“We understand that there is a possibility of the Design Team being novated to a contractor at some stage in the project. We confirm that we have had experience of this type of situation and are comfortable with this arrangement. Our fees would still stand if novation took place.”
“A particular feature of the scheme is the extensive boundary retaining wall requirement. Height of walls varies from approximately 2-4m at the north up to approximately 11.5m along the south boundary. All walls will be close to existing buildings or highways. Design and construction methods will have to ensure that no significant movement occurs at the top of the walls which could lead to damage to structures, road construction or underground services. Where walls are low and spaces available to excavate outside the line of the wall then in situ reinforced concrete walls can be used. Elsewhere options will include secant pile walls … and diaphragm walls ... Over 4-5m high both these types will need to be propped temporarily before construction of adjoining structure …”
“We understood that there is a possibility that we would be novated under a Design/Build Contract in due course. Is this still the case and if so should this be referred to here?”
“(b) – No it will be a JCT 80 contract.”
“From an initial review of the drawings, it would appear that superstructure outside the cinema area will be similar to our original proposals but with total area reduced. Within the cinema area, the main entrance floor has dropped below the Plaza Level, and the roof has been lowered …”
“Construction probably to be by Morrison Construction with BA reviewing and commenting on all prices. Critical packages to be identified and where necessary a letter of intent given to start prefabrication etc before main contract agreed.”
“Q. And I just want to ask you about the last, pretty much the last entry on your note, which says: "Architect less comfortable with D and B traditional, eng no problems." Can you explain what was being discussed and what that note reflects? A.That was reference to the fact that the project would probably be a design and build project and the impression that I got from the discussion that went around the table is that the architect would have preferred a traditional scheme rather than a design and build scheme but there was no problem noted from the engineer, in respect that it would be a design and build.”
“It was noted that drawings of the existing structures are stored in the old hospital buildings and it was felt that these may contain information which could be of use to the engineers in respect of the elements of the structure which are to be retained. JG [Mr Gray of MDL] to arrange for licence to cover access to this information.”
“… although the drawings of existing structures were available, these were stored in the old hospital building and ran into many thousands of drawings, with no apparent index system. Previous enquiries have confirmed that it has not been possible to locate drawings for the existing elevations and structure which were to be retained and as such it was felt that the offer was there, to the engineer and architect should they require it, but it was felt that the time spent looking for this information may be counterproductive.”
“5.1.3 ML [Mr Lewis of MDL] confirmed that a further meeting with Morrison Construction had been held in the offices of DLG to discuss detailed design of the project. A draft programme had now been received from Morrison Construction, together with ongoing design discussions – this will be firmed up in more detail … 12.2 NF [of BA] to prepare a list of standard amendments to the D&B form of Contract as these will be required for the Agreement to lease of AMC. PR [of MDL] confirmed that standing amendments have been agreed with Morrison Construction and the two would need to be considered jointly. PR to send ML a copy of agreed amendments.”
“This new development in the city centre of Birmingham is by Morrison Property Solutions Limited a joint venture company between Morrison Development Limited and Property Solutions Limited. Construction of the project will be managed by Morrison Construction Limited. The project consists of the following developments: (i) a multi-cinema complex with 22 auditoria; (ii) retail and restaurant units; (iii) three level basement car park for 1,400 cars; (vi) residential units; (v) a fitness club with 25m swimming pool. The site is located at the former Birmingham Children’s Hospital where the façade will be retained and the rest of the old buildings will be demolished for this new development. A particular feature of the scheme is the extensive boundary retaining wall requirement. Height of walls varies from approximate 2-4m at the north up to approximately 11.5m along the south boundaries … The size of the site is approximately 200m x 180m.”
“MMG Structures Division will provide a full civil and structural design service to Morrison Property Solutions Limited. The work consists of the following … • Prepare demolition specification and schedule document for the Birmingham Children’s Hospital. • Prepare performance specification and scheme drawings for retaining wall along perimeter of the site boundary. • Prepare preliminary design and general arrangement drawings for superstructures of multi-cinema complex, three level basement car park, retail and restaurant units, residential units and fitness club with 25m swimming pool, including roads and drainage works. • Follow on from preliminary design work, prepare specification, detailed design and contract drawings for sub-structure foundation and superstructures of the complex …” • Prepare demolition specification and schedule document for the Birmingham Children’s Hospital. • Prepare performance specification and scheme drawings for retaining wall along perimeter of the site boundary. • Prepare preliminary design and general arrangement drawings for superstructures of multi-cinema complex, three level basement car park, retail and restaurant units, residential units and fitness club with 25m swimming pool, including roads and drainage works. • Follow on from preliminary design work, prepare specification, detailed design and contract drawings for sub-structure foundation and superstructures of the complex …”
“An overall review will be carried out during April 1999. The reviewer will: • Review design for suitability of concept. • Check load paths for vertical and horizontal loads …”
“I enclose for your attention the schedule for Morrison Construction showing when information is required in terms of procurement in order to obtain [bid] packages for a Design and Build Contract to be completed with firm price by the end of June.”
“1. The “bid period” in its entirety, 23 weeks, was discussed. It was reiterated that the initial four weeks was to allow MDL to meet the Development and design freeze date and issue the “bid documentation”
“We confirm it is our intention to enter into a contract for the design and construction of the above development, subject to agreement being reached on the terms and conditions of the proposed form of contract. Pending issue of the full suite of Main Contract Documents, please make all necessary appropriate arrangements to ensure the progress of the under noted list of advanced works packages (together with the establishment of a suitable level of on site preliminaries and off site management resources) is commence[d], in order to enable you to comply with and accommodate the current strategic programme of events: • Contiguous piling to perimeter retaining walls – approximate anticipated cost of works£600,000 . • Enabling works and attendances associated with the contiguous piling – approximate anticipated cost of works£200,000 …”
“Design development and revised layouts to suit potential tenants is to continue in parallel but be kept separate from the preparation of the bid information.”
“It was confirmed that Rowens would be brought on board as initial partners on the basis of their offer to work up the design with Mott Macdonald for a six-week period until the end of September. At this stage Rowens were prepared to re-negotiate a tender figure or if we are unable to agree terms with them, time will allow to resubmit full tender submissions to the market. This therefore gives us the benefit of the design sub-contract input at nil cost and the option to re-approach the market if it is felt appropriate.”
“As the PSM meetings have been advised from28 June 1999 and at each subsequent meeting, we have had growing concerns in respect of the sufficiency of design information being released to allow us to adequately tender the Bid packages and meet our stated intention of 60% of cost surety by the end of September: these concerns have proven to be well founded and the assessment on9 September 1999 by myself and Mark Weaver, the Employer’s Agent, is that this may fall to as low as 25%. In light of our video conference with Ken Gillespie, wherein the difficulties we are facing in respect of the Design Team’s release of information due to the fact that they are still responding directly to MDL as the “paymasters” were discussed at length, I confirm that a meeting has been arranged to include Martin Lewis, Alistair Paterson [DLG] and Tim Dawson [Motts] tomorrow to discuss how the problems can be mitigated and establish handover of the Design Team to MCL and under what auspices.”
‘J McM advised the consultants that from this point onwards they were to respond to MCL’s requirements as priority. ML [of MDL] objected to this proposal, reminded J McM that Developments were under extreme pressure to progress lettings and reiterated that both he and John Gray [of MDL] had acknowledged that their use of the shared architectural, and to a lesser extent structural, resource had impacted on the consultants’ ability to release the bid information to MCL. Notwithstanding this ML required “first call” on the Design Team to enable MD to complete the deliberations with at least Healthlands and Wessex and possibly other opportunities before they would be in a position to allow the Design Team handover to take place …’
“The consultants confirmed, in discussion with Neil Marshall, that all outstanding information would be made available by close of business Friday 24.09.99. This will be too late for the end of September but should allow us to utilise the procedure suggested in 4 above to provide a more accurate contract sum at the end of the programmed bid period.”
“CBB [Mr Byrne of MCL] queried the design responsibilities of the team. PE [Mr Emerson] explained that MM were producing the base design in close liaison with SR (to achieve best value engineering solutions) and SR were detailing final connections.”
“It was confirmed that insufficient information was available from Mott Macdonald and it was confirmed that all outstanding information would be with Rowens by 24 September. Rowens agreed to consider and submit a price by the 6 October …”
“It was acknowledged that the Design Team would probably not be novated to MCL prior to the end of October but for all intents and purposes had been under Morrison Construction’s control for several weeks.”
“As you are aware the Appointment documentation is to be novated to the Building Contractor upon completion of the Design and Build Contract. To enable us to accomplish this, a Novation Agreement needs to be entered into between yourselves, ourselves and Morrison Construction Limited. I enclose the form of Novation Agreement, which we use, which requires to be agreed between us. The services listed in the Second Schedule will be the services retained by [MDL] with you and the services to be included within the First Schedule are any additional services that are required from you, as agreed with the Contractor.”
“The Consultants hereby acknowledge that subject to Clause 5 below the Contractor is the party now entitled to the full benefit and burden of the Consultancy Agreement together with the full benefit of all payments already made by the Client to the Consultants thereunder and of all the services so far supplied by the Consultants.”
