it was not prepared to continue with the reference. It was common ground that it was not repudiatory merely to bring proceedings in breach of an arbitration agreement, even if the claims pursued in those proceedings were plainly ones which were subject to the arbitration agreement. It was undisputed that a breach of an arbitration agreement by bringing other proceedings was only repudiatory if it was done in circumstances that showed that the party in question no longer intended to be bound to arbitrate. It was also agreed that such an intention could not lightly be inferred and could only be inferred from conduct which was clear and unequivocal. If there was some other reason for the breaching of proceedings it would be hard to infer that the party bringing them intended to renounce its obligation to arbitrate. 14. Thus, if the conduct of that party in all the surrounding circumstances did not reveal a clear intention not to be bound by the agreement to refer the claims in question to arbitration, it could not be said that the arbitration agreement or reference had been repudiated. If it was clear that the party intended to pursue the arbitration, again there could be no repudiation. Whilst Mr McGrath for BEA contended that, if Bellway was seeking to run the same claims against BEA in both the arbitration and in Tel Aviv 2, this would amount to repudiation, because running the claims in Tel Aviv was inconsistent with arbitrating them, it is clear that this could not amount to a renunciation or repudiation of the agreement to refer, since the intention expressed was to continue with the arbitration, albeit alongside other litigation. 15. Whilst a number of authorities were referred to in the skeleton arguments, in the end I was referred only to the decisions of Lloyd J (as he then was) in the Mercanaut[1980] 2 Lloyds Reports 183 and the Golden Anne[1984] 2 Lloyds Reports 489 where the arbitration agreements were breached but the court concluded that the breach was not repudiatory because there was some explanation for bringing the court proceedings which in turn meant that the court could not infer an intention to repudiate.”
“(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section. For this purpose “dispute” includes any difference. (2) The contract shall— (a) enable a party to give notice at any time of his intention to refer a dispute to adjudication; (b) provide a timetable with the object of securing the appointment of the adjudicator and referral of the dispute to him within 7 days of such notice; (c) require the adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred; (d) allow the adjudicator to extend the period of 28 days by up to 14 days, with the consent of the party by whom the dispute was referred; (e) impose a duty on the adjudicator to act impartially; and (f) enable the adjudicator to take the initiative in ascertaining the facts and the law. (3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement. The parties may agree to accept the decision of the adjudicator as finally determining the dispute. (4) The contract shall also provide that the adjudicator is not liable for anything done or omitted in the discharge or purported discharge of his functions as adjudicator unless the act or omission is in bad faith, and that any employee or agent of the adjudicator is similarly protected from liability. (5) If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply.”