“There be a preliminary issue to determine in respect of the Phase 1 Contract and the Phase II Contract to what extent, if at all, clause 4.3 of the Third Party’s standard terms and conditions of contract : a. formed part of the Third Party’s offer which was accepted by the Defendant; b. is enforceable as a matter of law; c. was revised and/or waived; d. cannot be relied upon by the Third Party by reason of estoppel.”
“4.3 Our maximum total liability is limited to the Contract Price; whether in contract or in tort, for any damage or loss whatsoever, including all direct, indirect or consequential loss.”
“We thank you for your recent enquiry and have pleasure in submitting our agreed offer of£100,000.00 net, as detailed in the attached documents. The programme is 3 days on site for the first visit starting early next week and 20 days for the second visit in mid July, with 5 weeks float. The current period of notice, which may vary from time to time, is two weeks. If this offer is of interest we look forward to visiting the site and agreeing terms etc before accepting an order.”
“Further to our recent discussions and your offer letter dated 27th June2001, we have pleasure in confirming your [sic] instruction to commence piling works at the above site on Monday2nd July 2001 . The agreed lump sum price to supply, pitch and drive a total of 641 piles to achieve the required loading capacity set out on the construction drawings passed to you at our meeting on Wednesday27th June 2001 , is£100,000 net. This price is based upon two visits to site only. Any additional visits will be subject to a mobilisation charge as set out in your lump sum schedule of£ 2,207.00 . For clarity, we confirm that you have received all AIG Borehole logs for this site, have made an assessment of likely pile depths for the scheme and as such bare (sic) all risks/retain all benefits associated with conditions varying from your initial assessment. The first visit to site is primarily to install piles to the three show-homes identified, however if at all possible we would request that you also install the associated piles (2-3 plots) in the area of the proposed Shepherd Homes compound area during this visit. The second visit will follow on within a maximum of two weeks from this point and will encompass the majority of the remaining works. Finally, as discussed we are proceeding with a “value engineering” exercise to reduce through design the number of piles necessary to complete these works. This will be an ongoing process and we confirm that any savings realised after additional design costs have been take into account will be shared equally between AIGR and Green Piling Ltd. I trust you will find the above satisfactory and look forward to working with you on what I hope will be a mutually successful project. Our formal order will be forwarded to you during the course of the next few days.”
“ - Steel piles – design issues - Connection detail – concrete + rebar” - Connection detail – concrete + rebar”
“We thank you for your order and confirm that the agreed start date, in accordance with the terms and conditions of our tender, was 3rd July. A copy of our Safety Plan together with letter of indemnity is enclosed as requested. We also confirm that we have PI cover for£1m in aggregate which we intended [sic] to keep in force for the next twelve years.”
“We hereby confirm that we will indemnify you and Hilton Jolly against your liabilities for the pile head design and enclose a sketch of the proposed detail.”
“Cover: Cover to indemnify the insured for any sum or sums which the insured may become legally liable to pay arising from any claim or claims first made against them and notified to the underwriters during the period of insurance stated in the schedule as a direct result of negligence on the part of the insured in the conduct and execution of the Professional Duties and Activities as defined Professional Activities and Duties. Design and specification… Supervision of construction Feasibility study Technical Information Calculation Surveying Limit of Indemnity£1,000,000 in the aggregate. Excess:£2,500 in respect of each and every claim or incident.”
“Further to your submissions for the quotation of piling as above please accept this letter as notice of our intention to place an order with you to pile a minimum of 10 number plots on week commencing5 August 2002 as discussed”
“Meaning of Notice. It is not necessary that the conditions contained in the standard form document should have been read by the person receiving it, or that he should have been made subjectively aware of their import or effect. The rules which have been laid down by the courts regarding notice in such circumstances are three in number: (1) If the person receiving the document did not know that there was writing or printing on it, he is not bound; (2) If he knew that the writing or printing contained or referred to conditions, he is bound. (3) If the party tendering the document did what was reasonably sufficient to give the other party notice of the conditions, and if the other party knew that there was writing or printing on the document, but did not know it contained conditions, then the conditions will become the terms of the contract between them.”
