“The first date is to be agreed and thereafter on the same date in each month adjusted to the nearest working day in that month.” (b) Clause 30.3.1.2 provided that the Contractor should make Applications for Interim Payment as follows: “Where Alternative B applies, Applications for Interim Payment shall be made on the dates provided for in Alternative B in Appendix 2 and which date shall continue up to the day named in the Employer’s statement of Practical Completion or to within one month thereafter. Thereafter Application for Interim Payment shall be made as and when further amounts are due to the Contractor and after the expiration of the Defects Liability Period named in Appendix 1 or on the issue of the Notice or Completion of Making Good Defects (whichever is the later) provided that the Employer will not be required to make any Interim Payment within one calendar month of having made a previous Interim Payment.”
“We confirm we are preparing an account on Ringway’s behalf and we will forward this for your consideration when it is completed. It is the case however that Ringway completed the Works … in 2005. We understand it is not in issue that the total amended Purchase Order value is£3,190,686.00 and against this sum Walfords have certified and/or Vauxhall … have paid the total sum of£2,980,739.19 , giving a shortfall (and sum due) of£209,946.81 , excluding interest and VAT. We trust it is agreed that no retention should be withheld from any sum due at this date. We further understand that Walfords have informed Sue Cormack (Ringway’s Divisional Credit Controller) that no further certificate will be issued until the ‘claim’ is dealt with. Clearly such decision is not based upon a contractual provision and we would ask whether Vauxhall … have sanctioned such action/inaction on Walfords part, as certifiers under the Contract. For the avoidance of doubt Ringway will claim interest on any sum due, but not paid by Vauxhall … and we request you consider this matter further and issue a certificate, as a matter of urgency, to reduce any unnecessary items being presented.”
“We … would be grateful if you could inform us within 7 days as to whether or not a certificate will be issued/payment made in respect of the sum due of£209,946.81 (or other sums due), plus VAT. Please note that our client will claim interest on any unpaid/overdue sum(s). Please also note that if Ringway do not receive payment of the sum due in the next 7 days they will consider that a dispute has arisen and we are instructed to seek recovery of the said sum in adjudication proceedings, if necessary. …”
“We are pleased to see that there is now the opportunity to finally resolve the issue of this account … one would imagine your task of preparing an account for consideration may be a difficult one. In this letter I do not wish to go into the problems that were encountered, the delays incurred and who’s fault that may be, if necessary this can logged and further discussions take place, what I would say however is that we were trying to engage in a dialogue with Ringway into reaching an amicable settlement to the whole account. Meetings were held with Mr Tony Stevens and other Ringway Management staff and the ‘claim’ put forward by Ringway. This in the main has been rejected or further information requested. No further correspondence was ever received from Ringway. If this “open dialogue” is no longer to be the case our Client would have to review their previously very considerate actions in not invoking any Liquidated …Damages due under the contract from the late completion by the Contractor … In my brief telephone conversation with Sue Cormack I did not mean to imply that no further Certificate would be issued but presumed a final account/settlement could be reached relatively quickly and any balance of payment made accordingly. If you feel that this is not the case then we will value the works in accordance with the Contract and certify accordingly …”
“We note the statements in your letter regarding past “dialogue” that took place in respect of the resolution of Ringway’s account and state Mr Wood rang your office yesterday (after receipt of your letter) to re–enter (afresh) the dialogue with you with a view to understanding your client’s current position concerning the account and any sum accepted as due, together with the likelihood of an amicable and speedy settlement. Please contact Mr Wood on … to discuss the matter at any time.”
“We refer to the recent telephone conversations … and (notwithstanding your recent assurances) we note that as of 11.15 am today we have not received any response to the Interim Account No. 11, sent to you on 17May 2007. If it is your intention to send a valuation to us today, we would be grateful if it could be sent by facsimile to the above address and also sent to the offices of A L Lamb Associates Ltd … “Please note our client is concerned at the on–going delay to the valuation and the extended period for payment of the substantial sum due. On the basis of the previously started Order Value (£3.19M ) and the sum paid to date of£2.97m and on the basis that there will be a substantial increase in the Order Value in the light of our detailed application, we would be grateful if you could inform us when payment will be made by VM. Please note that our client reserves its position in respect of the interest on overdue payments. You also state that Ringway wish to seek an overall settlement of this account on a speedy/amicable basis, without the need to revert to adjudication proceedings and we would welcome the opportunity to meet with VM before such a position is reached. Please advise whether this is possible in the short term.”
