“General Responsibilities: … 4. Provide information and consents promptly, and give written confirmation of the same promptly. … 7. Ensure that the sub-contractor has at all times such access to the purchaser’s business premises, computer software and other office facilities as is necessary to enable the sub-contractor to perform his obligations. 8. Ensure that all data and other information supplied and/or made available to the sub-contractor by or on the purchaser’s behalf is, unless drawn to the sub-contractor’s project manager’s attention in writing, complete and accurate in all respects. … Special Responsibilities: 1. Adhere to Schedule 5 (Time for Completion of Sub-Contract Works). …”
‘The existing DFA* mobilising system holds valuable data for loading gazetteer and PDA details. A data load utility [programme] will be provided to take data … provided by the Authority and construct part of the Gazetteer. The remaining gazetteer for CAMP East will be taken from Ordnance Survey Address Point data …’
‘… the percentage stated in the Appendix of the contract value It is worth noting at this point the definition of ‘contract value’, which is ‘such part of the contract price … as is properly attributable to the plant or work in question’: clause 1.1.i. of such parts of the works as cannot in consequence of the said failure be put to the use intended for each week between the time for completion and the actual date of completion [and that] the amount so deducted shall not exceed the maximum percentage stated in the Appendix of the contract value of such parts of the works …’
‘Insofar as the extension of time clause is ambiguous, it should be construed against the contractor.’
‘57. The third proposition however must be treated with care. It seems to me that, in so far as any extension of time clause is ambiguous, the court should lean in favour of a construction which permits the contractor to recover appropriate extensions of time in respect of events causing delay. This approach also accords with the principle of construction set out by Lewison in ‘The Interpretation of Contracts’ (3rd edition, 2004). That principle reads as follows: ‘Where two constructions of an instrument are equally plausible, upon one of which the instrument is valid and upon the other of which it is invalid, the court should lean towards that construction which validates the instrument.’ 58. That principle is supported by a line of authority as set out in paragraph 7.14 and is encapsulated in the Latin maxim verba ita sunt intelligenda, ut res magis valeat quam pereat.’
“I am bound to say that I see considerable force in Professor Wallace’ criticisms of Gaymark. I also see considerable force in the reasoning of the Australian courts in Turner and in Peninsula and in the reasoning of the Inner House in City Inn. Whatever may be the law of the Northern Territory of Australia, I have considerable doubt that Gaymark represents the law of England. Contractual terms requiring a contractor to give prompt notice of delay serve a valuable purpose; such notice enables matters to be investigated while they are still current. Furthermore, such notice sometimes give the employer the opportunity to withdraw instructions when the financial consequences become apparent. If Gaymark is good law, then a contractor could disregard with impunity any provision making proper notice a condition precedent. At his option the contractor could set time at large.”
‘It now appears to be accepted that a contractor is entitled to an extension of time notwithstanding the matter relied upon by the contractor is not the dominant cause of delay, provided only that it has equal ‘causative potency’ with all other matters causing delay [the footnote refers to Henry Boot Construction v Malmaison Hotel Manchester [1999] 70 Con LR 32]. The rationale for such an approach is that where the parties have expressly provided in their contract for an extension of time caused by certain events, the parties must be taken to have contemplated that there could be more than one effective cause of delay (one of which would not qualify for an extension of time) but nevertheless by their express words agreed that in such circumstances the contractor is entitled to an extension of time for an effective cause of delay falling within the relevant contractual provision.’