“Onerous or unusual terms. Although the party receiving the document knows it contains conditions, if the particular condition relied on is one which is a particularly onerous or unusual term, or is one which involves the abrogation of a right given by statute, the party tendering the document must show that it has been brought fairly and reasonably to the other’s attention. ‘Some clauses which I have seen’ said Denning LJ, ‘would need to be printed in red ink on the face of the document with a red hand point to it before the notice could be held to be sufficient’”
“..if one condition in a set of conditions is particularly onerous or unusual, the party seeking to enforce it must show that that particular condition was fairly brought to the attention of the other party”
“The tendency of the English authorities has, I think, been to look at the nature of the transaction in question and the character of the parties to it; to consider what notice the party alleged to be bound was given of the particular condition said to bind him, and to resolve whether in all the circumstances it is fair to hold him bound by the condition in question. This may yield a result not very different from the civil law principle of good faith…”
“…rejected a submission that for general words of incorporation to be effective a clause had to be well known and in common use and held that as a matter of general principle the question was whether the term was sufficiently unusual or uncommon so that it would be unfair in all the circumstances to hold the party to it…”
“found that clause 8 was not standard or customary, but in no sense unique.”
“…I am not persuaded that the Interfoto test applies to a term that is merely unusual, at any rate in the context of a binding incorporation clause. I acknowledge that some of the dicta in previous cases mention the case of a term that is “usual”, but Interfoto v Stiletto itself was concerned with a term which was not merely unusual but very onerous, unreasonable and extortionate. No one has suggested that those descriptions apply to cl. 8, however much it might increase the risk undertaken by an insurer…Lord Justice Dillon spoke of a term which is “particularly onerous or unusual (at 439A); and both he and Lord Justice Bingham went out of their way to stress the particular objections to the offending clause in that case”
“WARRANTY, LIMITATION OF LIABILITY AND NOTICE OF COMPLAINT (a) We warrant that we shall carry out the Works in a proper workmanlike manner based upon the information provided to us and in accordance with the knowledge and standards commonly available to and used by the building industry at the date of this Contract, All other warranties, except those given in writing and signed for an on behalf of the Company , whether purportedly express or implied (whether by statute or otherwise) in relation to the quality or fitness for purpose of the Works or in relation to our performance of the Contract are hereby expressly excluded. (b) Our liability under the Contract shall, except for liability for (i) death or personal injury due to negligence, and (ii) delay as specified in clause 6 above, be limited to the cost of remedial or rectification work (whether carried out by ourselves or a third party) on physical defect in the Works, such cost not to exceed the Contract Price (exclusive of VAT). All liability on our part for indirect or consequential loss or economic damage (including but not limited to loss of revenue or profit) is hereby expressly excluded.”
“6.6. Where any valid claim in respect of any of the Works and Materials which is based on any defect in the quality of Works or condition of the Materials or the failure to meet specification is notified to the Company in accordance with these Conditions the Company shall be entitled to repair the Works or replace the Materials (or the part in question) free of charge or at the Company’s sole discretion refund to the Customer the invoice price (or a proportionate part of the price) but the Company shall have no further liability to the Customer”
“4. WARRANTY 4.1. We warrant that we shall design and carry out the Works in a workmanlike manner and exercise reasonable skill and care in accordance with these terms and conditions. This warranty is in affect (sic) from the practical completion of the Works for a period of six years, providing the contract price had been paid in full and on time. …………………………………… UNFORSEEN GROUND CONDITIONS 10.1 If any physical conditions or obstructions are encountered which cause delay or additional costs and were not foreseen and not expressly allowed for in our Tender we will notify the Employer as soon as reasonably practicable. 10.2 Any associated addition (sic) work will be valued as a Variation. 10.3 We will be entitled to any extension of time for any delays arising from 10.1. above”
“For clarity, we confirm that you have received all AIG Borehole logs for this site, have made an assessment of likely pile depths for the scheme and as such bare (sic) all risks/retain all benefits associated with conditions varying from your initial assessment.”