“We have reviewed the information submitted, some of which has assisted us in being able to agree elements within the accounts. It will become self–evident upon your review of where we failed to agree your contractual understanding or valuation of the works. We also enclose our Employer’s Valuation No. 11. You will note that the Valuation is higher than the current order value and the Employer is currently checking the extent of orders raised. Will you please arrange for Ringway to submit their invoice to the Accounts Payable department in Barcelona? As we have previously discussed VM will obviously be keen to avoid adjudication if the account can be settled. Perhaps we should discuss this again once you have had a chance to review our response.”
“We refer to our previous discussions and confirm Ringway wish to settle the matter of the proper amount remaining due to it on an amicable basis and as soon as possible. In so far as we have not heard from you following your meeting on Thursday 5July 2007, Ringway suggests that the dispute is now decided by a neutral third party and append the names of three eminent civil engineers, with extensive experience in the adjudication of such matters. We would be grateful if you would concur in the name of one of the three named persons to act as adjudicator, to allow the resolution of this matter to be concluded, or otherwise inform us of any persons you suggest are suitable. We would be grateful for your reply to this request at your earliest convenience and by close of business on Wednesday 11July 2007.”
“Re: Adjudication between Ringway Highway Services Limited and Vauxhall Motors Limited in respect of a dispute arising out of works in the Vehicle Distribution Centre at Ellesmere Port and Ringway’s Interim Application No. 11 A dispute has arisen between the parties as to the proper sum due to Ringway Highway Services Limited, arising out of Interim Application No. 11, sent to Vauxhall Motors Limited’s representatives on16th May 2007 . We confirm the Parties are in agreement as to your appointment as adjudicator in this matter. The matter confirms the construction of a large (surface) vehicle distribution car parking and HGV area, together with an ancillary office building and the demolition of 3 No. buildings elsewhere on the Ellesmere Port site. The Contract Price was£3.1M and the amount sought by Ringway is some£4.25M . The amount in dispute is now approximately£1M . The dispute contains, inter alia, quantum and legal matters. We would be grateful if you would formally confirm you are willing and able to accept this appointment and provide the Parties/their representatives with a copy of your terms and conditions. We will forward the Notice of Adjudication and Referral Notice to you thereafter.”
“(1) The document sent on16th May 2007 was not an interim application within the meaning of the Contract. (2) The parties agreed that they would not adopt the contractual procedure and would instead seek to negotiate. Accordingly, by their agreement, Ringway disentitled itself from seeking to rely upon the operation of Clause 30.3. (3) By its conduct in discussing the account with Vauxhall, as particularised above, Ringway waived its entitlement to rely upon the provision of Clause 30.3. (4) By reason of the matters set out above, a common assumption arose between the parties that they would seek to negotiate the ultimate entitlement and would not resort to the procedures within Clause 30.3. In the circumstances it would be unjust to allow Ringway to resile from that common assumption.”
“In my view it is helpful to state or restate four basic principles: 1. The adjudication procedure does not involve the final determination of anybody’s rights (unless all the parties so wish) 2. The Court of Appeal has repeatedly emphasised that adjudicators’ decisions must be enforced, even if they result from errors of procedure, fact or law: see Bouygues, C&B Scene and Levolux. 3. Where an adjudicator has acted in excess of jurisdiction or in serious breach of the rules of natural justice, the court will not enforce his decision: see Discain, Balfour Beatty and Pegram Shopfitters. 4. Judges must be astute to examine technical defences with a degree of scepticism consonant with the policy of the 1996 Act. Errors of law, fact or procedure by an adjudicator must be examined critically before the Court accepts that such errors constitute excess of jurisdiction or serious breaches of the rules of natural justice: see Pegram Shopfitters and Amec.”
“The objective which underlies the Act and the statutory scheme requires the courts to respect and enforce the adjudicator’s decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should only be in rare circumstances that the courts will interfere with the decision of an adjudicator.”
