“We understand that the development proposal is to excavate the minimum of contaminated material from within the footprints of the proposed structures and replenish the excavated voids with clean, inert material and no measures are currently proposed to remediate the remainder of this area of the site.”
“Chemical contamination testing has shown a high degree of contamination, and consideration must be given to the relative costs of total removal and replacement compared to partial removal and replacement in containing the movement of the remaining contaminants on site.”
“During the construction of the SAC plant, materials were excavated and tipped on the area of derelict ground on the northwest area of the site. The excavated materials, blue in colour, were thought to have originated from former sulphuric acid manufacture or possibly a former gasworks, although its presence has never been established. It is considered likely that Blue Billy spent oxide from gasworks was imported to the site as a raw material for use in the sulphuric acid production.”
“I have spoken with Adam regarding potential land filling of the cyanide enriched material. Landfill costs may be in the region of£70 per cubic metre (roughly 2 tonnes) however this does not include for the import of fill to replace the voids, which would be subject to availability. This also assumes a landfill in relatively close proximity to the site that may accept hazardous waste. The new legislation relating to land filling of hazardous waste does come into effect in July 2004. From this time on, all hazardous waste will require pre-treating prior to disposal. The definition of ‘pre-treatment’ is however open to some interpretation and has yet to be confirmed. Screening of materials to remove large particles may be sufficient enough to qualify as ‘pre-treatment’ however more extensive treatment may be required.”
“● Highly contaminated source areas (e.g. Blue Billy’s) are removed from site prior to the introduction of the new Landfill Directive in July 2004; ● The Environment Agency continues to adopt an element of pragmatism during the agreement of risk based cleanup levels for contaminated ground water, especially in relation to dilution. The Environment Agency have already been contacted and although the exact location of the site was not discussed, it was inferred that they would favourably view our assumptions in relation to the proposed remediation scheme; ● The construction of a clay cap across the site is considered an adequate remedial option by the Local Authority and protective of human health; ● Soil and ground water contamination does not increase in extent or concentration from that encountered during this investigation, potentially resulting from current or future operations; and ● The costs do not account for demolition of the existing facility or potential contamination resulting from these works.”
“… A high technology sulphuric acid re-concentration plant and dedicated water treatment system was constructed and opened in September 1995. During the construction of the SAC (Sulphuric Acid Concentration) plant, materials were excavated and tipped on the area of derelict ground in the north west area of the site. The excavated materials, blue in colour, were thought to have originated from former sulphuric acid manufacture or possibly a former gas works, although its presence has never been established. It is considered likely that ‘Blue Billy’ spent oxide from gas works was imported to the site as a raw material for use in the sulphuric acid production …” (b) Paragraph 2.8, which set out in detail the previous investigations. This part of the Report identified the high levels of cyanide disclosed in the first and second Travers Morgan Reports, referred to above, and also referred to other Travers Morgan Reports which I have not seen, but which, according to the URS summary, also talked about cyanide contamination. (c) Paragraph 2.11, which was entitled ‘Preliminary Conceptual Site Model’ and which stated, in respect of Zone 2 that “a site walkover indicated the presence of blue coloured ground in several areas across the lorry park and along the edge of the raised area to the far north of the western area of derelict land. This is suggested to be associated with former site activities such as the manufacture of sulphuric acid”
“The analysis is also based on a greater than 90% probability that the Local Authority will not request the removal of soil contaminated with Blue Billy residues to a maximum depth of 1.5 metres bgl in those areas identified to the south and north west of the site. The probability of being asked to provide a more complex cap is deemed to be a more likely scenario than full excavation. It is for this reason that the cost for the disposal of Blue Billy at depths greater 0.5 m bgl has not been included in the Worst Reasonable Case.”
“… could reduce the forecast worst case estimate to£7.5 million , although there is some doubt that disposal of the material could be completed before July 2004.”
“When analysing the information the biggest cost risk areas relate to the Local Authority’s attitude to the removal of the Blue Billy. Following consultation with the LA, we will be able to develop a management strategy in conjunction with yourselves that should be able to reduce the costs liabilities to a maximum of£7.4 million and hopefully even less. We are aware that Barrett Homes are dealing with a contaminated Blue Billy site in Southend and their solution is to leave the Blue Billy in situ, treat the soils and provide a cap for the gardens.”
“JOHN WANTS THIS PARAGRAPH REMOVING.”
“Both of the scenarios described above are based on the understanding that source removal of the soils, unless associated with any ground water treatment, and in addition to the Blue Billy residues, are not required. However, following approval from the regulators, the proposed cap may mitigate risks to end users from contaminated soil that remains on-site … When analysing the information the biggest cost risk area relates to the Local Authority’s attitude to the removal of the Blue Billy. Following consultation with the LA, we would propose to develop a management strategy, in conjunction with yourselves, that will aim to reduce the costs liabilities to lower than those contained with the worst forecast case. Indeed we have just been made aware, through a sub-contractor, that Barrett Homes are dealing with a contaminated site (Blue Billy) in Southend. The solution comprises in-situ treatment of the Blue Billy and the provision of a capping layer, where required. We are at present endeavouring to acquire more details of this example, and would hope that this example may provide the Local Authority with some confidence in our proposed strategy.”
“(a) Lambson had discovered soil visually impacted by Blue Billy in the areas on top of which Lambson proposed to and did thereafter construct buildings and infrastructure.” (b) Lambson had excavated all of the Blue Billy visually impacted soils and deposited the materials on the area of derelict ground in the northwest area of the site. (c) Lambson also confirmed that the Blue Billy visually impacted soils in the southern area had been there when Lambson purchased the property and had not been moved by Lambson.”