“It was stressed that the Project Co-Ordinator, in respect of the scheme is Martin Lewis on behalf of Morrison Developments. Therefore, if actions that have been agreed at meetings are then consequently not to be pursued they must be communicated immediately to Martin Lewis, so that Morrison Developments are kept informed of progress or otherwise.”
“Following our discussions of Wednesday20th October 1999 we write enclosing the revised wording of the First Schedule of the Novation Agreement for your company’s services in the format agreed at our meetings. Please would you confirm by return that the format is now agreed and that although not specifically discussed or agreed that the services do not attract additional fees to those contained within Morrison Developments’ original services agreement with your company.”
“[BA] have received a report from MCL on detailing information flow for the bid… Given the content of this report and its implications on the bid, [BA] are finding it difficult to provide Group [Morrison Group] with a market tested figure to enable a capped cost to be provided to the bank due to the fact that only 29% of the construction costs are anywhere near firm. The overview of this situation is firstly MCL will provide a bid by 31/10/99 which will obviously due to lack of information/market tested prices include an element of contingency and risk…”
“…we write to further clarify that the release of design information from the Consultants on the project as of18 October 1999 is continuing to affect our ability to provide fixed price certainty. We are continuing to analyse and assess through package co-ordination/interface meetings the risk associated with the information shortfall but will necessarily need to include contingency figures to compensate for these shortfalls at the end of the month.”
“Poor issue of information by consultant to date, particularly Structural Engineer. Allowance for contingency to be made against each trade package taking into account the level of information provided.”
“S McBrierty queried why the current contract sum was so high, why it had moved so much in the period since the interim adjudication and in particular why the cladding package had doubled. T Marsh responded that at every Project Strategy Meeting and at the Interim Review it had been explained that the Design process, which MCL were trying to manage but did not control, was not keeping pace with the Bid and consequently the bid packages were being issued with big detail deficiencies … T Marsh reiterated that the single biggest ‘failing’ of the Bid was MDL not establishing and freezing the base design and relinquishing control of the Design Team in accordance with the ‘roll-out’ document and this had been discussed on number occasion [sic] during the Bid period with C Matthews. S McBrierty responded to the effect that Developments needed the Design input to finalise their requirements. T Marsh acknowledged this but the knock-on effect to the efficiency of the Bid could not therefore be ignored. S McBrierty said ‘this always happens’ – T Marsh responded that in that case either the roll-out philosophy should be reviewed or MDL, when they appoint the consultants, should write-in the dual MDL/MCL requirement for resource so that neither party should be seen to be instructing the other.”
“The foregoing clearly demonstrates two important points (i) MCL have voiced concerns at the ability of the Design Team to provide the necessary Bid information since 28 June, one week after week zero was set and three weeks before the commencement of the MCL Bid and consistently thereafter. (ii) The lack of information and late release is recorded in the information review and when paraphrased in the final package summary the late issue/returns in the last three weeks of the Bid period evidences our assertion that to have achieved the costs certainty levels that we did by the end of October was a minor miracle.”
“As discussed the attached highlights details of the late release of information that the Bid team had to contend with and demonstrates the major influx of material received between the dates of the interim adjudication and the final adjudication. I have also taken the opportunity to add details of when we recorded our concerns, and to whom, to confirm that the original targets set by Group could not have been met and that the relatively high levels of assessed works and residual contingency should not have been a surprise to anyone involved with the Bid…” (i) MCL have voiced concerns at the ability of the Design Team to provide the necessary Bid information since 28 June, one week after week zero was set and three weeks before the commencement of the MCL Bid and consistently thereafter. (ii) The lack of information and late release is recorded in the information review and when paraphrased in the final package summary the late issue/returns in the last three weeks of the Bid period evidences our assertion that to have achieved the costs certainty levels that we did by the end of October was a minor miracle.”
“In an attempt to resolve the issue of our contract value and enable us to commence meaningful design, to protect what is becoming a pressing programme constraint, we are willing to undertake the design work on the basis that Mott Macdonald provide us with all necessary assistance in respect of co-ordination and access to design information in their possession.”
“We are now entering into the critical phase of the design and construction work and so I would like to make some suggestions for the management of the design. During the development of the retaining wall drawings we tried to incorporate building development concurrently with our drawings in order to minimise later construction changes. This has caused disruption to the design process of co-ordination checking, etc and criticism from the site team. To date we have necessarily had to develop the design on a broad front to meet the costing requirements. In order to meet future milestones we need to manage the design more methodically so that the flow and quality of information can clearly be monitored. We are always last to receive information but first required on site.”
“The Novation of the Professional Appointments is still outstanding, as negotiation of additional fees to Professionals requires reconciling. ML/TM [Messrs Lewis and Marsh] are to discuss this outside the meeting as it is not logical for additional fees to be required as the original appointments were both on a full design service and not the lesser Design Build service.”
“TM reviewed his report and confirmed that with regard to Bid, the Adjudication Meeting held on10 November 1999 came up with a figure of£37.6m and actions had been agreed to close the gap. MCL are reviewing again the situation next Wednesday. As Bank of Scotland require a further credit approval, a firm construction price is required before the final adjudication AJ [MDL] will discuss this with SMcB/JMcM.”
“You should be aware that Morrison Building Division have now concluded their initial bidding period and have presented Morrison Developments with their financial proposals for the above scheme. Whilst much remains to be done, on negotiating the final figure and concurrently ‘engineering’ the current design with the preferred sub-contractors; with the principal leases of AMC, Healthlands and Wessex Bowl in place, it is now appropriate to formally effect the novation of the designers from Morrison Developments to Morrison Building. With this objective, I invite you to attend our Sutton Coldfield offices on Friday26 November 1999 at 10 am …”
“With respect of the steel frame design, this design will be completed by our sub-contractor Rowen Structures Limited, therefore the related section of the Scope of Design and Services will be amended to read ‘Steel frame check and co-ordinate’ only. Please confirm your acceptance of the above revised documents and the reduction in the fee previously agreed with Morrison Developments due to the revised Scope of Services required by the First Schedule.”
“Design Fabrication Supply and Installation of Structural Steelwork Metal Deck and Pre-Cast Concrete …”
“From a technical perspective, we just need to make sure that any delays or costs to date are not ‘lost’ through the Novation process.”
“The First Schedule incorporating additional services requested by MCL had been agreed. Given MCL’s decision to go with a Contractor designed solution for the steelwork, final agreement of the fees had not been reached.”
“The Execution of the Novations After the meeting C Byrne proposed to circulate final copies of the Agreements that MCL had reached with each of the designers. Documents will be signed and ‘held’, to be executed concurrently with the Building Contract.”
“Please find enclosed our updated procurement programme C dated18 November 1999 . This document will be supplemented with design information release schedules which will be issued in the coming week. These documents will form part of the Agreement and will detail when design information release is required.”
“Steel frame coordinate and checking only”
“13. The requirements for the works to the S/C [Sub-Contractor] design is as instructed and has been instigated to reduce the risks that were inherent if MMcD had continued with the design – the overall control of the design remains with MCL.”
“Further to your letter I would like to advise that I do not agree with your assertion that we had a shortfall of design information and that this has offset the effects of the tenant’s changes and the reduction in design of the steelwork. There have been considerable changes to the Project, both technically and from a programme point of view. The car park was changed to incorporate a flat plate design. I advised of our additional costs at the time. The effect of the car park changes caused considerable delays and redesign to the structure and also the highway works. It should be noted that at the time of our fee bid/offer, it was anticipated that the car park would be a pre-cast concrete package i.e. with Contractor’s design. Therefore there is no reduction in our scope. This is a complex Project and I believe that a significant input is required from us to assist in its success. This will require large teams to enable a fast turn around of information etc. I must reiterate that we maintain a significant resource on the Project to achieve the costing requirements even though in my opinion the Project had not been developed in a methodical manner. I would like to discuss our scope of work with you for the remaining work so that I can determine our fee situation. I am very keen to resolve this issue so that we can keep the correct resources on the Project to meet your tight deadlines.”
“Notwithstanding the difficulties we had encountered in obtaining sufficient design details in order to price the contract, we submitted a firm bid for the construction contract on21 January 2000 based on the design information which had been provided by the design team, including Mott”
“The floor slabs in the car park and at plaza level are generally used to prop the retaining walls, as specified in Clause G10/111 of the Specification Structure Steelwork. Could you please provide your calculations, in accordance with this clause, to demonstrate that the floor construction satisfied the loadings given?”
“6. The meeting was advised that the report recognised only two values; the£38.1m January Bid and the£35.375 Contract Sum …”
“We are in receipt of your copy letter to Tim Dawson to Chris Byrne27 October 1999 relating to the First Schedule at the Novation Agreement and had no objection to this letter being incorporated within the Agreement to clarify your company’s duties in relation to the specific clauses. With reference to the Design Release Schedule this document was produced in November 1999 when the document was agreed in principle and records the requirement for design release at the moment in time. This Schedule will necessarily be updated during the Project to incorporate design change. I would request that you sign the Novation document on the above basis and return to me as a matter of urgency.”