“1. The word ‘dispute’ which occurs in many arbitration clauses and also in Section 108 of the Housing … Act should be given its normal meaning. It does not have some special or unusual meaning conferred upon it by lawyers. 2. Despite the simple meaning of the word ‘dispute’, there has been much litigation over the years as to whether or not disputes existed in particular situations. This litigation has not generated any hard–edged legal rules as to what is or is not a dispute. However, the accumulating judicial decisions have produced helpful guidance. 3. The mere fact that one party (whom I shall call ‘the claimant’) notifies the other party (whom I shall call ‘the respondent’) for the claim does not automatically and immediately give rise to a dispute. It is clear, both as a matter of language and from judicial decisions, that a dispute does not arise unless and until it emerges that the claim is not admitted. 4. The circumstances from which it may emerge so that a claim is not admitted are Protean. For example, there may be an expressed rejection of the claim. There may be discussions between the parties from which objectively it is to be inferred that the claim is not admitted. The respondent may prevaricate, thus giving rise to the inference that he does not admit the claim. The respondent may simply remain silent for a period of time, thus giving rise to the same inference. 5. The period of time for which a respondent may remain silent before a dispute is to be inferred depends heavily upon the facts of the case and the contractual structure. Where the gist of the claim is well known and it is obviously controversial, a very short period of silence may suffice to give rise to this inference. Where the claim is notified to some agent of the respondent who has a legal duty to consider the claim independently and then give a considered response, a longer period of time may be required before it can be inferred that mere silence gives rise to a dispute. 6. If the claimant imposes upon the respondent a deadline for responding to the claim, that deadline does not have the automatic effect of curtailing what would otherwise be a reasonable time for responding. On the other hand, a stated deadline and the reason for its imposing may be relevant factors when the court comes to consider what is a reasonable time for responding. 7. If the claim as presented by the claimant is so nebulous and ill–defined that the respondent cannot sensibly respond to it, neither silenced by the respondent nor even an expressed non–admission, it is likely to give rise to a dispute for the purposes of arbitration or adjudication.”
“I entirely accept that all depends on the circumstances of the particular case. I would, in particular, endorse the general approach that while the mere making of a claim does not amount to a dispute, a dispute will be held to exist once it can reasonably be inferred to that the claim is not admitted. I note that Jackson J does not endorse the suggestion in some of the cases, either that a dispute may not arise until negotiation or discussion has been concluded, or that a dispute should not be likely inferred. In my opinion he was right not to do so.”
“It appears to me that negotiation and discussion are likely to be more consistent with the existence of a dispute, albeit an as yet unresolved dispute, than with an absence of dispute. It also appears to me that court is likely to be willing readily to infer that a claim is not admitted and that a dispute exists so that it can be referred to arbitration or adjudication. I make these observations in the hope that they may be of some assistance and not because I detect any disagreement between them and the propositions advanced by Jackson J.”
“1. Clause 66 refers, not only to a ‘dispute’, but also to a ‘difference’. ‘Dispute or difference’ seems to me to be less hard–edged than ‘dispute’. This accords with the view of Danckwerts LJ in F&G Sykes v Fine Fare[1967] Lloyd's Rep 53 , at 60 where he contrasted a difference being a failure to agree, with a dispute. 2. In many instances, it will be quite clear that there is a dispute. In many of these, it may be sensible to suppose that the parties may not expect to challenge the engineer’s decision in subsequent arbitration proceedings. But major claims by either party are likely to be contested an arbitration may well be probable and necessary. Commercial good sense does not suggest that the clause should be construed with legalistic rigidity so as to impede the parties in starting timely arbitration proceedings. The whole clause should be read in this light. This leads me to lean in favour of an inclusive interpretation of what amounts to a dispute of difference.”
“An adjudicator derives his jurisdiction from his appointment. That appointment is governed by the statutory provisions of HGCRA which … require there to be a dispute that has already arisen between the parties to the construction contract. It follows that the appointing procedure must also relate to such a dispute. Thus, the notice of adjudication, the selection of a person to act as an adjudicator by an adjudicator nominating body; the indication from the selected adjudicator of his willingness to act; and the referral notice must all relate to the same pre–existing dispute. Any selection, acceptance of appointment or subsequent adjudication and decision which are not confined to that pre–existing dispute would be undertaken without jurisdiction.”
“The test in each case is first what dispute did the parties agree to refer to the adjudicator? And, secondly, on what basis? If the basis which is argued in the adjudication is wholly different to that which a defendant has had an opportunity to respond in advance to the adjudication, this may constitute a different dispute not referred to the adjudicator or, put another way, insofar as the adjudicator reaches a decision on the new issues it is not responsive to the issues referred to him.”
“seek to recover the net sum of£6,950.00 paid to their subcontractor plus an uplift of 10%. Ringway claim the total sum of£7,645.00 ”