‘Have we got most of it? Yes, we have’
“I warrant and confirm that from31 December 1977 , being the date the Company … took occupation of the property the company has not deposited generated or utilised the Blue Billy situated in the areas edged blue on the plan attached to this letter.”
“Further to our recent meeting, you have asked that I confirm the position regarding possible contamination at the property in addition to that previously disclosed. I note you are particularly concerned to ensure that I am not aware of any contamination under the buildings due to be demolished pursuant to the Demolition Contract which I am shortly to complete with my demolition contractor. I should be grateful if you would accept this letter as my undertaking and confirmation that I have no knowledge of any further contamination at Cinder Lane, Castleford, other than that specifically identified in the Environmental Survey Report produced by URS dated May 2004. We have agreed that the bore hole test results indicate a level of contamination for the property as a whole and should therefore not be construed as meaning there is only contamination at the site of the bore holes. I note that you and your lender will be relying on this letter as part of the general disclosures on this transaction and in the circumstances, reference to this letter is made in the Sale and Leaseback Contract.”
“A. The parties have agreed to enter into this deed pursuant to an agreement dated [14 May 2004 ] wherein the Seller agreed that the Buyer would withhold£500,000 of the purchase price for the property as the Seller’s contribution towards the Clean-Up Costs of any further contamination caused by the Seller at the Property during the Period. B. The parties have entered into this Deed to give further clarification as to the terms upon which the Retention is to be held and the circumstances in which the Retention is payable to the Seller.”
“’Clean-Up Costs’ means the reasonable and proper additional clean-up costs that the Buyer or any successor is likely to incur in developing the Property for residential use in accordance with the environmental standards required by the local authority and the environment agency and taking into account common industry practice which result from the Further Contamination and for the avoidance of doubt such costs shall include costs such as loss of revenue arising from the Seller being unable to use any part of the Property due to the treatment of such Further Contamination … ‘Further Contamination’ means (1) in relation to those parts of the Property previously tested by URS and recorded in the URS Report – an increase in the level of contamination from that shown in the URS Report for the relevant part of the Property and (2) in relation to those parts of the Property on which the Demolition Works have been undertaken and which have been tested for the first time following the Date of Completion of the Demolition Works – an increase in the level of contamination from that shown in the URS Report for the parts of the Property immediately adjacent to the part of the Property on which the Demolition Works have been undertaken … ‘New Environmental Survey’ means a further environmental survey carried out by the Environment Expert to identify: (a) whether there has been Further Contamination; (b) whether the Further Contamination has been caused by the Seller during the Period and if the Demolition Works were carried out after the Period whether the carrying out of the demolition works have caused Further Contamination; (c) if relevant the likely level of Clean –Up Costs.”
“2.1 To pay the Retention to the Buyer’s Solicitors and to direct that the Retention be held in the Howard Kennedy’s Client Account on trust for the Seller to be dealt with in accordance with this Deed with interest accruing to the Seller. 2.2 Within ten Working Days of the Date of Completion of the Demolition Works to instruct the Environmental Expert to carry out a New Environmental Survey. 2.3 That it has instructed Howard Kennedy that no monies may be withdrawn from Howard Kennedy’s Client Account save in accordance with Clauses 2.4, 4 or 9.2 hereof. 2.4 That it has instructed Howard Kennedy to telegraphically transfer to the Seller’s Solicitors Client Account the Retention with accrued interest: 2.4.1 within five Working Days of receipt by the Buyer of the results of the New Environmental Survey if the results of the New Environmental Survey either 2.4.1.1 confirm that there is no Further Contamination or are inconclusive; or 2.4.1.2 confirm that there is Further Contamination but does not conclude that this was caused by the Seller during the Period subject to clause 15; 2.4.2 within five Working Days of the expiration of the three month period commencing on the Date of Completion of Demolition Works if the Environmental Expert fails to issue the results of the New Environmental Survey to the Seller within such three month period.” 2.4.1 within five Working Days of receipt by the Buyer of the results of the New Environmental Survey if the results of the New Environmental Survey either 2.4.1.1 confirm that there is no Further Contamination or are inconclusive; or 2.4.1.2 confirm that there is Further Contamination but does not conclude that this was caused by the Seller during the Period subject to clause 15; 2.4.2 within five Working Days of the expiration of the three month period commencing on the Date of Completion of Demolition Works if the Environmental Expert fails to issue the results of the New Environmental Survey to the Seller within such three month period.”
“The parties have agreed to enter into this Deed whereby the Seller agrees to allow the Buyer to withhold£100,000 from the existing retention of£500,000 as the Seller’s contribution towards the Clean-Up costs of any further decontamination caused by the Seller at the Property during the Period. The parties have entered into this Deed to give further clarification as to the terms on which the Retention is to be held and the circumstances in which the Retention is payable to the Seller.”
“We have agreed to halt operations to review where legally responsibilities remain, however I understand you together with URS are looking at other options. I would request in my absence no monies are removed from the escrow account until I return from China when hopefully we may have other options to pursue. In relation to costs to date, we are quite happy as a gesture of goodwill to fulfil our commitment in relation to the areas previously agreed between ourselves. However in support of our last telephone conversation I agree it gives rise to a conflict of interests if we dig out material sub-surface in relation to the progress you wish to follow (i.e. capping the material in situ).”
“One has to remember, when looking at issues about the factual matrix, that although reference to that matrix is not limited to cases where the words are clearly ambiguous, the first place where one expects to find the meaning of the words and the intention of the draftsmen is in the words themselves. If they yield a fairly clear solution, and in my judgment these words do, then one has to pause long before concluding that at that point the draftsmen has used words with a meaning that do not fit in with the objective that he was seeking to attain.”