“At the beginning of March 2000 our Credit Management Section were advised by the Morrison Group that our invoices for Nov ’99, Dec’99, Jan ’00, Feb ’00 were to be reissued to Morrison Construction Ltd with Edgbaston, Birmingham. This we did on7 March 2000 including with them a new account for additional fees. We have now received a letter from Mr N Marshall with Morrison Construction Ltd saying that the Nov ’99 and Dec ’99 invoices remained Morrison Development’s responsibility for payment and we were asked, during a telephone conversation on20 March 2000 , to reissue the two invoices to cover the Morrison Property Solutions in Edinburgh. We trust that you will therefore find these reissued accounts in order and look forward to receiving settlement in due course.”
“We intend to place a building contract (“the Building Contract”) in a version of the JCT Standard Form of Building Contract [1980 Edition] [with Contractor’s Design 1981 Edition] with [ ] (“the Contractor”] to construct the Development…”
“The Normal Services set out in the ACE Conditions as previously referred to and Additional Services as shown on the attached Appendix”
“2.4 Scheme Design Stage After receiving the Client’s consent to proceed to the Scheme Design Stage:- … (b) Develop the design of the outline proposals for the Works in collaboration with the Lead Consultant and any Other Consultants. (c) Prepare such representative sketches, drawings, specifications and/or calculations as are necessary to enable the Lead Consultant or any Other Consultant to prepare the Cost Plan… (e) Collaborate with the Lead Consultant and any Other Consultant to prepare the scheme design and Cost Plan for presentation to the Client… 2.6 Tender Stage After receiving the Client’s approval of the developed design and the Client’s consent to proceed to the Tender Stage:- (a) Assist the Lead Consultant to assemble the tender Documentation and to issue it to firms selected to tender… 2.7 Production Information Stage After receiving the Client’s consent to proceed to the Production Information Stage:-… (c) Prepare any further drawings and schedules necessary to enable Contractors to carry out the Works…”
“…does not involve the transfer of any property at all, for…it comprises the annulment of one debt and the creation of another” (United Railways of Havana and Regla Warehouses Ltd[1960] Ch 52 , 88) Chitty on Contracts (Para. 19.87) adds: “It should, however, be noted that the effect of a novation is not to assign or transfer a right or liability but rather to extinguish the original contract and replace it with another”
“When requested by us to do so you shall execute Warranties in which you will recognise that you owe a duty to exercise reasonable skill, care and attention in the execution of your professional duties hereunder and that the duty of care owed by you extends not only to us but to third parties who might have or acquire an interest in all or part of the Development. The execution by you of such a Warranty will create contractual relationships with and/or duties of care owed to, but exclusively, Tenants, Purchasers and/or Funders (whether commercially or by way of grant) of the Development…”
“[MM] acknowledges and warrants to the [recipient of the warranty] that [MM] has been appointed and properly instructed by the Developer as Structural Engineers in connection with the Development and in respect of all matters which lie within the scope of its professional responsibility in relation to the Development insofar as they relate to the Property [MM] has and will continue to exercise all reasonable skill care and attention. [MM] shall owe no greater obligations or liabilities under this Agreement than it owes to the Developer under the terms of the Appointment”
“Upon and subject to the Conditions and, where so stated in Appendix, upon and subject to the Supplementary Provisions issued February 1988 which modify the aforesaid Conditions, the Contractor will, for the consideration mentioned in Article 2, both complete the design for the Works and carry out and complete the construction of the Works.”
“2.5.1 The Contractor warrants to the Employer that: 2.5.1.1 The Contractor is a qualified, skilled and professional Design and Build Contractor, experienced in carrying out projects of a similar type, nature, scope and complexity to the Works; 2.5.1.2 The Contractor will execute the design and construction of the Works in accordance with good industry practice and in accordance with the Health and Safety Plan; … 2.5.1.4 Each Section and the Works will with effect from its date of practical completion comply with and satisfy the Employer’s Requirements, the Agreements, the Lease, the Development Control Requirements and the Statutory Requirements; and 2.5.1.5 The Works shall, once completed, in all respects be suitable and fit for the purpose for which they are intended as indicated in the Employer’s Requirements or for any other purpose which might reasonably be inferred from the Employer’s Requirements.” 2.5.1.1 The Contractor is a qualified, skilled and professional Design and Build Contractor, experienced in carrying out projects of a similar type, nature, scope and complexity to the Works; 2.5.1.2 The Contractor will execute the design and construction of the Works in accordance with good industry practice and in accordance with the Health and Safety Plan; … 2.5.1.4 Each Section and the Works will with effect from its date of practical completion comply with and satisfy the Employer’s Requirements, the Agreements, the Lease, the Development Control Requirements and the Statutory Requirements; and 2.5.1.5 The Works shall, once completed, in all respects be suitable and fit for the purpose for which they are intended as indicated in the Employer’s Requirements or for any other purpose which might reasonably be inferred from the Employer’s Requirements.”
“19.1 Where requested by the Employer, at the time of entering into this Contract the Contractor shall enter into a Novation Agreement in terms of the draft Novation Agreement reproduced in Appendix 7 hereto with the Employer and each of the following Consultants: … 19.1.2 The Project Civil and Structural Engineers – Mott Macdonald Ltd … which said Consultants comprised the existing Design Team (the ‘Design Team’) for the Project … 19.3 The Contractor acknowledges and accepts full responsibility for the work and performance of the services of the members of the Design Team and for any negligence, omission or default on the part of the Design Team or any of them (whether before or after the date of Novation or the date of execution of this Contract) and for the accuracy and adequacy of any design and/or services undertaken and provided by them irrespective of when such design and services are or were carried out by them.”
“For the avoidance of doubt, the following items shall comprise the minimum retractable content of the Contractor’s Proposals:- … (f) Mott Macdonald’s Structural Engineer’s Detailed Specification (g) Mott Macdonald’s Highways Detailed Specification (h) Mott Macdonald’s M&E Services Detailed Specification…”
“The principles as discussed at the meeting6 October 1999 were reviewed, i.e. both parties marked up a set of drawings showing the assessment in either percentage or tonnage for the areas which had not been fully designed and that [Rowen] had taken these assessments on board in agreeing an all encompassing figure for the package.”
“The Sub-Contractor will supply – All necessary competent staff, supervision, labour, plant, small tools, fuels, materials and fixings, To Design and prepare fabrication and working drawings to fabricate, assemble, supply, deliver, distribute and fix into final position, The … Structural Steelwork Pre-Cast Concrete (excluding Residential) and Metal Deck Flooring and Pre-Cast Concrete Staircases and Auditoria Terracing and supply only of loose steelwork to the Residential only, All – Executed in strict compliance and in accordance with all prevailing and relevant British standards, European Community Regulations, codes of practice, manufacturers’ recommendations and instructions.”
“Original bid based on Engineer’s Design – Final scheme to be Sub-Contract Design.”
“The Sub-Contractor’s rates and prices are deemed to have been based upon the information issued to MCL at tender stage by the Clients, i.e. preliminaries, specifications, preambles etc, and the Sub-Contractor has been given the opportunity to view these documents or they are otherwise incorporated into the sub-contract enquiry.”
“Guaranteed Maximum Price, incorporating rates and prices abstracted from Rowen Structures tenders and correspondence dated 06/10/99, 13/10/99, 14/10/99 (cost 2), 27/10/99, 29/10/99, 15/11/99 and 17/11/99, all as the appended Sub-Contract Sum Analysis [blank]£7,600,000.00 .”
“The above is a Guaranteed Maximum Lump Sum Price for the Design and (subject always to MCL approval), Fabrication, Supply and Installation of the Structural Steelwork, Pre-Cast Concrete (excluding Residential) and Metal Deck Flooring, Pre-Cast Concrete Staircases and Pre-Cast Concrete Auditoria Terracing together with the Supply only of the loose Steelwork to the Residential Units all as detailed on the drawings listed on the appended schedule, excluding any steelwork to the glazed support … The foregoing rates and prices, incorporating where applicable reductions for lump sum and average savings, will be utilised for the purpose of measuring and evaluating the scheme upon completion of the Sub-Contractor’s design and value engineering exercises. Those items of value engineering already identified as savings are at the Sub-Contractor’s risk with no adjustment for the Guaranteed Maximum Lump Sum Price in the event of those savings not being realised. In the event of any value engineering savings arising over the identified£1.31 Million (noted * thus), the initial£100,000 will remain with the Sub-Contractor to fund the design costs and the remainder will be shared on a 50/50 basis between the Sub-Contractor and the Morrison Construction Group. Any further value engineering savings realised other than those previously identified will be shared on a 50/50 basis, as before.”
“1.1 Design Warranty 1.1.1 The sub-contractor warrants to have exercised, and to exercise, all reasonable skill and care in: the design of the sub-contract works in so far as the sub-contract works have been, or will be, designed by or on behalf of the sub-contractor … The satisfaction of any performance specification or requirement in so far as such specification or performance requirement is included, or referred to or implied in the description of the sub-contract works included above or annexed hereto. 1.5 Co-ordination of Design 1.5.1 The sub-contractor shall ensure that his design is fully Co-ordinated and integrated with the design of the structure and/or other installations including products or components to be provided by the suppliers named in the tender documents.”
“Car park construction. I am keen to progress the decision as to the form of construction for the car park frame and slab. The following is the list of options that I understand are available, are there any that can/should be ruled out on engineering reasons? Options (1) Pre-cast concrete frame and slabs. (2) Composite 1: steel frame and PC slabs. (3) Composite 2: concrete columns (could be either in situ or PC) steel beams with PC slabs. (4) In situ concrete frame with P.C slabs.”
