“19. . . . Obviously it has been clear since applications for enforcement were first made to this court that the intention of Parliament was that adjudicators’ decisions should be honoured, even if the reasoning that justified the decision was erroneous in law or fact. However that policy only applies to decisions which were valid, in that they were decisions which the adjudicator was authorised to make: for example, that the adjudicator had the power to do so (sometimes termed the jurisdiction to do so) and that the decision was not vitiated by some material failure to comply with basic concepts of fairness (sometimes termed compliance with the rules of natural justice, whether in respect of independence or impartiality or in respect of procedural fairness). Accordingly, to speak of a right of enforcement of an adjudicator’s decision is misleading; the right is always qualified or contingent. Moreover section 108(3) of the Act says that the decision is “binding until the dispute is finally determined by legal proceedings….”
“The fundamental issue that I have to decide is whether this submission is correct. Other issues have been raised but that is the key question.”
“It will be convenient to start with [the sub-contractor’s] application for summary judgment, since if that succeeds, the remaining applications fall away.”
“85. The objective which underlies the Act and the statutory scheme requires the courts to respect and enforce the adjudicator’s decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the decision of an adjudicator. The courts should give no encouragement to the approach adopted by DML in the present case; which (contrary to DML’s outline submissions, to which we have referred in paragraph 66 of this judgment) may, indeed, aptly be described as ‘simply scrabbling around to find some argument, however tenuous, to resist payment’. 86. It is only too easy in a complex case for a party who is dissatisfied with the decision of an adjudicator to comb through the adjudicator’s reasons and identify points upon which to present a challenge under the labels ‘excess of jurisdiction’ or ‘breach of natural justice’. It must be kept in mind that the majority of adjudicators are not chosen for their expertise as lawyers. Their skills are as likely (if not more likely) to lie in other disciplines. The task of the adjudicator is not to act as arbitrator or judge. The time constraints within which he is expected to operate are proof of that. The task of the adjudicator is to find an interim solution which meets the needs of the case. Parliament may be taken to have recognised that, in the absence of an interim solution, the contractor (or sub-contractor) or his sub-contractors will be driven into insolvency through a wrongful withholding of payments properly due. The statutory scheme provides a means of meeting the legitimate cash-flow requirements of contractors and their subcontractors. The need to have the ‘right’ answer has been subordinated to the need to have an answer quickly. The Scheme was not enacted in order to provide definitive answers to complex questions. Indeed, it may be open to doubt whether Parliament contemplated that disputes involving difficult questions of law would be referred to adjudication under the statutory scheme; or whether such disputes are suitable for adjudication under the Scheme. We have every sympathy for an adjudicator faced with the need to reach a decision in a case like the present. 87. In short, in the overwhelming majority of cases, the proper course for the party who is unsuccessful in an adjudication under the scheme must be to pay the amount that he has been ordered to pay by the adjudicator. If he does not accept the adjudicator’s decision as correct (whether on the facts or in law), he can take legal or arbitration proceedings in order to establish the true position. To seek to challenge the adjudicator’s decision on the ground that he has exceeded his jurisdiction or breached the rules of natural justice (save in the plainest cases) is likely to lead to a substantial waste of time and expense – as, we suspect, the costs incurred in the present case will demonstrate only too clearly.”
“This was an inappropriate methodology because by the time the adjudicator reached his decision, the figures in certificate No. 35 were no longer ARL's figures. They had been replaced by the larger negative figure in interim certificate No. 36.”
“Accordingly, I should instead take the figure of£552,891.30 , being the figure by which ARL asserted that GOL had been overpaid in IC35, and if I determine that the two disputes referred to me have a value in excess of that figure I may decide that a payment is due to GOL.” 70. Taken by itself that is unremarkable. However, at paragraph 28 he said: “It therefore seems to me to be the preferable course to take the alleged overpayment figure in IC 35, which was the crystallized figure prior to commencement of the adjudication, based on an interim certificate which had been issued, and to award sums as due to GOL only if their total exceeds the figure of£552,891.30 contained in that certificate. I note that that is the alternative position adopted by ARL in paragraph 95 of the Response and that is therefore the methodology which I propose to adopt.”
“In ordering ARL to pay any sum to GOL, the Adjudicator ignored his own findings as to what ARL had credited GOL with in Certificate 35 and accordingly . . . was wrong in law”