“Further to your valued enquiry, we have pleasure in submitting our quotation in accordance with the Schedule of Rates. To supply and fix 1.0mm Rheinzink Graphite Grey finish zinc reveal panel cladding, together with flashings, trims, insulation and support system, etc, in the sum of£45,519.63 exc. VAT. Our offer excludes design, but we would be pleased to advise on details for incorporation in the Architects design; should full design service be required, we would be pleased to advise additional costs. The prices are based on current metal and currency values, to be reviewed on receipt of order. All works to be re-measured on completion. We enclose an Attendance Schedule for your perusal and this should be read in conjunction with this offer. Prices nett and do not include MCD [Main Contractor’s Discount], Monthly Valuations. Payment due 30 days from our invoice date. We do not accept pay when paid Terms. Dayworks:£30 per hour. Materials: Cost + 25% Plant: Cost + 25%. We trust our quotation is of interest and look forward to your further instructions.”
“Further to our previous quotation and subsequent meetings on site, we have pleasure in submitting our revised quotation in accordance with the Schedule of Rates. The quotation has been prepared in accordance with [and there were then set out the revised drawings]. To supply and fix 1.0mm Rheinzink Graphite Grey finish zinc reveal panel cladding, together with flashings, trims, insulation and support system, etc in the sum of£51,308.64 exc. VAT. Our offer excludes design, but we would be pleased to advise on details in the Architects design; should full design service be required, we would be pleased to advise additional costs. All terms and conditions as original quotation. We trust our quotation is of interest and look forward to your further instructions.”
“To supply and fix 1.0mm Rheinzink Graphite Grey finish zinc reveal panel cladding, together with flashings, trims, insulation and support system, etc. All as per your quote dated19th March 2009 .”
“£51,308.64 ” and then these words: “Please liaise with Max on site for programme and details. I will attach details of windows, etc.”
“The parties met on site in about March 2009. At that time the Responding party had received the Referring party’s quotation, but had not accepted it. The Responding party was Mr. Kerai together with his site agent, Mr. Vaghji met Mr. Shanahan for the referring party. Mr. Shanahan was told expressly that the contract between the Responding party and its main contractor - Globeplan Developments Ltd - required the Responding party to hand over the site to Globeplan at the end of June 2009. It was explained that the last works to be undertaken on the site will be the connection of utilities such as gas, water and electricity. For that purpose all scaffolding on the site would have to be dismantled by the end of May 2009. Accordingly, the installation of cladding had to be completed by that date.”
“This defence is served in response to the Referral Notice to Adjudication raised by the Referring party - All Metal Roofing Limited. It is served without prejudice to the Responding party’s contention that the contract between it and the referring party was not a contract in writing within the meaning of Section 107 of the Act and that the Adjudicator has no jurisdiction to make an adjudication thereon.”
“Materially, it is averred that the parties entered into a contract in or about April 2009 based upon the Referring party’s quotation and the purchase order raised by the Responding party on 17th April. However the contract was varied orally or contained express oral terms, namely that time was of the essence and that the time for completion of the Referring party’s works was to be no later than the end of June 2009. In the premises the contract was not a contract in writing within the meaning of Section 107 of the Act in that all the terms have not been evidenced in writing and the Adjudicator has no jurisdiction to adjudicate upon any dispute arising under it.”
“It follows that all the express terms to the Agreement were either in writing or subsequently confirmed in writing such as to satisfy Section 107(2) of the Act. Therefore I conclude that the Agreement was a written construction contract to which the Act applies. That is contrary to Kamm’s submission.”