“RE PERIMETER RETAINING WALL At Thursday meeting we were asked to prepare a method statement for the construction of the perimeter retaining wall. Attached for your comment/information is the construction sequence that I currently envisage. In order that we can talk to suppliers regarding the size/availability of props, can you please give me (order of) prop loads. [There was written in afterwards “350kN/m Service Load + 50%”] The sketch dimensions are based [sic] the section of wall along Tricorn House. If we can agree the various slopes/dimensions I will prepare a method statement before we meet on Weds. Martin requested that your section and our method statement are issued to Bucknalls so that they can issue the party wall notices on Friday 5th. It may be that the piles are levelled and will need to be constructed before the upper props can be removed, but I would like the piles to be designed so that only Level 3 is required.”
“Broadway Plaza – Basement Car-park. Further to telephone conversation this morning, the prop forces in compression that the car-park slab must carry is as follows: (i) At 151.750 level the force (unfactored service load) is 180kN/m run of wall. (ii) At 148.750 level the force (unfactored service load) is 300kN/m run of wall.”
“Plaza deck will prop pile wall – therefore no requirement for additional cols and bracing.”
“(d) the plaza level cinema slabs are generally 225 thick composite slabs reinforced with 15kg per Metre Square of reinforcement … (f) the internal areas of plaza slabs other than the cinema i.e. restaurants, retail, bowling alley etc are generally 225 thick composite slabs reinforced with a 10kg per Metre Square of reinforcements. The designs of these areas are not as progressed as the cinema areas at this stage and special provisions may be necessary over the service yard areas.”
“With reference to the above project, it is our intention, as stated in the last project meeting, to complete a fully detailed costs plan by the end of March 1999. This will enable us to undertake cost checks against the base scheme and negotiate with Morrison Construction from a position of strength. In order to complete this we will require by March 19th 1999 draft specifications and structural schemes for all areas of the development and any further design development undertaken on the cinema and car park …”
“Please find attached an amended copy of our Project Strategy and Bid Programme together with an expanded Schedule of Tender Information. We have indicated in more detail the form in which we wish to receive the information. We will be pleased to receive any steelwork quantities that you have already estimated or your estimates for minor steelwork not yet detailed. Rebar quantities can be expressed as Kgs/M³ with an indication of diameters required …”
“This document has been prepared for the titled project or named part thereof and should not be relied upon or used for any other project without an independent check being carried out as to its suitability and prior written authority of Mott MacDonald being obtained. Mott MacDonald accepts no responsibility or liability for the consequences of this document being used for a purpose other than the purposes for which it was commissioned. Any person using or relying on the document for such other purpose agrees, and will by such use or reliance be taken to confirm this agreement, to indemnify Mott MacDonald for all loss or damage resulting therefrom. Mott MacDonald accepts no liability for this document to any person other than the person by whom it was commissioned.”
“G10 Structural Steel Framing To be read with Preliminaries/General Conditions and the latest edition of the National Structural Steelwork Specification for Building Construction. GENERAL REQUIREMENTS/INFORMATION 111 DESIGN: - The structural steelwork shown on the drawings and described in this specification has been designed to BS5950 where applicable, unless otherwise stated. - Complete the design and detailing of member sizes and connections to BS5950 to satisfy loading requirements specified or otherwise calculable from the information given … The following design parameters have been assumed: - Car-park imposed load Qk = 2.5kN/m² (UDL) and Qk = 4.0kN Concentrated load - Plaza imposed load: - Qk = 10.0kN/m² (UDL) and Qk = 10.0kN Concentrated load. - Floor slab to act as permanent props to embedded retaining walls. - Floor slab to act as diaphragm for stability of structures above… - Floor plates are folded and sloping, design means cranked as necessary …”
“ - The floor slab shall be designed to carry the prop forces from the retaining wall as indicated by the piling contractor. In no case shall these be less than: - At 151.750 level 180kN/m run of wall (unfactored service load). - At 148.750 level 300 kN/m run of wall (unfactored service load).” - At 151.750 level 180kN/m run of wall (unfactored service load). - At 148.750 level 300 kN/m run of wall (unfactored service load).”
“Further to yesterday’s meeting, please find list of queries for pile wall-contractors, before pre-contract meeting on24 May 1999 . They are as follows: … (iii) Please provide indicative prop forces and prop stiffness assumed in the design for temporary and permanent conditions?… (vi) Are the piles provided with the starter bars for connecting into the basement and car park slabs …”
“Tender submissions had been received in respect of the first stage information. It was confirmed that Rowans would be brought on board as initial partners on the basis of their offer to work up the design with Mott MacDonald for a six-week period until the end of September. At this stage, Rowans were prepared to re-negotiate a tender figure or if we are unable to agree terms with them, time will allow to resubmit full tender submissions to the market. This therefore gives us the benefit of the design sub-contract input at nil cost and the option to re-approach the market if it is felt appropriate.”
“Preliminary info issued to Severfield-Rowen and tender process ongoing. All specifications outstanding and overdue and steel design for above plaza level (excluding cinema) also outstanding.”
“In the car park there were to be 140mm slabs with steel decks. Meanwhile in the retail area and crescent the slabs were to be 175mm thick with steel decks. In the area of the cinema, floors were to be 255mm thick with concrete and steel decking.”
“[Mr Byrne] queried the design responsibilities of the team. PE explained that MM were producing the base design in close liaison with [Rowen] (to achieve best value engineering solution) and [Rowen] were detailing final connections.”
“This document should not be relied on or used in circumstances other than those for which it was originally prepared and for which Mott MacDonald Ltd was commissioned. Mott MacDonald accepts no responsibility for this document to any party other than the person by whom it was commissioned.”
“A meeting was to be held at MCL/[BA]/Mott/Rowans to review Rowan’s progress. It was confirmed that insufficient information was available from Mott MacDonald and it was confirmed that all outstanding information would be with Rowans by 24th September. Rowans agreed to consider and submit a price by 6th October. It was confirmed irrespective that a single tender action would be run with Rowans.”
“Risk Assessments from Designers still outstanding. All to note that these are to be with Morrison Construction urgently.”
“That the Design Team would probably not be novated to MCL prior to the end of October but for all intents and purposes had been under Morrison Construction’s control for several weeks.”
“Mott MacDonalds had fallen behind in respect of information required for Steelwork Tender. Mott MacDonalds were therefore not attending the meeting and Tim Dawson, Sonny Lee please note that this issue must be addressed urgently …”
“14. Any horizontal loads into steelwork from perimeter retaining wall.”
“Sonny to advise (100kN/m …) planks X in situ √ Get load into col grids.”
“Conservative 50% or less in final.”
“NOT APPLICABLE TO STEEL PRICE.”
“All steps (difference in levels) been accounted for ie grid W56/VB see drawing on elevation on drawing DWG167 (ie double support beams).”
“Despite previous assurances from MMcD at the meeting held on 06/10/99 Severfield-Rowen were only in possession of approx 85-90% of the info to allow a fixed bid to be submitted - as a result, they will now submit a GMP bid for the steel structure only on 12/10/99 – PCC figures to follow by 18/10/99.”
“Please supply accurate horizontal retaining wall loadings @ floor support locations.”
“(4) Following discussions with AP [of DLG] I confirm that the thickness of concrete slabs to the 154.00/155 level of the cinema given on RCS/203 is incorrect. Pls confirm what we need.”
“The floor slab in the retail and residential units will act as a prop along the full length of the capping beam of Wall 5 … It is assumed that the slab will have a stiffness of at least 50,000kN/m² and be capable of carrying a horizontal load of 60kN/m run of wall. The Engineer must confirm that the superstructure can accommodate these design requirements.”
“- Progressing detailed design and drawings for structural steelworks. - Appraisal, checking and amending latest cinema column layout by DLG and P. …”
“Design, Fabrication, Supply and Installation of Structural Steel Frame, Metal Deck and Pre-Cast Concrete Flooring and Pre-Cast Concrete Staircases and Auditoria Terracing”
“With reference our discussion Friday last26 November 1999 regarding design fees, client’s view of your design works to date is as follows: - Areas of the project were not designed initially these were highlighted during our meeting on 6th October to review the steelwork design. - As now proposed the detailed steel frame design will now be carried out by Severfield Rowen with your team’s input into co-ordination and checking rather than full design.”
“Object To familiarise Severfield Rowen of all the issues that will affect the final detailed design of the steel frame. Rowen has 13 weeks in which to design and fabricate the steelwork for the first area of work. No minutes will be taken.”
“Further to your fax of 27.11.99 response is as follows:- Item 5. I will copy the full Amec/Gibb pile designs and forward to you 1/12/99 (Walls 6, 1, 2, 3, 4 and 5 first) MM will not provide any information … Item 17. MM to provide by end 3/12/99.”
“To be reply [sic] later.”
