“The contractor shall make applications for interim payments as follows”, and then it sets out the text of which applies in this case. 30.3.2: “Each application for interim payments shall be accompanied by such details as may be stated in the Employer’s Requirements”
“Not later than five days after the receipt of an application for payment, the Employer shall give a written notice to the Contractor specifying the amount of payment proposed to be made in respect of that application, the basis on which such amount is calculated and to what the amount relates”
“We have considered your submission and enclose our assessment and valuation together with our comments. You will see that we do not consider that a further payment to Rok Build is required and due under the contract. You will also see that it is our view that a payment of£8,487 is due to be paid by Rok Build to the Employer. Please accept this letter and contents as notices under clauses 30.3.3 and 30.3.4 of the Contract from the Employer.”
“Rok Build trading as Llewellyn Rok Centre, Guardian Road, Exeter Business Park, Exeter, the referring party (and referred to herein as ‘Rok’) hereby give notice to Harris Wharf Development Company of 13-15 New Burlington Place, Regent Street, the respondent (and referred to herein as ‘WHDC’) of its intention to refer a dispute that has arisen out of the construction contract to adjudication. The matter in dispute is the employer’s failure to comply with the requirements of clause 30.3.3 of the contract.”
“The dispute has arisen at the school”, and the date and the address is given. As to nature of the redress sought, it is put in these terms: “Rok seeks of the adjudicator a direction that the employer should comply with the requirements of clause 30.3.5 of the contract and to make payment of the amount stated”
“The referring party is Rok Build. The notice of intention to refer a dispute to adjudication identifies Rok Build Limited as trading as Llewellyn. The response documents served by Harris states that under the contract in dispute the contractor is described as Walter Llewellyn & Sons Limited. The reply for response, paragraph 1 states that the contract was amended to include Rok Build Limited’s address following the takeover of Walter Llewellyn & Sons Limited. The reply for response states the correspondence and previous payments have been addressed or made to Rok Build Limited. There are no further submissions on the identity of Rok Build save that the response to the referral cites the referring party as Rok Build Limited trading as Walter Llewellyn & Sons Limited.”
“Neither the employer nor the contractor shall without the written consent of the other assign this contract”
“It is helpful to state to restate four basic principles. The adjudication procedure does not involve the final examination of anybody’s rights unless all the parties so wish. 2. The Court of Appeal has repeatedly emphasised that adjudicator’s decisions must be enforced even if they result from errors, procedure, fact or at law.”
“3. Where an adjudicator has acted in excess of his jurisdiction or in serious breach of the rules of natural justice, the court will not enforce his decision. (See Discain, Balfour Beatty v. Pegram) “4. The judges must be astute to examine technical defences with a degree of scepticism consonant with the policy of 1996 Act. Errors of law fact or procedure by an adjudicator must be examined critically before the court accepts that such errors constitute excessive jurisdiction or serious breaches of the rules of natural justice.”
“1. The word dispute which occurs in many arbitration clauses and also in s.108 of the Housing Grants Act should be given its normal meaning. It does not have some special or unusual meaning conferred upon it by lawyers. “2. Despite the simple meaning of the word ‘dispute’ there has been much litigation over the years as to whether or not disputes existed in particular situations. This litigation has not generated any hard edged legal rules as to what is or is not a dispute. However, the accumulating judicial decisions have produced helpful guidance. “3. The mere fact one party whom I shall call ‘the claimant’ notifies the other party who I shall the ‘the respondent to the claim’ does not automatically and immediately give rise to a dispute. It is clear both as to a matter of language from judicial decisions that a dispute does not arise unless and until it emerges the claim is not admitted. “4. The circumstances from which it may emerge that a claim is not admitted are protean. For example, there may be an express rejection of the claim. There may be discussions between the parties from which objectively it is to be inferred that the claim is not admitted. The respondent may prevaricate, thus giving rise to the inference that he does not admit the claim. The respondent may simply remain silent for a period of time thus giving rise to the same inference. “5. The period of time for which a respondent may remain silent before a dispute is to be inferred depends heavily upon the facts of the case and the contractual structure. Where the gist of the claim is not well known and it is obviously controversial, a very short period of silence may suffice to give rise to this inference. Where the claim is notified to some agent of the respondent who has a legal duty to consider the claim independently and then give a considered response a longer period of time may be required before it can be inferred that mere silence gives rise to a dispute. “6. If the claimant imposes upon the respondent a deadline for responding to the claim that deadline does not have the automatic effect of curtailing what would otherwise be a reasonable time for responding. On the other hand, a stated deadline and the reason for its imposition may be relevant factors when the court comes to consider what is a reasonable time for responding. “7. If the claim as presented by the claimant is so nebulous and ill-defined that the respondent cannot sensibly respond to it, neither silence by the respondent nor even an express non-admission is likely to give rise to a dispute for the purposes of arbitration or adjudication.”
“For my part I would accept those propositions as broadly correct. I entirely accept that it all depends upon the circumstances of the particular case. I would in particular endorse the general approach that while the mere making of a claim does not amount to a dispute, a dispute will be held to exist once it can reasonably be inferred that a claim is not admitted. I note that Jackson J. does not endorse a suggestion in some of the cases either that the dispute may not arise until negotiation or discussion has been concluded or that a dispute should not be likely inferred.”
“As agreed at our meeting on Friday15th September 2006 and as subsequently discussed in our telephone conversation, I am arranging to transfer the sum of£100,000 on account of amounts which we anticipate will be due to you when outstanding works are completed. We trust that these outstanding works will now be put in hand. “Our understanding is that whilst meaningful negotiations are in progress on the final account you will not seek to enforce an adjudication decision given in your favour. Similarly and on the same basis, we will not take any unilateral action in respect of the final account notice which has been served. “We await hearing from you regarding mediation and hope that the differences between us have been amicably resolved.”
“The concept of a duty to carry on negotiations in good faith is inherently repugnant to the adversarial position of the parties when involved in negotiations. Each party to the negotiations is entitled to pursue his (or her) own interest so long as he avoids making misrepresentations. To advance that interest he must be entitled, if he thinks it is appropriate, to threaten to withdraw from further negotiations or to withdraw in fact, in the hope that the opposite party may seek to reopen negotiations by offering improved terms. Mr. Naughton, of course, accepts that the agreement upon which he relies does not contain a duty to complete the negotiations. “That still leaves needs the vital question - how is a vendor ever to know that he is entitled to withdraw from further negotiations? How is the court to ‘police’ such an agreement? A duty to negotiate in good faith is as unworkable in practice as it is inherently inconsistent with the position of a negotiating party. It is here that the uncertainty lies. In my judgment whilst negotiations are in existence either party is entitled to withdraw from these negotiations at any time for any reason. There can thus be no obligation to continue to negotiate until there is ‘a proper reason’ to withdraw. Accordingly, a bare agreement to negotiate has no legal content. Putting matters at its highest, this agreement is such a bare agreement.”