“Could you please help me by giving a schedule of the forces to be carried on each floor for each of the different wall and height/support conditions. I want to be sure that our structure is being designed to carry the correct forces (I accept that the pile calcs contained this info but it is not easy to find). If it helps a list of where the correct info can be found, will at least task me to the right pages …”
“BROADWAY PLAZA – Structural Steelwork Horizontal forces from the embedded piled wall. We refer to your fax of8 December 1999 , we confirm that the horizontal forces from the embedded piled walls will be transferred by the car-park slabs to the piled wall at both ends. The car-park slabs will act as a diaphragm to transfer this force and the end piled walls will act as shear walls. The forces from the pile wall will be transferred to the car-park slabs in direct bearing and dowels will be provided to transfer the shear forces from car-park slabs to the end pile walls.”
“17. Sonny Fax 10/12 – slab at Plaza/screed at -1, - 2.”
“We refer to your fax of8 December 1999 , we confirm that the horizontal forces from the embedded piled walls will be transferred by the car-park slabs to the piled wall at both ends. The car-park screeds at - 1 and - 2 and the slab at plaza level will act as a diaphragm to transfer this force and the end piled walls will act as shear walls. The forces from the pile wall will be transferred to the car-park slabs in direct bearing, and dowels will be provided to transfer the shear forces from car-park slab to the end piled walls.”
“Are the forces from the propped retaining wall to be taken out in steelwork bracing or do they disappear somehow?”
“(17) The retaining wall propping forces will go directly into/out of the structural screed and we do not need to concern ourselves with this as it is to remain Mott’s problem.”
“(2) I understand your thinking on the thermal break under the cavity but if this is a problem structurally as the slab needs to take horiz [ontal] forces from the pile wall then we will have to assess the likely effect.”
“2. Joints not possible slab needs to transfer prop forces. (Permanent case).”
“Judge: But during this period, really looking at the six months leading up to the signing of your contract which is late January 2000 -- A. Yes. Judge: -- I think you said you were expecting MCL to novate direct with Mott? A. Mott to novate to us, yes. Judge: Yes, whichever way round. A. Yes. Judge: And did you actually in this period think about what would happen if Motts got things wrong? Were you thinking in terms: well, if things really go wrong here, we will always be able to sue Motts because we will be getting a novation? You may not have thought of it as bluntly as that. A. No, no. Judge: But in terms of responsibility we have a come back against Motts "because we will be getting a novation". A. The normal contractual relationship, yes. Judge: And so were you therefore really relying on your assumption that there would be a novation? A. I was relying on that things would carry on as they normally do under other contracts, so yes, I think I have to say yes.”
“8. Check levels on plaza for strutting - Most important.”
“Subject: Lateral Loads to Plaza Slab Please Supply/Clarify the Following: The floor slabs in the car park and at plaza levels are generally used to prop the retaining walls, as specified in Clause G10/111 of the Specification of the Structural Steelwork. Could you please provide your calculations, in accordance with this clause, to demonstrate that the floor construction satisfies the loadings given?”
“Responsibilities: Rowen’s (stick Motts) - start r/wall Motts: - Rowen’s: MG/AC – horizontal load transfer to r/wall thro floor plate whose [sic] is responsible. Have Rowen’s taken it thro steel frame at plaza level: Rowen’s spec passed to Motts: … - Load onto steel is not been [sic] discussed as Rowen’s responsibility: deck – Motts overseeing the steel-floor plates Motts overseeing calcs: - Motts discuss internal RTRS [Mr Saunders] needs a view tomorrow steel/floor plate load transfer – discuss with Rowen’s tomorrow: - way order was placed?”
“Responsibility for the design of the floor plates to transfer the horizontal forces from the piled retaining walls has not been removed from Mott MacDonald. Sonny Lee has previously confirmed that the p.c. floor and structural screed/in situ slab at Plaza level can transfer the forces.”
“It was always clearly understood and was confirmed in the attached fax from Sonny that all loads from the pile walls would be transferred by the screed or slab (at Plaza) as RSC (Rowen) are not contracted to supply the screed or in situ concrete design of the screed must fall with others.”
“I am disappointed that in spite of the discussions that took place yesterday you felt it necessary to ignore all that was said by both myself and Sonny Lee and issue TQ014. When the Steelwork Spec was issued, Mott MacDonald had full design responsibility for the steel frame and floors. The steelworks subcontractor was to be responsible for the design of connection. In order to achieve cost savings it was agreed, including with Mott MacDonald, that Rowen’s design would be enlarged to include the design of steel members. Responsibility for the design criterion and the transfer of the horizontal forces for the piled wall remains with Mott MacDonald. Clause G10/111 of the Tender Specification should not be taken out of context “complete the design …” was at the time limited to connections and a review of the RHS columns.”
“7. Check propping/permanent to retaining walls.”
“Further to our previous discussion, Mott MacDonald still have not resolved their diaphragm problem, we are still continuing in line with the original brief.”
“6. Plaza deck horizontal forces MM meeting 17-3-00. MG [Mr Gidwani] to give the results of this meeting by 22nd.”
‘“Framing + bracing” with action by Rowen.’
“In order to accommodate the horizontal thrust at Plaza deck level, either additional steelworks 50-60 tonnes would be required or a revised concrete design, the area effected by cinema area. The responsibility for the works is debatable i.e. Rowens believe Mott MacDonald took on responsibility in thro concrete structure and Mott MacDonalds believe Rowen should have designed.”
“13. Plaza level Rowen to look at diagonal steelwork grillage for balance horizontal forces.”
“Further to our discussions, we enclose approximate estimated loadings for Walls 4 and 5 acting on the proposed steel supports at the 153.5 approx level. These loadings ideally need to be confirmed by Amec Piling/Gibb Ltd who also need to confirm that the walls were cantilever as discussed and we presume Roger Saunders will be asking them to do this shortly.”
“4. MCL Decisions Made Horizontal forces from the piled walls 4 and 5, this will result in extra steel and likely extra cost.”
“Re Propping of Pile Walls Further to our discussions on Thursday regarding the propping of the piled wall at the junction of walls 4 and 5, I confirm accepting the need for an additional area of steel to brace the corner at 153.5 level. Also as discussed, I believe that the propping forces from the length of wall 4 from VL to VF need to be taken through the Plaza deck slab in order to keep to a minimum the extent of the additional 153.5 seal.”
“Further to the meeting on23rd March 2000 , with regard to ourselves undertaking the design of additional steelwork to transfer the loads from retaining wall 4 to retaining wall 5 at approximately plaza level. We view this as an addition to our scope of work. At all times until the arrival of Maurice Gidwani, Mott MacDonald confirmed in writing that the plaza level slab took the retaining wall load. We also referenced the contract steelwork specification, which states “The floor slab shall be designed to carry the prop forces from the retaining walls”
“3. RS has instructed Rowen only to buttress the corner of Francis Road. He is looking for further justification of diaphragm action on remainder. RS wants this demonstrated.”
“10. Plaza Deck Forces Option 1 – additional steelworks to fill in between Option 2 – stiffen pile wall Option 3 – redesign steelwork to take forces.”
“14. Plaza level bracing Three choices (a) Steel bracing to firm Plaza deck (b) Try to cantilever the wall (c) Take the force in the brace. Asked to look at framing bracing too.”
“As you are aware, following last Thursday’s design team meeting, the decision was taken to pursue a steelwork solution to accommodate the prop forces at Plaza deck level; this after Maurice Gidwani had confirmed that he was unable to design the floor slabs to comply with your specification. I would reiterate my extreme concern and disappointment that I am presented with this fait accompli at a relatively late stage in the design development process and would confirm that Morrison Construction now face significant costs from Rowen, Parkstone and programme implications which will in all probability delay a number, if not all, of the handover dates. On Thursday I requested that Mott MacDonald carry out the basic design of the steelwork noted in the opening paragraph, with the agreed design novated to Rowen thereafter for warranty purposes: please be advised that I require the Scope of this design to be extended to include the prop, currently being addressed by Rowens, that transfers the wall 4 loads between VL and VF to ensure a sympathetic and homogenous design of all below – plaza steelwork required to replace the slab properties …”
“One of the first tasks undertaken by TC was to determine all levels at the Plaza level. It was this exercise that identified that no diaphragm action would be possible for lateral load transfer. This resulted in a complete re-design by…MM”
“… full responsibility for the work and performance of the services of the members of the Design Team and for any negligence, omission or default on the part of the Design Team or any of them (whether before or after the date of Novation or the date of execution of this Contract) and for the accuracy and adequacy of any design and/or services undertaken and provided by them irrespective of when such design and services are or were carried out by them.” in circumstances in which MCL knew that it had not reached agreement with MM about the novation again points strongly to there being no effective reliance. (k) The only reliance in the period leading up the MCL/MPS contract was MCL’s assumption that there would be a novation with MM and that it would be through that route that any responsibility of MM would be resolved. (l) At Paragraph 222 of its written Closing Submissions, MCL asserts 4 areas of pre-contract reliance: “MCL acted in reliance upon Mott’s advice: (1) In tendering for the design and build contract on the basis of Mott’s design concept for dealing with the horizontal loads at Plaza level; (2) In inviting tenders for the piling and steelwork subcontracts on the basis of Mott’s design concept for dealing with the horizontal loads at Plaza level; (3) By assuming responsibility under the Design and Build Contract on the basis of that Mott’s design concept was feasible and its advice and statements were correct; (4) By not including any cost or programme allowance for the steelwork to take the horizontal loads from the retaining walls”
“A. Main and Subcontractor cost limits. Advise Morrison Construction that any design development is likely to affect the costs of the works compared with the design contained within the contractor’s proposals.”
“A man cannot be said voluntarily to be undertaking a responsibility if at the very moment when he is said to be accepting it he declares that in fact he is not”
“Commissioning means ordering. In this context it means more than requesting or encouraging. It connotes an obligation to pay.”
“They are part of the material from which one deduces whether a duty of care and a liability for negligence was assumed. If both parties say expressly (in a case where neither is deliberately taking advantage of the other) that there shall be no liability, I do not find it possible to say that a liability was assumed.”
“In the case of other loss and damage [other than death and personal injury], a person cannot so exclude or restrict his liability for negligence except in so far as the term or notice satisfies the requirement of reasonableness.”
“On26 February 1999 …….. [Mr Lee] explained that the [Mott] design philosophy was that the car park floors were to be used to act as horizontal props to the pile wall, with the Plaza level slab acting as the upper prop and the middle and lower car park floors propping the middle points of the piles. This was to be achieved by allowing the horizontal force from one pile wall to counteract and balance the horizontal force from the opposite pile wall (and vice versa) which concept was described as “diaphragm action”…………. My note of that discussion specifically records that, "Plaza deck will prop pile wall [therefore] no requirement for additional [columns] and bracing".” (ii) I have made findings above (at Paragraph 200) about this meeting: “On26 February 1999 , Mr Lee of MM mentioned to Mr Saunders at an un-minuted and informal meeting that the plaza deck would prop the piled walls”. (iii) I do not see that this was or amounted to advice being given to MCL at this early stage when it was not absolutely clear to MM what role MCL was performing at that stage and whether it was other than being one part of the design team. It was an informal discussion. MM simply told MCL what its thought process at that stage was. The advice was not negligent in any event. There was nothing wrong in principle in the Plaza deck propping the piled retaining walls; at that stage, there was no indication that the prop forces would be taken in the concrete as opposed to the steel. (iv) There was no reliance or continuing reliance as a matter of fact by MCL on this informal discussion. (b) Representation 2 (i) This relates to the contents of MM’s Steelwork Specification produced in April and revised, immaterially so far as this case is concerned, in August 1999. (ii) I do not consider that this was relied upon by MCL. It was not given to Rowen. That may have been an oversight or deliberate on the part of MCL; if deliberate, that is proof positive that it was not being relied upon by MCL. If it was an oversight, that demonstrates a “couldn’t care less” attitude and a lack of reliance. The history up to21 December 1999 demonstrates that there was no continuing reliance. (iii) Whilst Mr Lee accepted in evidence that the Specification demonstrates a design philosophy which is that the prop forces were to be taken by or within the concrete part of the deck, the designer at that stage (MM) was recognising that the floors were or were likely to be a composite structure with the steel part of the flooring acting compositely or together with the concrete part of the floor; put another way, if the concrete moved under the prop forces, the steelwork would also move with it. The fact that Mr Lee believed that “slab” meant the concrete part of the floor is not necessarily determinative as to what it means as a matter of interpretation; it is probably unnecessary to determine what it does mean because MCL did not pass it on to Rowen at least before it entered in to its sub-contract with Rowen. (iv) I am not satisfied on a balance of probabilities that the Specification was negligently drawn up. It was prepared before the drawings referred to in it were drawn up-the drawings were to arrive in September and October 1999. It did not specify that the steelwork would, should or could not be designed to take into account the prop forces where necessary. Indeed, Clause 111 states that the steelwork sub-contractor should: “Complete the design and detailing of member sizes and connections to BS5950 to satisfy loading requirements specified or otherwise calculable from the information given …” (v) Although only the loading requirements for the car park floors were given in the Specification, the obligation to be imposed on the sub-contractor does require it to take into account prop forces which will sooner or later be calculable. If and to the extent that it was unavoidable that prop forces could not be taken solely by the concrete part of the slab, the steel work would have to be designed to take them. The reality was that at this stage up to August 1999 MM had not worked out precisely how the prop forces were to be accommodated in the Plaza deck and that is why the prop forces specified related only to the two lower floors. (c) Representation 3 (i) This is summarised in MCL’s Closing Submissions at Paragraph 52: “A meeting attended by, inter alios, MCL and Mott was held on17th May 1999 to discuss the piling tenders. Lee of Mott explained how the plaza floor was also to act as a prop. As Saunders recorded in his diary (C3/277) and accepted by Lee (T9/92): “Plaza deck will use friction along pile wall 4 and 5 to resist thrust from adjacent wall - deck to act as diaphragm.”” (ii) Again, this was an informal meeting. I do not accept that there was any reliance by MCL upon what was said by Mr Lee. Matters were still at an early stage; it was well before the time when any bid was due in from MCL. Mr Lee was not advising MCL but simply informing MCL what MM current thought process was. The history up to21 December 1999 demonstrates that there was no continuing reliance. (iii) I do not consider that what was said was negligent as such. There was nothing wrong for the Plaza deck to use friction along pile walls 4 and 5 to resist thrust from the adjacent wall or for it to act as diaphragm. Mr Lee was not saying that the steelwork, as yet largely not designed by MM, would not have to be used to accommodate these forces. (d) Representation 4 (i) This is set out in paragraph 61 of the Closing Submissions: “On 6th July MCL and Mott went to Birmingham City Council’s Building Control Section. This was the body chosen to check the design for compliance with Building Regulations. The submission, at that stage, was limited to the piling design. Richard Culliford of Building Control wanted to understand how the pile walls would be propped. Lee said that the piles would be permanently propped by the completed structure and drew a sketch of the plaza level to show how the frictional forces were transferred from wall 4 to 5 and vice versa without the need for steel bracing. (F [26]/ paragraphs 97 and 98 and admitted by Lee at T9/94) A reproduction of that sketch is to be found at F/312B. (Confirmed by Lee to be accurate T9/95)”. (ii) Mr Saunders’ handwritten notes of the meeting (E1/375-6) do not even mention Mr Lee being present and do not record the advice which it is said was relied upon by MCL. This was an informal meeting. Mr Lee was cross-examined by Mr Furst QC for MCL on this on Day 9: “Q. As part of those discussions you had with Richard Culliford, who was the gentleman from building control, you said that the piles will be permanently propped by the completed structure and you drew a sketch of the plaza level to show how the frictional forces would ensure that the force from wall 4 was transferred diagonally to wall 5 and vice versa, without the requirement for steel bracing; is that correct? A. Yeah, at this meeting, the purpose of the meeting which I attended with Mr Saunders and Alastair -- sorry, Mr Patterson, the sole purpose is for Mr Patterson to discuss the height of the building and also for Mr Saunders to discuss the idea of -- I believe it's to use the long wall 4, which is the wall along Francis Road, and yes, there is a very brief discussion of the permanent props of the wall, yes. Q. And I think you've got attached to your statement at page 312B, a little diagram? A. That's right. Q. Which, just to be clear, I don't think is the diagram from the meeting itself, A. No. Q. It's a diagram I think you produced, is that right? A. No. Q. Sorry, Mr Saunders has produced -- A. That's correct. Q. -- as to what he says you provided at that meeting? A. Yes. Q. And of course the question I want to ask you: Is it accurate, as far as you can recall? A. Yes”
“Accordingly Lee’s failure to even refer to the need for the loads to go into the steelwork constituted, in the all the circumstances, a further representation that the steelwork was not required to perform that function, although it remained open to Lee to correct that representation by answering the queries raised”. (ii) If there is no overriding duty of care of the “akin to contract” or services requested and provided type, this sort of plea is much more difficult to maintain, as a complaint of omission to advise pre-supposes a duty to advise positively which does not exist in this case. It is of course possible to make a Hedley Byrne type statement which is negligent and wrong because it is not in any way qualified. (iii) I refer to my findings at Paragraphs 229-233above. Nothing was said by Mr Lee at that meeting about the Plaza deck in the context of how prop forces were to be accommodated or the steps or changes in level were to be addressed. What was said by him related to the lower car park floors and was not negligent. It seems to be accepted by all experts (and it is not suggested otherwise) that the design of the lower floors so far as prop forces and otherwise was unexceptionable. (iv) I am satisfied that there was no material or indeed any reliance upon what was said by Mr Lee at this meeting in relation to prop forces specifically in the context of the Plaza deck. The very fact that Rowen on its own account and through MCL needed to ask the questions which they did in late November and December 1999 about the horizontal forces proves to my satisfaction that nothing was said or done by MM in October 1999 which was relied upon in that context by them. (g) Representation 7 (i) This is said to arise out of the letter dated8 October 1999 from MM to MCL relating to tonnages allowances for the step areas of the Plaza deck. My findings at Paragraph 239above are: “I do not consider that Mr Lee in reality accepted that he had not made any allowance for propping or diagonal strutting at the points where there were split levels at the plaza level. It is clear that the design was incomplete in these areas. It is my view, and I find, that Mr Lee simply made some unattributed allowances for additional steelwork to accommodate loads and stresses at the changes in level. Put another way, he made a stab at what he thought might be required in that area. It was certainly not an allowance which was calculated in any detail at all.” (ii) This “representation” was the subject matter of a very late amendment application by MCL after in effect its Counsels’ final speeches. I allowed the amendment offering MM the opportunity to recall any witness they wished; the offer was not taken up. (iii) For similar reasons given above in relation to Representation 6, I do not consider that there was any real reliance upon this. It was simply a tonnage allowance for the areas in question, given because, as everyone knew, MM’s design was incomplete in those areas. (iv) I am not satisfied that it was in any event a negligent allowance for the steelwork in those areas. It may have been an under-estimate but I do not find that if it was such an under-estimate it was negligent. (v) In any event, there was no effective reliance by Rowen or MCL on it because Rowen had not had an answer to General query 14 as raised at the 6 October meeting in relation to the Plaza deck level. This is corroborated by Rowen’s need to ask the questions which it did in November and December 1999. (h) Representation 8 (i) Representation 8 is said to have been made at the un-minuted design workshop meeting of25 November 1999 . It is put in these terms by MCL’s Counsel in closing at Paragraph126: “This meeting gives rise to Representation (8) in essence for the same reasons as arise in relation to the 6th October meeting. In short Lee’s failure to even refer to the need for the loads to go into the steelwork constituted, in the all the circumstances, a further representation that the steelwork was not required to perform that function, although it remained open to Lee to correct that representation by answering the queries raised.” (ii) There was no positive representation and there was no reliance; that is confirmed by the queries raised about prop forces by Rowen over the following 3-4 weeks. (iii) Again, it is difficult to blame MM for failing to advise someone who was not their client if there was no tortious duty of the “akin to contract” or “services supplied” type. I consider that it was clear to all at the meeting that MM was unable to or did not address the issue as to how loads were to be accommodated in the steelwork, if at all. As Mr Harper said, the issue remained to be decided. In those circumstances, it is impossible to say on a balance of probabilities that MCL relied upon MM’s silence at this meeting as meaning that the steelwork was not required to perform the function of accommodating the prop forces. (i) Representation 9 (i) This is, in my view, the strongest of the assertions made by MCL as to a Hedley Byrne statement. It is summarised at Paragraph 150 of MCL’s Counsels’ Closing Submissions: “Accordingly the conversation on 10th December (as passed to MCL in Mott’s fax of 10th December, C6/482) and the further conversation on 16th December (as confirmed in Rowen’s fax of 21st December, C7/50) constituted Representation (9) to the effect that (a) the horizontal loads from the retaining wall would be taken in diaphragm action at plaza level and (b) by necessary inference, would not need to be taken in the steelwork.” (ii) I address this part of the history at Paragraphs 257-264above. It is necessary to read what Mr Lee orally agreed to, as confirmed in the fax of21 December 1999 , which in essence was: “The car-park screeds at - 1 and - 2 and the slab at plaza level will act as a diaphragm to transfer this force and the end piled walls will act as shear walls.”
“[The fax] simply described the plaza slab acting as a diaphragm to transfer the prop force from the piled walls at plaza deck level, but did not confirm that the steelwork would not be required to resist any part of these forces”
“Q. We'll come back to that. At 7.21, you say: "Mott's fax of10th December 1999 ... (reading to the words)... resist any part of these forces." Since you wrote that, of course, you've heard and read much more evidence. When you use the word "ambiguous", were you referring to the wording of the faxes themselves or what were you referring to? A. I mean the conclusions that were drawn or that could have been drawn from it. If I could explain and take that in sections --Mott's fax is 10th December. That didn't mention the plaza deck, so it didn't help with the design philosophy for the structure as a whole, or particularly the plaza deck. Judge: It's not ambiguous; it's incomplete. A. It's incomplete ... A. And the second document, the Rowen fax of 21st December, which, as I understand the position, amended Mott's fax of 10th December, and referred to the slab at plaza deck level acting as a diaphragm. I think an engineer would understand what that meant, but also would look at the plaza deck itself and wonder to himself how on earth does that work. It might be helpful to refer to a drawing that I produced, in fact the drawing that you had just handed to you recently. Mr Furst: Do you have the large version of it? A. I have the large version of it. What I mean by that is the idea that this slab will act as a diaphragm, transferring the forces from here to here. The principle of a diaphragm is that it's in plane, it has to be in plane. And yet you have this substantial step here. So somehow the forces have got to go from here in the concrete, let's ignore that step for a moment, past here and somehow get into the steel, because there's no concrete there, jump up and then get transferred to the other wall in the concrete. I think an engineer looking at that will think: how is that going to work? And that, I'm sure, would have prompted a lot of discussion. Mr Furst: Would have or should have? A. Should have.” (vi) He confirmed in this context (T14/53) that Rowen should have been aware of the “obvious detail” that at Plaza deck level there were steps or changes in level, that the steelwork at those points would have to take some of the prop forces and that this had to be overcome unless it was told that it did not have to deal with it. At T14/56, he said: “Q. And any specialist subcontractor assuming responsibility for the design of the steelwork would have realised that, because of the step, prop forces could not be taken just into concrete it would also go into the steelwork? A. That's correct, unless they'd been informed to the contrary. Q. Then you go on and say: "Rowen sought and obtained further information ... during December 1999." Here I assume you're referring to that exchange of faxes? A. Yes. Q. "... which led them to conclude ...(reading to the words)... by Mott MacDonald at this level." That's an inference which you have not drawn from those faxes? A. It led them to conclude that, but the faxes I don't believe say that with a sufficient clarity. Q. Would you agree with me that if Rowen reached that conclusion they were in error? A. They certainly were in error.” (vii) There was some apparent qualification of this view by Mr Blois-Brooke following extensive cross-examination by Mr Sutherland for Rowen (which I had felt was skirting around what was a key point so far as any liability of Rowen was concerned). So I asked him at T15/45: “I mean, a lot of your [Counsel’s] questions are, possibly like this slab, a bit composite and it's a bit difficult to see -- let me put that question, Mr Blois-Brooke, to you. If it be the case I find that Rowen believed that they were being told in these faxes and conversations by Mott that the horizontal forces from the embedded piled walls were going to be transferred only into the concrete, was that an unreasonable assumption for them to make? A. Because they were the steelwork designer and not the designer with overall responsibility, I don't think it was unreasonable.”
"Tim Dawson: existing building visit + Ian Weardon [of MM] 9.30"
“The attached is our first thoughts on the refurb of the hospital. In principle most cross walls can be removed with fairly nominal extra structure. The chimney walls could also be removed. However we need to give some additional stiffness to the building. The two central corridor walls are load bearing. Therefore any major openings will need support lintels. If significant length is to be removed then new columns would have to be installed …”
“3.1 Site Clearance and Demolition … We have allowed a provisional sum of£50,000 for temporary works to support the existing Hospital building. The stability and condition of existing structure will need to be established to fully ascertain the costs associated with temporary support work. The costs to carry out such investigative surveys are included in the provisional sum. 4.2 Work to Retain Hospital. Cost Allowances 4.2.1£50K net for any work associated with the retention of the existing façade or structural work to the existing load-bearing walls to allow the existing floors to be retained whilst the existing rooms can be opened up/connected. 4.2.2£170K net for all work associated with the cleaning, restoration of the existing façade and windows, alterations to the existing façade and the revision of the glazed screens, any alteration to the stairs, the modifications to the structure for the two new lifts, the lowering of the existing ground floor, the removal of the existing roof coverings/chimney stacks and all modification to the existing roof top tank room.” 4.2.1£50K net for any work associated with the retention of the existing façade or structural work to the existing load-bearing walls to allow the existing floors to be retained whilst the existing rooms can be opened up/connected. 4.2.2£170K net for all work associated with the cleaning, restoration of the existing façade and windows, alterations to the existing façade and the revision of the glazed screens, any alteration to the stairs, the modifications to the structure for the two new lifts, the lowering of the existing ground floor, the removal of the existing roof coverings/chimney stacks and all modification to the existing roof top tank room.”
“MW [BA] confirmed that the extent of the temporary works and permanent works to the existing hospital building was still not finalised by the designers and that the provisional allowances made in both respective costs plans were of similar magnitude. It was agreed that the allowance should remain unchanged until more detailed information was available.”
“-detail design is on going with DLG+P and client’s tenant”
“I still need your thoughts on the need for any support to the existing Hospital building before/after the removal of the rear section.”
“5.1 The Healthlands scheme has been finally agreed and signed up. But the main General Arrangement drawings are being altered to incorporate the agreed scheme so that they can be issued and included as part of the bid. Mott Macdonald are looking at possible structural solutions to achieve the agreed arrangements.”
“I am most concerned, as reported to myself, that there is an inference that the original fee did not cover works required to the existing building and façade to Ladywood Middleway. The scope of the works was always known and included for these works. At the time we agreed the fee therefore there could have been no misunderstanding on the nature or extent of your duties and I trust the report I have received is no more than a misunderstanding between the scope of works agreed and the engineer actually carrying out the works.”
“One of the areas where we need to progress work is the existing hospital building. There are two main areas which need to be addressed. We need to make an assessment of the capacity of the existing, retained R.C. slabs, to determine their allowable loading capacities. Secondly, we need to assess the effects of the internal wall demolition, proposed by DLG. Some of the walls which it is proposed to remove are undoubtedly load bearing, and will require the introduction of new supporting structure. In order to make these assessments, we need to know three things. These are the strength of the concrete, the size, strength and arrangement of the reinforcement, and the conditions at the supports. Some intrusive testing is required. Samples of concrete (ideally cores), and reinforcement should be taken and tested. Concrete would have to be broken out locally, in a number of places to expose the reinforcement, in order to measure bar size. A cover meter survey is also recommended. Some breaking out at supports would be required to determine support conditions. Testing of brick samples would be useful, too. Before this work can commence, the structure must be made safe. Any areas where support has been removed must be temporarily propped until the assessment is complete. Safe access must be provided to all areas of the slab, at all levels. We would recommend that a specialist testing house is brought in to carry out the sampling and testing work. We would provide a specification/brief and an Engineer would attend during the site works... Bearing in mind the programme, you will appreciate that this work needs to be started as soon as possible …”
“Your letter of1 August 2000 asks for our initial views on the need to provide a retention scheme if the decision is made to refurbish the existing retained area of the hospital. As we discussed at our meeting on 26 July, assuming that the refurbishment is taken from the top down after foundation strengthening has been installed, the removal of the roof takes away the support to the front wall. It is very possible that the façade at the upper level will need restraining until the new roof structure is in place …”
"It is important to appreciate the true nature of the so-called 'duty to mitigate the loss' or 'duty to minimise the damage'. The claimant is not under any contractual obligation to adopt the cheaper method: if he wishes to adopt the more expensive method, he is at liberty to do so and by doing so he commits no wrong against the defendant or anyone else. The true meaning is that the claimant is not entitled to charge the defendant by way of damages with any greater sum than that which he reasonably needs to expend for the purpose of making good the loss. In short, he is fully entitled to be as extravagant as he pleases but not at the expense of the defendant."
“The earlier of (a) the date of disposal by the Employer (whether by its sale or transfer) of the whole (or the last remaining part) of its interest in the Commercial Development, (b) the date on which the First Employer Insolvency Event occurs and (c) the date at which any adjudication or court proceedings are first commenced pursuant to Article 5 of Article 6B of the Building Contract (as the case maybe).”
“Without prejudice to any present or future obligation or liability of the Contractor to pay or allow liquidated and ascertained damages under the Building Contract and subject to the Contractor complying with its obligations under this Agreement, in the period from the date of this Agreement until the Initial Payment Date the Employer agrees not to take steps to recover and/or deduct any of the liquidated and ascertained damages that are or become payable or allowable under the Building Contract.”
“…the sum of£6,814,000 being the aggregate of (a)£3,700,000 being the liquidated and ascertained damages set out in Clause 2.1.2 of this Agreement, (b)£2,200,000 being the liquidated and ascertained damages in respect of the period from16 July 2002 to16 May 2003 and (c)£914,000 being interest at the Lending Rate on the aforementioned sums of£3,700,000 and£2,200,000 in the period from1 January 2002 until the [Date of Disposal].”
‘The date occurring after the date of disposal (“Date of Disposal”) by the Employer (whether by sale or transfer) of the whole (or the last remaining part) of its interest in the Commercial Development, which date occurring after the Date of Disposal, shall be fixed solely by Group in its absolute discretion subject to at least three months’ prior written notice being given of the date to the Contractor.’
“(i) [AWG] … [MPS] and [MCL] have entered into, or the Seller shall procure that they will enter into within 10 days of this agreement, a final agreement, in the Agreed Terms in respect of the Broadway Plaza development settling all claims between them arising out of or in connection with the Broadway Plaza development, save for those recorded in the Final Agreement of the Broadway Plaza Minute of Agreement. (ii) AWG shall procure that MCL shall use all reasonable endeavours prior to Closing to settle the outstanding professional indemnity claim and the outstanding claims by and against Mott MacDonald Limited such that any such settlement results in an aggregate neutral or positive financial position for [MCL] in relation to such claims and any amounts which are due to [MCL] should be accounted for in the accounts for [MCL] in 2005/2006. (iii) To the extent that such claims are not settled prior to Closing, the Purchaser shall procure that [MCL] shall use all reasonable endeavours to settle the claims, provided that it will be a term of any such settlement that [MM] shall not pursue any claim arising out of or in connection with the Broadway Plaza development against a company in [the AWG group] … (iv) If the outstanding claims by and against [MM] in connection with the Broadway Plaza development are settled, whether prior to or subsequent to Closing, [AWG] shall procure that [MPS] and [AWG] enter into an agreement with [MCL] pursuant to which the rights available to [AWG, MPS] and any other member of [the AWG Group] under the Broadway Plaza Minute of Agreement, including the fixing of an Initial Payment Date and/or seeking payment of the Initial Payment, as defined in the Broadway Plaza Minute of Agreement, are extinguished, and any rights the aforementioned have to pursue claims against [MCL] in respect of the delay to the completion of the Broadway Plaza development, whether under the Broadway Plaza Minute of Agreement or otherwise, are waived. (v) In any event, notwithstanding any other provision of this agreement, for so long as [MCL] is a member of the [Galliford Try Group], [AWG] hereby agrees that it shall not (and shall procure that all members of [the AWG Group] shall not), save to the extent expressly directed in writing by [GTC] or any member of the [Galliford Try Group] which at that time is the direct holding company of MCL, exercise any rights available to it (or them) pursuant to the Broadway Plaza Minute of Agreement, including the fixing of an Initial Payment Date and/or seeking payment of the Initial Payment, as defined in the Broadway Plaza Minute of Agreement, or pursue claims against [MCL] in respect of the delay to the completion of the Broadway Plaza development, whether under the Broadway Plaza Minute of Agreement or otherwise. (vi) Notwithstanding any other provisions of this Agreement, if [GTC] or any other member of [Galliford Try Group] sells [MCL] to a third party, then the benefit of this clause … shall be assigned by [GTC] to the company which is the direct holding company of [MCL] such that the benefit of this clause …is always held by the direct holding company of [MCL].”
‘Next there are the storage charges … [Counsel] correctly summarised the final position by saying that the bargain was that the Russian sellers would only claim against the plaintiffs if the plaintiffs could recover those charges from the defendants in this action. [Counsel] argued that an arrangement of that kind barred the plaintiffs recovering in this action. For my part I am unable to see why. The plaintiffs have – and this was not contested – apart from any agreement with the Russian sellers, a perfectly good claim for these storage charges. Why the plaintiffs should not make an arrangement for their own sellers, “we will claim these and hand the proceeds over to you if we recover provided you let us off if we do not”, I am unable to see. Nor do I see why the existence of such an arrangement should afford the defendants a defence which they would not otherwise possess. It seems to me an eminently sensible commercial arrangement …’
‘I now turn to the wholly distinct question whether the motorists have proved that they had suffered a recoverable loss through the unavailability of their own cars pending repairs. The Defendants say that they have not, because the cars were replaced by substitute vehicles which the motorists were able to use free of charge. In essence, it is said that the motorists have mitigated what would otherwise have been a valid claim for general damages reflecting their loss of the opportunity to make use of their own vehicles. On the opinion which I have formed of the obligations created by the obscure and incomplete terms of the two agreements this contention admits of a very short answer. In my judgment the motorists do not obtain the replacing vehicle free of charge. If the motorist had simply persuaded a garage to hire her a substitute on credit, without any of the superstructure of the present transaction, it would be no answer to a claim for damages equivalent to the sums due to the garage that these sums would not in practice be paid until a judgment in the motorist’s favour had provided the necessary funds: for the amount of the outstanding liability represents the loss suffered by the motorist, and the question whether the motorist intends to apply the damages recovered in satisfaction of the debt, or in some wholly different way, cannot effect his right of recovery. To distinguish that case from the present the defendants are forced to contend that the consideration for the provision of the cars consisted solely of a right to recoup themselves from the damages for loss of use. As will have appeared, I do not accept this interpretation. The hiring company has no direct right to the damages. The company is not an assignee or chargee of the cause of action or its fruits, although it expects that the damages that loss of use will form part of the assets from which the motorist will in due course pay for the substitute. The liability for the car hire, although suspended as regards enforcement, rests upon the motorist throughout. It is a real liability, the incurring of which constitutes a real loss to the motorist. Whatever the publicity material may have conveyed, the provision of the substitute cars was not “free”.’
‘In Randall v Raper … the defendant (A) sold to the plaintiff (B) seed barley, warranting it to be of a particular quality but delivered seed barley of an inferior quality. Relying on the warranty, B had on-sold the seed barley with a similar warranty to sub-buyers (C). In the event C claimed from B compensation for the damage which C had suffered; B accepted that it was liable to C but had not paid C and, indeed, the amount of the compensation had not been ascertained. B now claimed from A damages in the amount of B’s liability to C … The judgment of Erle, J (at p.90) went directly to the point. “But then it is said that here the plaintiffs have made no actual payment; so that if they recovered such damages in this action, they might put them into their own pockets without paying the sub-vendees. But I think that the true rule is, that a liability to loss is sufficient to give the party liable a title to recover.” The views of Crompton, J. were to like effect (at pp. 90-1): “…It is said, however, that the plaintiffs have here only incurred a liability, and have made no payment. But I entirely deny that payment is necessary to entitle a party to recover. Liability alone is sufficient. It has always been customary to state, in the allegation of special damage, ‘whereby the plaintiff became liable to pay:’